Some tasks and the order in which they must be performed according to their assembly requirements are shown in the following table. These are to be combined into workstations to create an assembly line. The assembly line operates 8 hours per day. The output requirement is 900 units per day. TASK A B с D E F PRECEDING TASKS A A B B C TIME (SECONDS) 18 12 22 Workstation cycle time 8 Work Station I || III IV V VI 13 14 a. What is the workstation cycle time? TASK G H I 3 K L Task PRECEDING TASKS с D E F, G H, I J, K seconds per unit TIME (SECONDS) 18 b. Balance the line using the longest task time rule based on the 900-unit forecast, stating which tasks would be done in each workstation. (Leave no cells blank - be certain to enter "0" wherever required.) Idle Time 9 11 14 5 10

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section4.8: Data Envelopment Analysis (dea)
Problem 42P
icon
Related questions
Question

Note:-

  • Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism.
  • Answer completely.
  • You will get up vote for sure.
c. What is the efficiency of your line balance? (Round your answer to 1 decimal place.)
Efficiency
%
d. After production was started, Marketing realized that they understated demand and must increase output to 1,000 units. There are
two options: reduce cycle time or work overtime. Please identify the following: (Round your answers to the nearest whole number.)
cycle time to
seconds or work
minutes of overtime.
Transcribed Image Text:c. What is the efficiency of your line balance? (Round your answer to 1 decimal place.) Efficiency % d. After production was started, Marketing realized that they understated demand and must increase output to 1,000 units. There are two options: reduce cycle time or work overtime. Please identify the following: (Round your answers to the nearest whole number.) cycle time to seconds or work minutes of overtime.
Problem 6-17 (Algo)
Some tasks and the order in which they must be performed according to their assembly requirements are shown in the following table.
These are to be combined into workstations to create an assembly line. The assembly line operates 8 hours per day. The output
requirement is 900 units per day.
TASK
A
B
с
D
E
F
PRECEDING
TASKS
A
A
B
B
с
Workstation cycle time
TIME
(SECONDS)
18
12
22
8
13
14
a. What is the workstation cycle time?
Work Station
I
||
III
IV
V
VI
TASK
G
H
I
J
K
L
Task
PRECEDING
TASKS
C
D
E
F, G
H, I
J, K
seconds per unit
TIME
(SECONDS)
18
9
b. Balance the line using the longest task time rule based on the 900-unit forecast, stating which tasks would be done in each
workstation. (Leave no cells blank - be certain to enter "0" wherever required.)
Idle Time
11
14
5
10
Transcribed Image Text:Problem 6-17 (Algo) Some tasks and the order in which they must be performed according to their assembly requirements are shown in the following table. These are to be combined into workstations to create an assembly line. The assembly line operates 8 hours per day. The output requirement is 900 units per day. TASK A B с D E F PRECEDING TASKS A A B B с Workstation cycle time TIME (SECONDS) 18 12 22 8 13 14 a. What is the workstation cycle time? Work Station I || III IV V VI TASK G H I J K L Task PRECEDING TASKS C D E F, G H, I J, K seconds per unit TIME (SECONDS) 18 9 b. Balance the line using the longest task time rule based on the 900-unit forecast, stating which tasks would be done in each workstation. (Leave no cells blank - be certain to enter "0" wherever required.) Idle Time 11 14 5 10
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 6 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,