University of Illinois Urbana Champaign Assignment
Department of Civil and Environmental Engineering Fall2023
CEE 422 Construction Cost Analysis
Assignment # 1
(Rough Estimating and Cost Indexes)
"I pledge to uphold the CEE Honor Code.”
Mohammed Mujthaba Ajazul Haq
ulhaq3@illinois.edu
Q 1) Exercise 1 (3 points)
Over 7 years ago your company built a restaurant in New London, Connecticut. It was completed
in 2016 with a total cost of $4,940,000. You were awarded a contract for a similar restaurant.
(Almost same design) that you are building this year (2023) in Daytona Beach, Florida. a) What is the estimated cost of the restaurant? b) If in 2020 you had built a similar restaurant in Decatur, Illinois, what would have been the
cost of it?
Solution
: -
a)
DAYTONA BEACH, FLORIDA.
1)
Time adjustment using the Historical Cost Indexes
INDEX New London, Connecticut: - 207.3
INDEX Daytona Beach, Florida: - 318.8
Cost in Year A = Cost in Year B X Index A
Index B
I assumed the basic cost of restaurant of New London, Connecticut 2016 $4940000
= 4940000 = x X 207.3
318.8
= $7597067.035
2)
Location adjustment using the City Cost Indexes:
City A Cost (Unknown) = City B Cost (Known) X City A Index
City B Index
= x = 7597067.035 X 87.9
101.4
= $6585623.21
Assignment # 1 – Solution Page | 1
University of Illinois Urbana Champaign Assignment
Department of Civil and Environmental Engineering Fall2023
CEE 422 Construction Cost Analysis
b) DECATUR, ILLINOIS
1)
Time adjustment using the Historical Cost Indexes
INDEX New London, Connecticut: - 207.3
INDEX Decatur, Illinois: - 234.6
Cost in Year A = Cost in Year B X Index A
Index B
= 4940000 = x X 207.3
234.6
= $5590564.399
2)
Location adjustment using the City Cost Indexes:
City A Cost (Unknown) = City B Cost (Known) X City A Index
City B Index
= x =5590564.399 X 101.2
101.4
= $5579537.645
Assignment # 1 – Solution Page | 2
University of Illinois Urbana Champaign Assignment
Department of Civil and Environmental Engineering Fall2023
CEE 422 Construction Cost Analysis
Q 2) Exercise 2 (3 points)
You are doing a rough cost estimate for a warehouse. The estimated gross area of the warehouse is 210,000 sf. You have historical cost data from similar previous projects (shown below). Based on these data, what is your estimate for this warehouse? State which estimating method you have
used.
Project
Total Project Cost Size (sf) 1
$46,478,500 223000
2
$13,609,300 96500
3
$23,087,100 100960
4
$12,107,360 65500
5
$38,645,500 176000
6
$31,266,510 193000
Solution
: -
Project
Total Project Cost Size (sf) Cost Per Square ft
1
$46,478,500 223000
$
208.42
2
$13,609,300 96500
$
141.03
Smallest Unit Cost
3
$23,087,100 100960
$
228.68
Largest Unit Cost
4
$12,107,360 65500
$
184.85
5
$38,645,500 176000
$
219.58
6
$31,266,510 193000
$
162.00
Formula: - UC = A
+
4
B
+
C
6
UC = forecast unit cost of proposed project
A = minimum unit cost of previous projects
B = average unit cost of previous projects
C = maximum unit cost of previous projects
Average: - ∑ (Unit Cost)/total no of Projects =
1144.56
6
= 190.7
Assignment # 1 – Solution Page | 3
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Related Questions
27 - please show complete solution, thanks!
arrow_forward
Complete solution, please. Thanks!
arrow_forward
A contract to build a 2-storey residential building is awarded to you. A Notice to Proceed (NTP) is given to you in 7 days. List down at least 10 activities you are going to do to start the project on time and explain each relevant activity.
arrow_forward
show solution thanks!
arrow_forward
pls answer full solution. thanks
.
arrow_forward
please show complete solution thanks. last 30 minutes left
arrow_forward
! I need a quick solution within 15 minutes With my best wishesTon
arrow_forward
Engr-429 Construction Management
1. Given the following construction progress chart, calculate the weekly cumulative progress
through the end of week 5, and show the curve on the chart. The total project labor hours is
33,985, the percent complete shown is actual progress for each activity. You must calculate
the weight of each activity.
