3.8 Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a num- ber of activities that must be completed before a training program of this nature could be conducted. The activities, immediate pre- decessors, and times appear in the accompanying table: a)  DrawtheappropriateAONPERTdiagramforJ.C.Howard’s management team. b)  Find the critical path. c)  What is the project completion time? • • 3.11 The following is a table of activities associated with a project at Rafay Ishfaq’s software firm in Chicago, their dura- tions, and what activities each must precede: ACTIVITY DURATION (WEEKS) PRECEDES A (start) 1 B, C B 1 E C 4 F E 2 F F (end) 2 — ACTIVITY IMMEDIATE PREDECESSOR(S) TIME (DAYS) A — 2 B — 5 C — 1 D B 10 E A, D 3 F C 6 G E, F 8 a)  Develop an AON network for this problem. b)  What is the critical path? c)  What is the total project completion time? d)  What is the slack time for each individual activity?

Management, Loose-Leaf Version
13th Edition
ISBN:9781305969308
Author:Richard L. Daft
Publisher:Richard L. Daft
Chapter7: Planning And Goal Setting
Section: Chapter Questions
Problem 2ED
icon
Related questions
icon
Concept explainers
Topic Video
Question

3.8 Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a num- ber of activities that must be completed before a training program of this nature could be conducted. The activities, immediate pre- decessors, and times appear in the accompanying table:

  1. a)  DrawtheappropriateAONPERTdiagramforJ.C.Howard’s management team.

  2. b)  Find the critical path.

  3. c)  What is the project completion time?

• • 3.11 The following is a table of activities associated with a project at Rafay Ishfaq’s software firm in Chicago, their dura- tions, and what activities each must precede:

ACTIVITY

DURATION (WEEKS)

PRECEDES

A (start)

1

B, C

B

1

E

C

4

F

E

2

F

F (end)

2

ACTIVITY

IMMEDIATE PREDECESSOR(S)

TIME (DAYS)

A

2

B

5

C

1

D

B

10

E

A, D

3

F

C

6

G

E, F

8

  1. a)  Develop an AON network for this problem.

  2. b)  What is the critical path?

  3. c)  What is the total project completion time?

  4. d)  What is the slack time for each individual activity?

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 6 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Management, Loose-Leaf Version
Management, Loose-Leaf Version
Management
ISBN:
9781305969308
Author:
Richard L. Daft
Publisher:
South-Western College Pub
Foundations of Business (MindTap Course List)
Foundations of Business (MindTap Course List)
Marketing
ISBN:
9781337386920
Author:
William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:
Cengage Learning
Foundations of Business - Standalone book (MindTa…
Foundations of Business - Standalone book (MindTa…
Marketing
ISBN:
9781285193946
Author:
William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:
Cengage Learning