Construction Accounting And Financial Management (4th Edition)
4th Edition
ISBN: 9780135232873
Author: Steven J. Peterson MBA PE
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Question
Chapter 4, Problem 9P
To determine
Ascertain the estimated cost at completion of project and variance for each cost.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
9. A contractor has a contract to remove and replace the existing landscape and sidewalks around an office building. The work includes demolition of the existing landscaping and sidewallks, importing fill and grading around the office building, constructing new concrete sidewalks, and new landscaping. The contractor uses the cost codes in Figure 2-6. The contractor will perform all of the work except placing the site concrete and the landscaping. The original estimate for the demolition was $30,000, and a $5,000 change order has been approved to remove some unexpected debris found during the demolition. The demolition work has been completed at a cost of $33,562. The original estimate for the fill and grading was $17,500 and a $2,000 change order for importing additional fill to replace the debris has been approved. The fill and grading costs to date are $17,264, and the estimated cost to complete has been estimated at $2,236. The original budget for the labor to pour the concrete was…
Jax Construction Company plans to erect a new building. It will use part of the space for its own offices and lease the balance of the space to tenants. The company has two alternatives: (1) do its own construction work or (2) use an independent contractor.
Cost estimates have been prepared to show the costs of operation for the coming year during which the new building will be constructed. The costs of constructing the building, if done by Jax, are included in that set of estimates.
If the company does its own construction work, it will not be able to handle outside construction contracts that would contribute $500,000 to net income. The costs attributable to these outside contracts are excluded from the estimated costs of operation shown below.
Estimated Costs toOperate –Construction byIndependentContractors
Estimated Costs toOperate (includingConstruction) –Construction by Jax(self)
Materials
$6,000,000
$7,000,000
Labour
3,000,000
4,800,000
Indirect materials and…
In connection with surfacing a new highway, a contractor has a choice of two sites on which to set up the asphalt-
mixing plant equipment. The contractor estimates that it will cost $1.25 per cubic yard mile (yd³ -mile) to haul the
asphalt-paving material from the mixing plant to the job location. Factors relating to the two mixing sites are as
follows:
Cost Factor
Average hauling distance
Monthly rental of site
Cost to set to and remove
equipment
Hauling expense
Flagperson
Site A
6 miles
$1,200
$17,000
$1.25 / yd³ -mile
Not required
Site B
4.3 miles
$5,500
$25,000
$1.25 / yd³ -mile
$96 / day
The job requires 50,000 cubic yards of mixed-asphalt-paving material. It is estimated that four months (17 weeks of
five working days per week) will be required for the job. Compare the two sites in terms of their total costs. Assume
that the cost of the return trip is negligible. A) Which is the better site? B) For the selected site, how many cubic
yards of paving material does the contractor…
Chapter 4 Solutions
Construction Accounting And Financial Management (4th Edition)
Ch. 4 - Define committed costs and provide two examples of...Ch. 4 - Why is labor seldom a committed cost?Ch. 4 - Prob. 3DQCh. 4 - What are overbillings and how do they occur?Ch. 4 - Prob. 5DQCh. 4 - What are the six key principals of internal...Ch. 4 - What should you look for in a construction...Ch. 4 - Prob. 8PCh. 4 - Prob. 9PCh. 4 - Prob. 10P
Knowledge Booster
Similar questions
- 8. A contractor has a contract to construct the sanitary sewer, water line, storm drain, and street lighting for a new subdivision. The contractor uses the cost codes in Figure 2-6. The original estimate for the sewer was $25,000, and a $3,200 change order has been approved to add a manhole. The sewer work has been completed by the contractor at a cost of $27,365. The original estimate for the waterline was $31,000, and no changes have been made to the budget. The costs to date for the waterline are $31,300 and it is estimated that it will take another $450 to complete the waterline. The water line is being installed by the contractor. The original estimate for the storm drain was $17,000, and no changes have been made to the budget. The contractor has paid $7,236 for materials and estimates that it will cost $9,764 to install the storm drain. The contractor will install the storm drain. The original estimate for the outside lighting was $23,600, and no changes have been made to the…arrow_forwardIvanhoe Co. purchased land as a factory site for $520,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $54,600 to raze the old buildings and sold salvaged lumber and brick for $8,190. Legal fees of $2,405 were paid for title investigation and drawing the purchase contract. Ivanhoe paid $2,860 to an engineering firm for a land survey, and $88,400 for drawing the factory plans. The land survey had to be made before definitive plans could be drawn. Title insurance on the property cost $1,950, and a liability insurance premium paid during construction was $1,170. The contractor's charge for construction was $3,562,000. The company paid the contractor in two installments: $1,560,000 at the end of 3 months and $2,002,000 upon completion. Interest costs of $221,000 were incurred to finance the construction. Determine the cost of the land and the cost of the building as they should be recorded on the books of…arrow_forwardQuestion 9. A contractor has a contract to remove and replace the existing landscape and sidewalks around an office building. The work includes demolition of the existing landscaping and sidewallks, importing fill and grading around the office building, constructing new concrete sidewalks, and new landscaping. The contractor uses the cost codes in Figure 2-6. The contractor will perform all of the work except placing the site concrete and the landscaping. The original estimate for the demolition was $30,000, and a $5,000 change order has been approved to remove some unexpected debris found during the demolition. The demolition work has been completed at a cost of $33,562. The original estimate for the fill and grading was $17,500 and a $2,000 change order for importing additional fill to replace the debris has been approved. The fill and grading costs to date are $17,264, and the estimated cost to complete has been estimated at $2,236. The original budget for the labor to pour the…arrow_forward