Shows planned schedule
Shows actual progress
Operation
1. Clear and
Grubbing
2. Drainage
3. Subgrade
5. Pave
6. Testing
Hours Wt.
7. Striping
1625
4. Base Course 8125
405
8745
14005
280
500
8. Punch List 400
SCH
ACT
SCH
ACT
SCH
ACT
SCH
ACT
SCH
ACT
SCH
ACT
SCH
ACT
SCH
ACT
1
10
2
40
30
15
3
80
160
30
4
100
100
55
Weeks
5
6
15
85
40
15
Fall 2023
7 8 9 10
The individual weight is simply the percentage the activity represents of the total project labor
hours.
100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
arrow_forward
I need solution in 15 minutese please
arrow_forward
Question 48
schedule is a schedule in which the resources for a project are assigned to activities so the activities can be closely monitored.
O resource-loaded
O time-loaded
A
look-ahead
O preliminary
amazon
Bcer
F12
Scr Lk
Artêtdéf
PrtSclimpréc
SysRg/Syst.
F4
F5
F6
F7
F8
F9
F10
F11
Bre
VA
arrow_forward
Q5/ The structural engineering design section within the engineering
department of a regional electrical utility corporation has developed
several standard designs for a group of similar transmission line towers.
The detailed design for each tower is based on one of the standard designs.
A transmission line project involving 50 towers has been approved. The
estimated number of engineering hours needed to accomplish the first
detailed tower design is 126. Assuming a 95% learning curve,
a. What is your estimate of the number of engineering hours needed to
design the eighth tower and to design the last tower in the project?
b. What is your estimate of the cumulative average hours required for the
first five designs?
arrow_forward
Using the same CPM diagram, what is the total project duration?
Immediate
Estimated
Activity
Activity Description
Predecessors
Duration
A
Excavate
2 weeks
Lay the foundation
Put up the rough wall
Put up the roof
Install the exterior plumbing
Install the interior plumbing
Put up the exterior siding
Do the exterior painting
B
A
4 weeks
C
10 weeks
D
C
6 weeks
4 weeks
5 weeks
7 weeks
9 weeks
7 weeks
8 weeks
4 weeks
E
C
F
E
G
D
E, G
Do the electrical work
F, I
Put up the wallboard
Install the flooring
Do the interior painting
Install the exterior fixtures
K
5 weeks
M
2 weeks
N
Install the interior fixtures
K, L
6 weeks
Total = 79 weeks
arrow_forward
Case study badly needed asap. I will rate helpful.
arrow_forward
please show complete solution. last 30 minutes left.. thank you!
arrow_forward
Construction problems and solutions
SITUATION 2: You are within two weeks of
turnover of a three-story build-to-suit office
building project. Many of the city inspections
are complete and it appears that a certificate
of occupancy (C of O) will be obtained on
time. Only the fire protection, elevator, and
life safety inspections remain. The
mechanical, electrical, fire protection and life
safety were all design-build systems. During
the punch list, it is discovered that the fire
protection subcontractor has installed a
different type of sprinkler head on each floor.
The first floor uses concealed heads with
white escutcheons to match the ceiling tiles.
The second floor uses decorative chrome
heads. The subcontractor installed
semi-recessed heads on the third floor. This
was not picked up prior as a person cannot
physically see more than one floor at a time.
The client is very upset.
QUESTION: Can you require the
subcontractor to change them all out now?
Would this be a good move given…
arrow_forward
can you answer this as fast as you can I badly need it for my exam please help me with an easy solution so that i can understand thankyou
arrow_forward
Show complete solution.
Answer Choices:
2pcs
3pcs
4pcs
5pcs
arrow_forward
Question 3 solution?
arrow_forward
ALESHOMA Indoor environmental quality assessment
(IE) Assessment
The three questions below are independent:
JEA(indoon Environment Quality), in any LEED Certified building
(3.1) For your homework #2 what are the biggest challenge(s) during the process of
conducting the IEQ assessment for the building you selected? List 1-2 challenges that
you encountered and explain. If you did not experience any challenges in your opinion,
list 1-2 limitations of your work (every work has some limitations). Provide the potential
solution(s) to the challenges/limitations identified.
