Question
Chapter 5, Problem 2MC
To determine
Concept introduction:
There are three types of costs according to the unit of production; Variable, Fixed and Mixed. Variable costs change proportionally with the number of units produced and variable cost per unit remains constant. Fixed Cost remains same in totality irrespective of the number of units produced.
The mixed cost is the mix of variable and fixed cost, some of its part is fixed and some variable.
To choose:
The correct option that is not a method to estimate the cost behavior
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Which of the following methods of cost estimation relies on only two data points?A. the high-low methodB. account analysisC. least-squares regressionD. SWOT analysis.
Obtaining regression estimates for cost estimation requires establishing the existence of a logical relation between activities and the cost to be estimated. Which of the following is not used to refer to these activities?
Multiple Choice
predictors.
dependent variables.
X terms.
independent variables.
12) Which of the following techniques is not used to analyze cost behavior?
A) Least-squares regression.
B) Visual-fit method.
O High-low method.
D) Multiple regression.
E) Linear programming.
Chapter 5 Solutions
Managerial Accounting
Ch. 5 - Define each of the following terms variable cost,...Ch. 5 - Prob. 2QCh. 5 - Prob. 3QCh. 5 - Prob. 4QCh. 5 - Prob. 5QCh. 5 - Describe the three methods used to estimate cost...Ch. 5 - Prob. 7QCh. 5 - Prob. 8QCh. 5 - Prob. 9QCh. 5 - Prob. 10Q
Ch. 5 - Prob. 11QCh. 5 - Prob. 12QCh. 5 - Prob. 13QCh. 5 - Prob. 14QCh. 5 - Which of the following increases when activity...Ch. 5 - Prob. 2MCCh. 5 - Prob. 3MCCh. 5 - Consider the following information for a local...Ch. 5 - Prob. 5MCCh. 5 - Prob. 6MCCh. 5 - Prob. 7MCCh. 5 - Prob. 8MCCh. 5 - Prob. 9MCCh. 5 - Hathaway Corp, manufactures garden hoses. Last...Ch. 5 - Identifying Cost Behavior Heather Oak is trying to...Ch. 5 - Prob. 2MECh. 5 - Defining Cost Behavior Match each of the following...Ch. 5 - Prob. 4MECh. 5 - Defining Terms for the High-Low Method Indicate...Ch. 5 - Prob. 6MECh. 5 - Prob. 7MECh. 5 - Prob. 8MECh. 5 - Prob. 9MECh. 5 - Prob. 10MECh. 5 - Prob. 11MECh. 5 - Prob. 12MECh. 5 - Prob. 13MECh. 5 - Prob. 14MECh. 5 - Prob. 15MECh. 5 - Prob. 16MECh. 5 - Compare full absorption costing to variable...Ch. 5 - Identifying Cost Behavior Patterns Steve...Ch. 5 - Prob. 2ECh. 5 - Prob. 3ECh. 5 - Prob. 4ECh. 5 - Estimating Cost Behavior Using High-Low Method...Ch. 5 - Prob. 6ECh. 5 - Prob. 7ECh. 5 - Prob. 8ECh. 5 - Prob. 9ECh. 5 - Estimating Cost Behavior Using Scattergraph and...Ch. 5 - Estimating Cost Behavior Using Least-Squares...Ch. 5 - Comparing High-Low Method and Least-Squares...Ch. 5 - Preparing Contribution Margin Income Statement...Ch. 5 - Determining Cost Behavior, Preparing Contribution...Ch. 5 - Prob. 15ECh. 5 - Prob. 16ECh. 5 - Prob. 17ECh. 5 - Prob. 18ECh. 5 - Comparing Full Absorption Costing and Variable...Ch. 5 - Estimating Cost Behavior Using Least-Squares...Ch. 5 - Prob. 1.1GAPCh. 5 - Prob. 1.2GAPCh. 5 - Prob. 1.3GAPCh. 5 - Prob. 1.4GAPCh. 5 - Prob. 1.5GAPCh. 5 - Prob. 1.6GAPCh. 5 - Prob. 2.1GAPCh. 5 - Prob. 2.2GAPCh. 5 - Prob. 2.3GAPCh. 5 - Prob. 2.4GAPCh. 5 - Prob. 2.5GAPCh. 5 - Prob. 2.6GAPCh. 5 - Prob. 2.7GAPCh. 5 - Prob. 3.1GAPCh. 5 - Prob. 3.2GAPCh. 5 - Prob. 3.3GAPCh. 5 - Prob. 3.4GAPCh. 5 - Prob. 3.5GAPCh. 5 - Prob. 4.1GAPCh. 5 - Prob. 4.2GAPCh. 5 - Prob. 4.3GAPCh. 5 - Comparing Full Absorption and Variable Costing...Ch. 5 - Comparing Full Absorption and Variable Costing...Ch. 5 - Prob. 5.3GAPCh. 5 - Prob. 6.1GAPCh. 5 - Prob. 6.2GAPCh. 5 - Prob. 6.3GAPCh. 5 - Prob. 6.4GAPCh. 5 - Prob. 6.5GAPCh. 5 - Prob. 6.6GAPCh. 5 - Prob. 1.1GBPCh. 5 - Prob. 1.2GBPCh. 5 - Prob. 1.3GBPCh. 5 - Prob. 1.4GBPCh. 5 - Estimating Cost Behavior Using Scattergraph,...Ch. 5 - Prob. 1.6GBPCh. 5 - Prob. 2.1GBPCh. 5 - Estimating Cost Behavior Using Scattergraph,...Ch. 5 - Prob. 2.3GBPCh. 5 - Prob. 2.4GBPCh. 5 - Prob. 2.5GBPCh. 5 - Prob. 2.6GBPCh. 5 - Prob. 2.7GBPCh. 5 - Prob. 3.1GBPCh. 5 - Prob. 3.2GBPCh. 5 - Prob. 3.3GBPCh. 5 - Prob. 3.4GBPCh. 5 - Prob. 3.5GBPCh. 5 - Prob. 4.1GBPCh. 5 - Prob. 4.2GBPCh. 5 - Prob. 4.3GBPCh. 5 - Prob. 5.1GBPCh. 5 - Prob. 5.2GBPCh. 5 - Prob. 5.3GBPCh. 5 - Prob. 6.1GBPCh. 5 - Prob. 6.2GBPCh. 5 - Prob. 6.3GBPCh. 5 - Prob. 6.4GBPCh. 5 - Prob. 6.5GBPCh. 5 - Prob. 6.6GBP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Explain how the high-low method is used for cost estimation. What, if any, are the limitations of this approach to cost estimation?arrow_forwardWhich of the following statements related to cost estimation methods is true ? a . Only high -low method has a slope and an intercept . b. The scatter - graph method is used to derive an estimated line of cost behavior by graphically connecting the two cost amounts identified with the highest and lowest volume levels . c. The most complex method of cost estimation is the high - low method . d. The least -squares regression method is the most accurate and reliable method to determine the cost behavior compared to scatter -graph plot and high -low methods . e. None of the given answersarrow_forward12) Which of the following techniques is not used to analyze cost behavior? A) Least-squares regression. B) Visual-fit method. C) High-low method. D) Multiple regression. E) Linear programming.arrow_forward
