Construction Accounting And Financial Management (4th Edition)
Construction Accounting And Financial Management (4th Edition)
4th Edition
ISBN: 9780135232873
Author: Steven J. Peterson MBA PE
Publisher: PEARSON
Question
Book Icon
Chapter 4, Problem 8P
To determine

Ascertain the estimated cost at completion of project and variance for each cost.

Blurred answer
Students have asked these similar questions
9. A contractor has a contract to remove and replace the existing landscape and sidewalks around an office building. The work includes demolition of the existing landscaping and sidewallks, importing fill and grading around the office building, constructing new concrete sidewalks, and new landscaping. The contractor uses the cost codes in Figure 2-6. The contractor will perform all of the work except placing the site concrete and the landscaping. The original estimate for the demolition was $30,000, and a $5,000 change order has been approved to remove some unexpected debris found during the demolition. The demolition work has been completed at a cost of $33,562. The original estimate for the fill and grading was $17,500 and a $2,000 change order for importing additional fill to replace the debris has been approved. The fill and grading costs to date are $17,264, and the estimated cost to complete has been estimated at $2,236. The original budget for the labor to pour the concrete was…
Alpine Company solicited bids from several contractors to construct an addition to its office building. The lowest bid received was for $1,200,000. Alpine decided to construct the addition itself at a cost of $1,100,000. What amount should be recorded in the building account?
Jax Construction Company plans to erect a new building. It will use part of the space for its own offices and lease the balance of the space to tenants. The company has two alternatives: (1) do its own construction work or (2) use an independent contractor. Cost estimates have been prepared to show the costs of operation for the coming year during which the new building will be constructed. The costs of constructing the building, if done by Jax, are included in that set of estimates. If the company does its own construction work, it will not be able to handle outside construction contracts that would contribute $500,000 to net income. The costs attributable to these outside contracts are excluded from the estimated costs of operation shown below.   Estimated Costs toOperate –Construction byIndependentContractors Estimated Costs toOperate (includingConstruction) –Construction by Jax(self) Materials $6,000,000  $7,000,000 Labour  3,000,000 4,800,000 Indirect materials and…
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
CONCEPTS IN FED.TAX., 2020-W/ACCESS
Accounting
ISBN:9780357110362
Author:Murphy
Publisher:CENGAGE L