Below matrix shows one of the important data used in project management, identify the name of the matrix and explain the roles of each person involved in this matrix. Total= 10 marks Facilities Plant Mgr HR Security Project Mgr Identify a minimum of three asphalt contractors from Angie's List Arrange for contractor visits and quotes Review quotes and references, R R A make contractor selection Review and finalize contract, lock in plant shutdown week Communicate project to shutdown maintenance crew, make sure all R vehicles are removed from the lot Provide security gate access codes for asphalt crew by June 15 A R Oversee the project during the plant shutdown week, ensure it is A R. completed on time R= Responsible, A = Accountable, C = Consulted, I = Informed

MARKETING 2018
19th Edition
ISBN:9780357033753
Author:Pride
Publisher:Pride
Chapter6: Target Markets: Segmentation And Evaluation
Section: Chapter Questions
Problem 4SC
icon
Related questions
icon
Concept explainers
Topic Video
Question
Part 1:
Below matrix shows one of the important data used in project management, identify the name
of the matrix and explain the roles of each person involved in this matrix.
Total= 10 marks
Facilities
Plant Mgr
HR
Security Project Mgr
Identify a minimum of three asphalt
R
contractors from Angie's List
Arrange for contractor visits and
quotes
Review quotes and references,
A
R
make contractor selection
Review and finalize contract, lock in
plant shutdown week
R
Communicate project to shutdown
maintenance crew, make sure all
R
vehicles are removed from the lot
Provide security gate access codes
for asphalt crew by June 15
A
Oversee the project during the plant
shutdown week, ensure it is
A
R
completed on time
R = Responsible, A = Accountable, C = Consulted, I = Informed
Transcribed Image Text:Part 1: Below matrix shows one of the important data used in project management, identify the name of the matrix and explain the roles of each person involved in this matrix. Total= 10 marks Facilities Plant Mgr HR Security Project Mgr Identify a minimum of three asphalt R contractors from Angie's List Arrange for contractor visits and quotes Review quotes and references, A R make contractor selection Review and finalize contract, lock in plant shutdown week R Communicate project to shutdown maintenance crew, make sure all R vehicles are removed from the lot Provide security gate access codes for asphalt crew by June 15 A Oversee the project during the plant shutdown week, ensure it is A R completed on time R = Responsible, A = Accountable, C = Consulted, I = Informed
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
MARKETING 2018
MARKETING 2018
Marketing
ISBN:
9780357033753
Author:
Pride
Publisher:
CENGAGE L