3. (1) Define critical path, ES, EF, LS, LF, dummy activity and slack. (2) Cables By Us is bringing a new product on line to be manufactured in their current facility in existing space. The owners have identified 11 activities and their precedence relationships. (a) Draw the network diagram of this project (b) Calculate the project completion time (c) Identify the critical path

Residential Construction Academy: House Wiring (MindTap Course List)
4th Edition
ISBN:9781285852225
Author:Gregory W Fletcher
Publisher:Gregory W Fletcher
Chapter14: Branch-circuit Installation
Section: Chapter Questions
Problem 11RQ
icon
Related questions
Question
3. (1) Define critical path, ES, EF, LS, LF, dummy activity and slack.
(2) Cables By Us is bringing a new product on line to be manufactured in their current facility in
existing space. The owners have identified 11 activities and their precedence relationships.
(a) Draw the network diagram of this project
(b) Calculate the project completion time
(c) Identify the critical path
日
OF 5
SONY
Transcribed Image Text:3. (1) Define critical path, ES, EF, LS, LF, dummy activity and slack. (2) Cables By Us is bringing a new product on line to be manufactured in their current facility in existing space. The owners have identified 11 activities and their precedence relationships. (a) Draw the network diagram of this project (b) Calculate the project completion time (c) Identify the critical path 日 OF 5 SONY
Exam Paper 1-Word
Activity
Description
Immediate Duration
Predecessar (weeks)
Developproduct specifications
Design manufactưing process
Source & purchasematerials
Source & purchase tooling &equipment
Receive & install tooling &equipment
None
4.
14
Receive materials
E&F
Pilat production run
Evaluate product design
Evaluate process performance
White documentation report
Transition to manufacturing
G
G
H&I
J
K
636 A52 2342
AAB DC
ABCDE ECHI sY
Transcribed Image Text:Exam Paper 1-Word Activity Description Immediate Duration Predecessar (weeks) Developproduct specifications Design manufactưing process Source & purchasematerials Source & purchase tooling &equipment Receive & install tooling &equipment None 4. 14 Receive materials E&F Pilat production run Evaluate product design Evaluate process performance White documentation report Transition to manufacturing G G H&I J K 636 A52 2342 AAB DC ABCDE ECHI sY
Expert Solution
steps

Step by step

Solved in 4 steps with 1 images

Blurred answer
Knowledge Booster
Issues during construction
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Residential Construction Academy: House Wiring (M…
Residential Construction Academy: House Wiring (M…
Civil Engineering
ISBN:
9781285852225
Author:
Gregory W Fletcher
Publisher:
Cengage Learning