Question
Chapter 3, Problem 39P
a)
Summary Introduction
To determine: The way the company can minimize the cost of meeting the month’s requirement.
Introduction: In linear programming, the unbounded solution would occur when the objective function is infinite. If no solution satisfied the constraints, then it is said to be an unfeasible solution.
b)
Summary Introduction
To investigate: The effect on the total cost of two simultaneous changes.
Introduction: In linear programming, the unbounded solution would occur when the objective function is infinite. If no solution satisfied the constraints, then it is said to be an unfeasible solution.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
A manufacturing plant produces a product 'A' that requires one unit of 'B' and ½ unit of 'C'. Each unit of 'B' is comprised of one unit of 'D', two units of 'E', and one unit of 'F'. Each unit of 'C' requires ½ unit of 'G' and three units of 'H'. The manufacturing lead times for the components are as follows: 'A' - two weeks, 'B' - one week, 'C' - two weeks, 'D' - two weeks, 'E' - three weeks, 'F' - one week, 'G' - two weeks, 'H' - one week. There are 20 units in stock for each of these components. 100 units of 'A' are needed for delivery in seven weeks: a) Develop the product structure and indexed bill of materials for the product. b) Create a gross and net requirements plan for the manufacturer of the product.
Company ZWZ manufactures three products in a serial system; Product XA is manufactured in Stage 1, Product XB in Stage 2, and XC in Stage 3. Product XB has a sales potential in the market; hence, some of it can be sold at the end of Stage 2, and
the remaining can be moved to Stage 3. The third stage produces Product XC, and then delivers it to customers. Two units of Product XA produced in Stage 1 are required for each unit of Product XB in Stage 2. In addition, four units of Product XB
produced in Stage 2 are required for each unit of Product XC in Stage 3.
Stage 1 can only use regular time; however, Stage 2 has the options of using regular time and overtime in manufacturing. On the other hand, Stage 3 has only one alternative, which is subcontracting. The pertinent data are provided below:
Stage 2
Stage 1
11
No overtime
No
subcontracting
No sales
0.07
Unit regular time cost (TL)
Unit overtime cost (TL)
Unit subcontracting cost (TL)
Unit selling price (TL)
Unit processing time (hrs)…
Because of its labor contract, a company must hire enough labor for 100 units ofproduction per week on one shift or 200 units per week on two shifts. It cannot hire,lay off, or assign overtime. During the fourth week, workers will be available fromanother department to work part or all of an extra shift (up to 100 units). There is aplanned shutdown for maintenance in the second week, which will cut production tohalf. Develop a production plan. The opening inventory is 200 units, and the desiredending inventory is 300 units
Chapter 3 Solutions
Practical Management Science
Ch. 3.6 - Prob. 1PCh. 3.6 - Prob. 2PCh. 3.6 - Prob. 3PCh. 3.6 - Prob. 4PCh. 3.6 - Prob. 5PCh. 3.6 - Prob. 6PCh. 3.6 - Prob. 7PCh. 3.6 - Prob. 8PCh. 3.6 - Prob. 9PCh. 3.7 - Prob. 10P
Ch. 3.7 - Prob. 11PCh. 3.7 - Prob. 12PCh. 3.7 - Prob. 13PCh. 3.7 - Prob. 14PCh. 3.7 - Prob. 15PCh. 3.7 - Prob. 16PCh. 3.7 - Prob. 17PCh. 3.8 - The Pigskin Company produces footballs. Pigskin...Ch. 3.8 - The Pigskin Company produces footballs. Pigskin...Ch. 3.8 - The Pigskin Company produces footballs. Pigskin...Ch. 3.8 - Prob. 21PCh. 3.8 - Prob. 22PCh. 3.8 - Prob. 23PCh. 3.8 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 26PCh. 3 - Prob. 27PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Prob. 31PCh. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 34PCh. 3 - Prob. 35PCh. 3 - Prob. 36PCh. 3 - Prob. 37PCh. 3 - Prob. 38PCh. 3 - Prob. 39PCh. 3 - Prob. 40PCh. 3 - Prob. 41PCh. 3 - Prob. 42PCh. 3 - Prob. 43PCh. 3 - Prob. 44PCh. 3 - Prob. 45PCh. 3 - Prob. 46PCh. 3 - Prob. 47PCh. 3 - Prob. 48PCh. 3 - Prob. 49PCh. 3 - Prob. 50PCh. 3 - Prob. 51PCh. 3 - Prob. 52PCh. 3 - Prob. 1C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Production and Materials Purchases Budgets White Corporation’s budget calls for the following sales for next year:Quarter 1 90,000 units Quarter 3 68,000 unitsQuarter 2 76,000 units Quarter 4 96,000 unitsEach unit of the product requires 3 pounds of direct materials. The company’s policy is to begineach quarter with an inventory of product equal to 5% of that quarter’s estimated sales requirementsand an inventory of direct materials equal to 20% of that quarter’s estimated direct materials requirements for