- Martini Company incurred the following costs in purchasing a land as a factory site:Purchase price 2,400,000Cost of tearing down old building 240,000Legal fee for title investigation 15,000Title insurance 10,000 Architect fee 125,000Liability insurance during construction 25,000Excavation cost 40,000Payment to building contractor 8,800,000Special assessment by city for public improvement 30,000Interest cost during construction 300,000 What is the cost of the building?arrow_forwardMartin Buber Co. purchased land as a factory site for $400,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $42,000 to raze the old buildings and sold salvaged lumber and brick for $6,300. Legal fees of $1,850 were paid for title investigation and drawing the purchase contract. Martin Buber paid $2,200 to an engineering firm for a land survey, and $68,000 for drawing the factory plans. The land survey had to be made before definitive plans could be drawn. Title insurance on the property cost $1,500, and a liability insurance premium paid during construction was $900. The contractor’s charge for construction was $2,740,000. The company paid the contractor in two installments: $1,200,000 at the end of 3 months and $1,540,000 upon completion. Interest costs of $170,000 were incurred to finance the construction. Instructions Determine the cost of the land and the cost of the building as they should be recorded…arrow_forwardMartin Buber Co. purchased land as a factory site for $400,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $42,000 to raze the old buildings and sold salvaged lumber and brick for $6,300. Legal fees of $1,850 were paid for title investigation and drawing the purchase contract. Martin Buber paid $2,200 to an engineering firm for a land survey, and $68,000 for drawing the factory plans. The land survey had to be made before definitive plans could be drawn. Title insurance on the property cost $1,500, and a liability insurance premium paid during construction was $900. The contractor’s charge for construction was $2,740,000. The company paid the contractor in two installments: $1,200,000 at the end of 3 months and $1,540,000 upon completion. Interest costs of $170,000 were incurred to finance the constructionarrow_forward
- Sage Reclaimers entered into a contract with Pronghorn Demolition to manage the processing of recycled materials on Pronghorm various demolition projects. Services for the 3-year contract include collecting, sorting, and transporting reclaimed materials to recycling centers or contractors who will reuse them. Sage incurs selling commission costs of $2,180 to obtain the contract. Before performing the services, Sage also designs and builds receptacles and loading equipment that interfaces with Pronghorn demolition equipment at a cost of $25,100. These receptacles and equipment are retained by Sage and can be used for other projects. Pronghorn promises to pay a fixed fee of $12,850 per year, payable every 6 months for the services under the contract. Sage incurs the following costs: design services for the receptacles to interface with Pronghorn equipment $3,220, loading equipment controllers $6,400, and special testing and OSHA inspection fees $2,180 (some of Pronghorn projects are on…arrow_forwardThe Madison Sign Company purchased land as a factory site for $75,000. Prior to construction of the new building, the land had to be cleared of trees and brushConstruction costs incurred during the first year are listed belowarrow_forwardCala Manufacturing purchases land for $259,000 as part of its plans to build a new plant. The company pays $26,400 to tear down an old building on the lot and $39,026 to fill and level the lot. It also pays construction costs $1,220,600 for the new building and $77,048 for lighting and paving a parking area. Prepare a single journal entry to record these costs incurred by Cala, all of which are paid in cash.arrow_forward
- Rex's Reclaimers entered into a contract with Dan's Demolition to manage the processing of recycled materials on Dan's various demolition projects. Services for the 3-year contract include collecting, sorting, and transporting reclaimed materials to recycling centers or contractors who will reuse them. Rex's incurs selling commission costs of $2,000 to obtain the contract. Before performing the services, Rex's also designs and builds receptacles and loading equipment that interfaces with Dan's demolition equipment at a cost of $27,000. These receptacles and equipment are retained by Rex's and can be used for other projects. Dan's promises to pay a fixed fee of $12,000 per year, payable every 6 months for the services under the contract. Rex's incurs the following costs: design services for the receptacles to interface with Dan's equipment $3,000, loading equipment controllers $6,000, and special testing and OSHA inspection fees $2,000 (some of Dan's projects are on government…arrow_forwardRex's Reclaimers entered into a contract with Dan's Demolition to manage the processing of recycled materials on Dan's various demolition projects. Services for the 3-year contract include collecting, sorting, and transporting reclaimed materials to recycling centers or contractors who will reuse them. Rex's incurs selling commission costs of $2,000 to obtain the contract. Before performing the services, Rex's also designs and builds receptacles and loading equipment that interfaces with Dan's demolition equipment at a cost of $27,000. These receptacles and equipment are retained by Rex's and can be used for other projects. Dan's promises to pay a fixed fee of $12,000 per year, payable every 6 months for the services under the contract. Rex's incurs the following costs: design services for the receptacles to interface with Dan's equipment $3,000, loading equipment controllers $6,000, and special testing and OSHA inspection fees $2,000 (some of Dan's projects are on government…arrow_forwardSheffield Co. purchased land as a factory site for $536,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $56,280 to raze the old buildings and sold salvaged lumber and brick for $8,442. Legal fees of $2,479 were paid for title investigation and drawing the purchase contract. Sheffield paid $2,948 to an engineering firm for a land survey, and $91,120 for drawing the factory plans. The land survey had to be made before definitive plans could be drawn. Title insurance on the property cost $2,015, and a liability insurance premium paid during construction was $1,206. The contractor's charge for construction was $3,671,600. The company paid the contractor in two installments: $1,608,000 at the end of 3 months and $2,063,600 upon completion. Interest costs of $227,800 were incurred to finance the construction. Determine the cost of the land and the cost of the building as they should be recorded on the books of…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education