A maintenance building construction project also includes an external electrical generator and water tank. The first activity is to excavate which requires two weeks. Following excavation, the maintenance building will be built, and then both the generator and the water tank can be installed. These three activities, building, generator, and tank, require six, four, and two weeks, respectively. Once this set of three activities is completed, the tank and generator can be connected to the building, an activity that requires five weeks. After the maintenance building is built, maintenance equipment can also be installed inside the building and this activity takes four weeks. Painting the maintenance building is also required, following its construction, and this takes three weeks. Finally, after the maintenance equipment is installed and the connection is completed, it will take two weeks to inspect the new maintenance facility.
Q: Define the terms main product, joint product, and byproduct. Give at least one example of each type…
A: Main Product: A main product is a product that is the primary focus of a production process, and it…
Q: Quality Management and Patient Safety into the Organization Define credentialing and explain why…
A: In a healthcare organization, credentialing refers to the following:
Q: As Dunn writes on p. 66, "Millennials represent a growing portion of the workforce. These…
A: Millennials in the workforce, it's particularly critical to comprehend the manner in which they…
Q: Zara stores in the United States stocks a particular type of designer denim jeans in the United…
A: Decision Variables: Suppose- X be the no. of jeans purchased from the Hong Kong supplierY the no. of…
Q: A manufacturing company preparing to build a new plant is considering three potential locations for…
A: Total cost crossover point can be caculate the unit sale point which is equal for both models. The…
Q: The members want to know how many of each item they should bake to maximize the money they make.
A: It is believed that the invention of linear programming was a major step forward for mankind since…
Q: How do you explain a technique used to analyze the quantitative data for resolving either a personal…
A: Statistical analysis is a powerful tool for analyzing quantitative data and can help individuals and…
Q: An automatic filling machine is used to fill 1-liter bottles of cola. The machine's output is…
A: Given- Mean = 0.93 litersStandard deviation (SD) = 0.02 litersSample size (n) = 29
Q: Which of these exponential smoothing models should be used, and what smoothing parameters should be…
A: The given data in terms of Demand has a trend , hence Double Exponential Smoothing is the most…
Q: When making a network adjustment at a big company, how do you typically get approval?
A: The process for getting approval for a network adjustment at a big company can vary depending on the…
Q: Types of Information Pollution?
A: Information pollution is consider to large amount of information which generated and distributed…
Q: Businesses are often faced with operational risks and decisions must be made to alleviate such…
A: In the business world, operational risk is always lurking around the corner. Employee actions,…
Q: Why IKEA’s Operations Model Is So Successful Operations management is an essential part of the…
A: The world's most significant and most valuable furniture retail business is a Swedish firm called…
Q: What are the factors that influence conflict between individuals in organizations and how do they…
A: There are several factors that could influence conflict between individuals in a firm, further,…
Q: Demonstrate how credit risk management issue can be resolved through the application of a The…
A: Credit risk management is an important concern for financial institutions as it involves the risk of…
Q: Talk about your thoughts around the dangers of assuming during the business definition phase. What…
A: Each project's success depends on clearly grasping its goals, specifications, and limitations. At…
Q: A company's biggest vulnerability in employing a best-cost provider strategy is A) getting trapped…
A: The best-cost provider strategy is a competitive approach where a company tries to offer a product…
Q: Why would a security manager prefer to hire an outside organisation to undertake research rather…
A: Security operations can be defined as the continuous exercises and cycles that are set up to…
Q: Do you agree that it's crucial, while in a management job, to break down a project into smaller,…
A: Work breakdown structure is a kind of diagram that provide a visual and hierarchical disintegration…
Q: What are the differences between in-house e-commerce development with packaged solutions and service…
A: In-house e-commerce development refers to the process of building an e-commerce platform or website…
Q: Philip Nelson owns a fireworks store. Philip's fixed costs are $10,000 a month, and each fireworks…
A: To find: (a) The break even point. (b) The new break even point. (c) The indifference points.…