production.Required Determine the production and materials purchases budgets for the second quarter.arrow_forwardRoedel Electronics produces tablet computer accessories, including integrated keyboard tablet stands that connect a keyboard to a tablet device and holds the device at a preferred angle for easy viewing and typing. Roedel produces two sizes of integrated keyboard tablet stands, small and large. Each size uses the same keyboard attachment, but the stand consists of two different pieces, a top flap and a vertical stand that differ by size. Thus, a completed integrated keyboard tablet stand consists of three subassemblies that are manufactured by Roedel: a keyboard, a top flap, and a vertical stand. Roedel's sales forecast indicates that 7,000 small integrated keyboard tablet stands and 5,000 large integrated keyboard tablet stands will be needed to satisfy demand during the upcoming Christmas season. Because only 500 hours of in-house manufacturing time are available, Roedel is considering purchasing some, or all, of the subassemblies from outside suppliers. If Roedel manufactures a…arrow_forwardRoedel Electronics produces tablet computer accessories, including integrated keyboard tablet stands that connect a keyboard to a tablet device and holds the device at a preferred angle for easy viewing and typing. Roedel produces two sizes of integrated keyboard tablet stands, small and large. Each size uses the same keyboard attachment, but the stand consists of two different pieces, a top flap and a vertical stand that differ by size. Thus, a completed integrated keyboard tablet stand consists of three subassemblies that are manufactured by Roedel: a keyboard, a top flap, and a vertical stand. Roedel's sales forecast indicates that 7,000 small integrated keyboard tablet stands and 5,000 large integrated keyboard tablet stands will be needed to satisfy demand during the upcoming Christmas season. Because only 500 hours of in-house manufacturing time are available, Roedel is considering purchasing some, or all, of the subassemblies from outside suppliers. If Roedel manufactures a…arrow_forward
- ) The following data have been prepared for master production scheduling purposes in IKEA Australia: End product A: Beginning inventory of 60, Period forecast of 10, Lot size of 30, and 30 hours in lot size. End product B: Beginning inventory of 20, Period forecast of 5, Lot size of 20, and 20 hours in lot size. End product C: Beginning inventory of 30, Period forecast of 15, Lot size of 50, and 50 hours in lot size. Capacity: 38 hours/ week (i) Prepare the master production schedule for these items during the next four periods using the Ethan Allen master production scheduling method. (ii) Suppose that the master production schedule is frozen for the next three periods. What specific impact would the policy have on the IKEA's performance?arrow_forwardA manufacturing firm has four plants and wants to find the most efficient means of meeting the requirements of its four customers. The relevant information for the plants and customers, along with shipping costs in dollars per unit, are shown in the table below: Customer (requirement) Factory (capacity) Customer 1 (125) Customer 2 (150) Customer 3 (175) Customer 4 (75) A (100) $ 15 $ 10 $ 20 $ 17 B (75) $ 20 $ 12 $ 19 $ 20 C (100) $ 22 $ 20 $ 25 $ 14 D (250) $ 21 $ 15 $ 28 $ 12 How many arcs will the network have?arrow_forwardA manufacturing firm has four plants and wants to find the most efficient means of meeting the requirements of its four customers. The relevant information for the plants and customers, along with shipping costs in dollars per unit, are shown in the table below: Customer (requirement) Factory (capacity) Customer 1 (125) Customer 2 (150) Customer 3 (175) Customer 4 (75) A (100) $ 15 $ 10 $ 20 $ 17 B (75) $ 20 $ 12 $ 19 $ 20 C (100) $ 22 $ 20 $ 25 $ 14 D (250) $ 21 $ 15 $ 28 $ 12 How many supply nodes are present in this problem? Multiple Choice: 4 3 1 8 16arrow_forward