- Which of the following statements related to cost estimation methods is false? a. The least-squares regression method is the most accurate and reliable method to determine the cost behavior compared to scatter-graph plot and high-low methods. O b. The low-high method is used to derive an estimated line of cost behavior by graphically connecting the two cost amounts identified with the highest and lowest volume levels. O c. The most complex method of cost estimation is the high-low method. O d. None of the given answers. O e. The three methods determine a slope and an intercept.arrow_forwardFrom the standpoint of cost control, why is the FIFO method superior to the weighted-averagemethod?arrow_forwardWhich of the following statements related to cost estimation methods is true? O a. The low-high method is used to derive an estimated line of cost behavior by graphically connecting the two cost amounts identified with the highest and lowest volume levels. O b. The high-low method is the most accurate and reliable method to determine the cost behavior compared to scatter-graph plot and least-squares regression methods. O c. None of the given answers. O d. Only high-low method has a slope and an intercept. e. The most complex method of cost estimation is the high-low method.arrow_forward
- Which of the following is NOT true of regression techniques for estimating costs? a) They permit the inclusion of more than one predictor. b) They typically use the highest and lowest activity points to estimate the relation between cost and activity. c) They help develop estimates that have a broader base than those based on a few select points. d) They are designed to generate a line that best fits a set of data points.arrow_forwardWhich of the following statements related to cost estimation methods is true? O a. The most complex method of cost estimation is the high-low method. O b. The high-low method is the most accurate and reliable method to determine the cost behavior compared to scatter-graph plot and least-squares regression methods. O c. The low-high method is used to derive an estimated line of cost behavior by graphically connecting the two cost amounts identified with the highest and lowest volume levels. O d. Only high-low method has a slope and an intercept. O . None of the given answers.arrow_forward_____Identifying the relationship between the activity and the costs is a key step in which of the following cost estimation methods? a) Scattergraph. b) High-low method. c) Linear regression. d) Account analysis.arrow_forward
- From the standpoint of cost control, why is the FIFO method superior to the weighted-averagemethod? Is it possible to monitor cost trends using the weighted-average method?arrow_forwardWhich of the following statements related to cost estimation methods is false? O a. The most complex method of cost estimation is the high-low method. The low-high method is used to derive an estimated line of cost behavior by graphically connecting the two cost amounts identified with the highest and lowest volume levels. None of the given answers. O d. The least-squares regression method is the most accurate and reliable method to determine the cost behavior compared to scatter-graph plot and high-low methods. e. The three methods determine a slope and an intercept.arrow_forwardWhich of the following statements related to cost estimation methods is false? The least-squares regression method is the most accurate and reliable method to determine the cost behavior compared to scatter-graph plot and high-low methods. O b. The low-high method is used to derive an estimated line of cost behavior by graphically connecting the two cost amounts identified with the highest and lowest volume levels. The three methods determine a slope and an intercept. O d. None of the given answers. The most complex method of cost estimation is the high-low method.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegePrinciples of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage LearningCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
How to Estimate Project Costs: A Method for Cost Estimation; Author: Online PM Courses - Mike Clayton;https://www.youtube.com/watch?v=YQ2Wi3Jh3X0;License: Standard Youtube License