Question

Give typed full explanation 

The City Commission of Nashville has decided to build a botanical garden and picnic area in the
heart of the city for the recreation of its citizens. The precedence table for all the activities required
to construct this area successfully is as follows:
Code Description
A
B
Find location, determine resource
requirements
Requisition of lumber and sand
C
Dig and grade
D
Saw lumber into appropriate sizes
E Position lumber in correct locations
F
G
H
모
Time
(hrs)
25
28282828
65
95
30
20
10
Nail lumber together
Put sand in and under the equipment
Put dirt around the equipment
Put grass all over the garden, landscape, 25
paint
20
10
Immediate Predecessor(s)
None
A
A
B
D. C
E
F
F
G, H
Refer to the legend for the activity that corresponds to each code
Using the line drawing tool, draw a Gantt chart for activities E through I of the project.
8-
0
D
E
H
0-
(110,5)
20 40 60 80 100 120 140 160 180 200
Transcribed Image Text:The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: Code Description A B Find location, determine resource requirements Requisition of lumber and sand C Dig and grade D Saw lumber into appropriate sizes E Position lumber in correct locations F G H 모 Time (hrs) 25 28282828 65 95 30 20 10 Nail lumber together Put sand in and under the equipment Put dirt around the equipment Put grass all over the garden, landscape, 25 paint 20 10 Immediate Predecessor(s) None A A B D. C E F F G, H Refer to the legend for the activity that corresponds to each code Using the line drawing tool, draw a Gantt chart for activities E through I of the project. 8- 0 D E H 0- (110,5) 20 40 60 80 100 120 140 160 180 200
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,