Q: The Barberton Municipal division of Road Maintenance is charged with road repair in the city of…
A: Find the Calculation methods below: Regular Production = Working hours * WorkersOutput Forecast =…
Q: 5. Solve for the scheduling data for the following site improvement project. Compute the relevant…
A: A network diagram shows the sequence of the various tasks that are connected to complete a project.…
Q: Find out what percentage of time each day is spent on the five functions of a supervisor (e.g.,…
A: Let us assume that 100% of the time is actually split up into multiple sections of one day which is…
Q: You have recently accepted the position of director for a full-service retirement home that has…
A: Thank you for bringing up these important questions, my assistant. As the new director, my priority…
Q: A company is adopting a new human resource information system that uses cloud computing. In which…
A: A cloud-based human resource information system can be defined as a device that permits associations…
Q: can you make an operations management analysis for this forecasting
A: The forecasting problem at Sanderson Produce Co. (SPC) involves predicting the quarterly demand for…
Q: Describe the use of a hardball negotiation tactic in a big telecom business. Include the following…
A: Below is the use of a hardball negotiation tactic in a big telecom business:
Q: As discussed in the course, suggest four (4) ways the group can attain a sustainable competitive…
A: The four ways that group can attain a sustainable competitive advantage: Low-cost leadership…
Q: At a fashion retailer, there are 3 cashiers providing checkout service simultaneously. On average,…
A: No. of servers (s) = 3Arrival rate (λ) = 6 min per customer = 606= 10 customers per hourService rate…
Q: Analyze the pros and cons of using a Work Breakdown Structure against a Product Breakdown Structure.
A: It is very important to breakdown the task and activities which is related to the project. Work…
Q: Discuss how a mountain bike maker can reduce consumer's perceived risks related to the product.
A: Perceived risk is a significant factor in consumer decision-making. When consumers purchase…
Q: Can you create a Quantitative Strategic Planning Matrix (QSPM) for a travel agency which offers an…
A: Below is how you can create a Quantitative Strategic Planning Matrix (QSPM) for a travel agency that…
Q: Make a list of ideas for a home office that may be used for telecommuting.
A: Below are the list of ideas for a home office that may be used for telecommuting:
Q: Explain the factors affecting compensation on firm’s financial conditions, workers productivity and…
A: The capacity of a firm to recruit, retain, and inspire its personnel is directly impacted by…
Q: Discjss what are some potential disadvantages of using a packaged application to help automate the…
A: Packaged applications, also known as off-the-shelf software, are pre-built software applications…
Q: Question 1: Which of the following best defines " stockout costs"? options: A) They are physical…
A: Stockout costs allude to the costs caused by a business when it runs unavailable or inventory of a…
Q: Suppose your manager presents you with the following information about machines that could be used…
A: Given: Machine Cost per unit($) Standard Deviation (mm) Specification Width(mm) A 12 0.062 0.48…
Q: The coefficient of variation for inter-arrival times of customers arriving at a sandwich shop is…
A: Given that, inter-arrival times of customers arriving at a sandwich shop is equal to 3.
Q: FAO-Funded Aquaponics Project Launched In Barbados Barbados GIS – The United Nations Food and…
A: A collection of conditions or demands must be satisfied for a project to be deemed successful and…
Q: Explain why it might be argued that the formulation of a company’s strategy is the responsibility of…
A: The formulation of a company's strategy is a complex process that involves setting the overall…
Q: examine the term settlement in the context of industrial relation
A: Below is the explanation of the term settlement in the context of industrial relation:
Q: Please elaborate on the significance of matching product requirements to production approaches
A: The laid-out product development process of the production is for the most part not coordinated in…
Q: Thank you for the comprehensive answer and I agree with the methodology and the answer it produced.…
A: Objective Functions and Constraints: Based on the given details, the objective…
Q: A manufacturing company preparing to build a new plant is considering three potential locations for…
A: Since you have asked multiple question, we will solve the first question for you. If you want any…
Q: You may argue that its importance to corporate operations makes it a must-have. While developing…
A: Introduction: In today's world, software has become an integral part of business operations. From…
Q: How do service firms' supply networks vary from manufacturing organizations' chains?