6 11
arrow_forward
You are within two weeks of turnover of a three-story build-to-suit office building project. Many of the city inspections are complete and it appears that a certificate of occupancy (C of O) will be obtained on time. Only the fire protection, elevator, and life safety inspections remain. The mechanical, electrical, fire protection and life safety were all design-build systems. During the punch list, it is discovered that the fire protection subcontractor has installed a different type of sprinkler head on each floor. The first floor uses concealed heads with white escutcheons to match the ceiling tiles. The second floor uses decorative chrome heads. The subcontractor installed semi-recessed heads on the third floor. This was not picked up prior as a person cannot physically see more than one floor at a time. The client is very upset.
arrow_forward
3. (1) Define critical path, ES, EF, LS, LF, dummy activity and slack.
(2) Cables By Us is bringing a new product on line to be manufactured in their current facility in
existing space. The owners have identified 11 activities and their precedence relationships.
(a) Draw the network diagram of this project
(b) Calculate the project completion time
(c) Identify the critical path
日
OF 5
SONY
arrow_forward
develop a WBS for your assumed building project. Mention duration for each activity of your project and total completion time.
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,
Related Questions
- 27 - please show complete solution, thanks!arrow_forwardComplete solution, please. Thanks!arrow_forwardA contract to build a 2-storey residential building is awarded to you. A Notice to Proceed (NTP) is given to you in 7 days. List down at least 10 activities you are going to do to start the project on time and explain each relevant activity.arrow_forward
- ! I need a quick solution within 15 minutes With my best wishesTonarrow_forwardEngr-429 Construction Management 1. Given the following construction progress chart, calculate the weekly cumulative progress through the end of week 5, and show the curve on the chart. The total project labor hours is 33,985, the percent complete shown is actual progress for each activity. You must calculate the weight of each activity. Shows planned schedule Shows actual progress Operation 1. Clear and Grubbing 2. Drainage 3. Subgrade 5. Pave 6. Testing Hours Wt. 7. Striping 1625 4. Base Course 8125 405 8745 14005 280 500 8. Punch List 400 SCH ACT SCH ACT SCH ACT SCH ACT SCH ACT SCH ACT SCH ACT SCH ACT 1 10 2 40 30 15 3 80 160 30 4 100 100 55 Weeks 5 6 15 85 40 15 Fall 2023 7 8 9 10 The individual weight is simply the percentage the activity represents of the total project labor hours. 100% 90% 80% 70% 60% 50% 40% 30% 20% 10%arrow_forwardI need solution in 15 minutese pleasearrow_forward
- Question 48 schedule is a schedule in which the resources for a project are assigned to activities so the activities can be closely monitored. O resource-loaded O time-loaded A look-ahead O preliminary amazon Bcer F12 Scr Lk Artêtdéf PrtSclimpréc SysRg/Syst. F4 F5 F6 F7 F8 F9 F10 F11 Bre VAarrow_forwardQ5/ The structural engineering design section within the engineering department of a regional electrical utility corporation has developed several standard designs for a group of similar transmission line towers. The detailed design for each tower is based on one of the standard designs. A transmission line project involving 50 towers has been approved. The estimated number of engineering hours needed to accomplish the first detailed tower design is 126. Assuming a 95% learning curve, a. What is your estimate of the number of engineering hours needed to design the eighth tower and to design the last tower in the project? b. What is your estimate of the cumulative average hours required for the first five designs?arrow_forwardUsing the same CPM diagram, what is the total project duration? Immediate Estimated Activity Activity Description Predecessors Duration A Excavate 2 weeks Lay the foundation Put up the rough wall Put up the roof Install the exterior plumbing Install the interior plumbing Put up the exterior siding Do the exterior painting B A 4 weeks C 10 weeks D C 6 weeks 4 weeks 5 weeks 7 weeks 9 weeks 7 weeks 8 weeks 4 weeks E C F E G D E, G Do the electrical work F, I Put up the wallboard Install the flooring Do the interior painting Install the exterior fixtures K 5 weeks M 2 weeks N Install the interior fixtures K, L 6 weeks Total = 79 weeksarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Fundamentals Of Construction EstimatingCivil EngineeringISBN:9781337399395Author:Pratt, David J.Publisher:Cengage,
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,