- A manufacturing firm has four plants and wants to find the most efficient means of meeting the requirements of its four customers. The relevant information for the plants and customers, along with shipping costs in dollars per unit, are shown in the table below: Customer (requirement) Factory (capacity) Customer 1 (125) Customer 2 (150) Customer 3 (175) Customer 4 (75) A (100) $ 15 $ 10 $ 20 $ 17 B (75) $ 20 $ 12 $ 19 $ 20 C (100) $ 22 $ 20 $ 25 $ 14 D (250) $ 21 $ 15 $ 28 $ 12 Note: This question requires Solver.Formulate the problem in Solver and find the optimal solution. What is the optimal quantity to ship from Factory B to Customer 3? Multiple Choice 25 units 50 units 75 units 100 units 125 unitsarrow_forwardThe Fly-Right Airplane Company builds small jet airplanes to sell to corporations for use by their executives. To meet the needs of these executives, the company's customers sometimes order a custom design of the airplanes being purchased. When this occurs, a substantial start-up cost is incurred to initiate the production of these airplanes. Fly-Right has recently received purchase requests from three customers with short deadlines. However, because the company's production facilities already are almost completely tied up filling previous orders, it will not be able to accept all three orders. Therefore, a decision now needs to be made on the number of airplanes the company will agree to produce (if any) for each of the three customers. The relevant data are given in the next table. The first row gives the start-up cost required to initiate the production of the airplanes for each customer. Once production is under way. the marginal net revenue (which is the purchase price minus the…arrow_forwardAn order for 200 units of a product is processed on work centers A and B. The set up time on A is 45 minutes and the run time is 5 minutes per piece. The set up time on B is 40 minutes and the run time is 8 minutes per piece. The wait time between the two operations is 2 hours. The move time between A and B is 15 minutes. Wait time after operation B is 1 hour and the move time into stores is 50 minutes. There is no queue at either work station. Calculate the total manufacturing lead time for the order.arrow_forward
- A producer has three products, A, B, and C, which are composed from many of the same raw materials and subassemblies by the same skilled workforce. Each unit of product A uses 15 units of Raw Material X, one Purge System Subassembly, one Case, one Power Cord, three Labour Hours in the Assembly Department, and one Labour Hour in the Finishing Department. Each unit of product B uses 10 units of Raw Material X, five units of Raw Material Y, two Purge System Subassemblies, one Case, one Power cord, five Labour Hours in the Assembly Department, and 90 minutes in the Finishing Department. Each unit of product C uses five units of Raw Material X, 25 units of Raw Material Y, two Purge System Subassemblies, one Case, a Power Cord, seven Labour Hours in the Assembly Department, and Three Labour Hours in the Finishing Department. Labour between the Assembly and Finishing departments is not transferable, but workers within each department work on any of the three products. There are three…arrow_forwardA producer has three products, A, B, and C, which are composed from many of the same raw materials and subassemblies by the same skilled workforce. Each unit of product A uses 15 units of Raw Material X, one Purge System Subassembly, one Case, one Power Cord, three Labour Hours in the Assembly Department, and one Labour Hour in the Finishing Department. Each unit of product B uses 10 units of Raw Material X, five units of Raw Material Y, two Purge System Subassemblies, one Case, one Power cord, five Labour Hours in the Assembly Department, and 90 minutes in the Finishing Department. Each unit of product C uses five units of Raw Material X, 25 units of Raw Material Y, two Purge System Subassemblies, one Case, a Power Cord, seven Labour Hours in the Assembly Department, and Three Labour Hours in the Finishing Department. Labour between the Assembly and Finishing departments is not transferable, but workers within each department work on any of the three products. There are three…arrow_forwardRoedel Electronics produces tablet computer accessories, including integrated keyboard tablet stands that connect a keyboard to a tablet device and hold the device at a preferred angle for easy viewing and typing. Roedel produces two different sizes of integrated keyboard tablet stands, small and large. Each size uses the same keyboard attachment, but the stand consists of two different pieces, a top flap and a vertical stand that differ by size. Thus, a completed integrated keyboard tablet stand consists of three subassemblies that are manufactured by Roedel: a keyboard, a top flap and a vertical stand. Roedel's sales forecast indicates that 7,000 small integrated keyboard tablet stands and 5,000 large integrated keyboard tablet stands will be needed to satisfy demand during the upcoming Christmas season. Because only 500 hours of in-house manufacturing time are available, Roedel is considering purchasing some, or all, of the subassemblies from outside suppliers. If Roedel…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,