A: Planning, organizing, and regulating resources is a part of operations management, which helps…
Q: PROJECT A Project A is a planning, design and implementation infrastructure development project…
A: As instructed, Question 1C is only answered. Project management is a field of study where specific…
Q: To Russia with love Jan de Rover sat back in his chair, his feet resting on the piles of paperwork…
A: The above case study is about Russian Bribes and its impact on business. A bribe is an illegal…
Q: Just what is performance testing, and where do the bottlenecks lie?
A: Below is the definition of performance testing and its bottlenecks:
A. $25,000
B. $450,000
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images
- Mike’s Auto Body Shop has five cars waiting to be repaired. The shop is quite small, so only one car can be repaired at a time. The number of days required to repair each car and the promised date for each are given in the following table. (given) Mike has agreed to provide a rental car to each customer whose car is not repaired on time. Compare the performance of the four sequencing rules FCFS, SPT, EDD, and CR relative to minimizing average tardiness.Suppose we have a school building project. According to the breakdown structure, twenty work packages were constructed for this project. The seventh work package is the plumbing process, and this work package needs to be done within 4 weeks. The required number of hours to complete the plumbing processes is 420 hours. The total working hours per day, in general, is 8 hours and 7 working days were assumed for each week. The total available time for each plumber per week is 15 hours. Find the required number of plumbers for the 4 weeks. 5 plumbers 1 plumber 7 plumbers 6 plumbersA B1 B2 B3 C1 C2 C3 D1 D2 D3 E A service process is described by the above flowchart. After going through workstation A, an order needs to be processed by one of the three lines, B1-C1-D1, B2-C2-D2, or B3-C3-D3 (in other words, they are substitutable). Finally, all orders need to go through workstation E. The capacities of the individual workstations are given as follows: Workstation A has a capacity of 3 orders/hour • Workstation B1, B2, and B3 have the same capacity of 4 orders/hour • Workstation C1, C2, and C3 have the same capacity of 3 orders/hour • Workstation D1, D2, and D3 have the same capacity of 4 orders/hour • Workstation E has a capacity of 6 orders/hour What is process time of this service process in minutes?
- A manutacturer is designing a product layout for a new product production. It plans to use a production line for B hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 lasks in total. These tasks are namely, A, 8, CD, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed Starting tasks Cneeds, the tack B to be completed. Also, starting task D needed task B to be completed Task E can only start upon completion of Task C. Whescas starting lask F needs the completion of both the tasks D and E Finally, starting task G needed, task Fto be completed. 1the processing times for tasks, A BC D, E F, andG are 28, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks nule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the FIRST workstation are Select one OaAB, and C ODAB Oc None…The following jobs are waiting to be processed at Rick Solano’s machine center. Solano’s machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs received during the previous 2 weeks. They are ready to be scheduled today, which is day 241 (day 241 is a workday). Job names refer to names of clients and contract numbers. Job Date job received Productiondays needed Date job due BR-02 228 15 300 CX-01 225 25 270 DE-06 230 35 320 RG-05 235 40 360 SY-11 231 30 310 a. Complete the following table. (Show your supporting calculations.) b.Which dispatching rule has the best score for flow time? c. Which dispatching rule would you select? Support your decision.A small maintenance project consists of the following jobs, whose precedence relationships are given below.
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 150 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting taskD needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.3, 2.1,0.9, 1.0, 1.2, 1.8, and 1.5 minutes respectively. Applying the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first. What will be the idle time for the LAST Workstation? O a. 1.7 O b. None is the…A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1,0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. What should be the (calculated) cycle time in minutes? O a. 4.8 Ob. 4.4 None is the correct answer O d. 0.9 O e. 4.5A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 150 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.4, 2.2,0.9, 1.0, 1.2, 1.8, are 1.5 minutes respectively. How many minimum numbers of workstations are needed? Round-up to the nearest integer а. 8 b. 4 С. 6 O d. 5 O e. None is the correct answer
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and Gare 2.8, 2.1,0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. How many minimum numbers of workstations are needed? Select one: O a.2 O b. None is the correct answer O c.6 O d. 8 O e. 4A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the SECOND workstation are Select one: Oa. B and…A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks rule for balancing the assembly line with ties broken according to longest task time first, the tasks that will be assigned to the SECOND workstation are: a. B,C and D b. C…