The following tasks are to be performed on an assembly line: TASKS THAT MUST PRECEDE TASK ABCDEFGH H SECONDS 25 15 20 29 16 8 35 32 A B BUD C E, F G The workday is 10.5 hours long. The demand for completed product is 900 per day. a. Find the cycle time required to meet the desired output rate. Note: Round your answer to 1 decimal place.
Q: Jonathan owns and operates 5 car window tinting shops in the Rio Grande Valley area. Each tint shops…
A: The design capacity is the most excellent output that a system, machine, or process can produce…
Q: The business-to-customer (B2C) approach can have certain potential downsides. Explain
A: "Business-to-consumer approach" work on transactional practices typically includes interaction with…
Q: Consider a production line with five stations in serial. The stations have the following process…
A: Find the Calculation methods below: Capacity = Process timeNumber of machines Bottleneck = Slowest…
Q: How can top management best help the new project manager get up to speed?
A: The query above relates to how top management may assist a new project manager to become productive.…
Q: for ideas what could be 5 whys for the movie 12 angry men the oringinal version? what could you do…
A: Here are five potential "5 Whys" scenarios for the movie 12 Angry Men and potential solutions: 1.…
Q: The following table shows the costs associated with distributing the items to the respective plants.…
A: Develop a spreadsheet as below to find the total minimum cost. Each machine should be assigned to 1…
Q: Managing and controlling scope changes affects project deliveries. Discuss change management and…
A: In organizations, change management refers to the practice of systematically addressing issues that…
Q: Your past projects gave the client wide berth when it came to suggesting changes at any time they…
A: One of a manager's most significant capabilities is to direct and control the activities of…
Q: Which of the following involves a test of two-related samples? Multiple Choice Test of whether…
A: To be determined: Which of the following involves a test of two related samples. Introduction A…
Q: Which of the following level of operational risks relates to model errors and losses arising from…
A: Introduction Operational risk refers to the potential for losses resulting from inadequate or failed…
Q: What are the most important features that would influence a customer to buy a smartphone
A: There are multiple prominent features that would influence a customer to buy a smartphone, a…
Q: a) Determine the type of fraud committed and describe the symptoms of fraud that might be evident to…
A: The provided excerpt tells the tale of Sharp, a bookkeeper employed by John Travolta, the proprietor…
Q: SLO 8.2. If the buyer does not have a clear and unambiguous description or specification and wants…
A: If you have any desire to purchase materials from a supplier for an expert venture, you might…
Q: The owner of a large machine shop has just finished its financial analysis from the prior fiscal…
A: a. To compute the inventory turnover ratio (ITR), we need to divide the cost of goods sold by the…
Q: You've just completed a pilot run of 10 units of a major product and found the processing time for…
A: A learning rate illustrates how a process improves over time as a result of learning and growing…
Q: An ethical statistical consultant would not always
A: Ethical statistical practices are the set of guidelines and principles that govern the proper…
Q: Time estimates Expected Variance Activity Optimistic Most Likely Pessimistic Time (ET) (6²) m 40 50…
A: Formulae used: Expected time is (E)= (O + 4M + P)6. Variance (σ2)=P-O62 Standard Deviation=σ2…
Q: Professional integrity in project management is crucial.
A: Integrity can be defined as a framework or an item that is the quality or condition total; solid…
Q: What are the six rules for crisis management? Can you explain it with example?
A: The six rules for crisis management are: Act quickly: In a crisis, it is essential to respond…
Q: Jeff Winters is considering investing some money that he inherited. The following payoff table gives…
A: Mathematic models of decision-making help businesses take the correct decision for their operational…
Q: Steve is a marketing intern at Home-Style Cookies. One of Steve’s responsibilities is to set up a…
A: Labor productivity refers to the ratio of output to the input labor hours
Q: When would you want more space for your belongings?
A: The need for more space for belongings can arise in various operational management scenarios, such…
Q: The grocery store has bulk pecans on sale, which is great since you're planning on making 8 pecan…
A: Buying in bulk can be a great way to save money when cooking or baking for a large event, such as a…
Q: A company that produces pleasure boats has decided to expand one of its lines. Current facilities…
A: Given- For Alternative A, fixed cost = $250,000 per year; Variable cost = $500 per boatFor…
Q: Enumerate the possible objectives of: Influence of Cultural differences in busines.
A: The cultural norms of a country have a significant bearing on its approach to international trade.…
Q: Invoice clearance and payment procedures: Are best performed by the user or specifier Are the same…
A: ANSWER:1 The other options are incorrect: Ideally, the user or specifier should: Users and…
Q: 1. Draw the Activity on Node network. 2. Perform the CPM calculations using the forward and backward…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: A process includes 9 tasks and there are 3 workers. Each task can be assigned to only one worker and…
A: Given data: No. of task 1 2 3 4 5 6 7 8 9 Time in seconds 80 50 30 25 55 15 45 105 40
Q: Explain what you mean by the terms "functional," "matrix," and "project." Describe the effects of…
A: The terms "functional," "matrix," and "project" are different types of organizational structures…
Q: Should firms outsource their technical requirements to software service providers? Your thoughts?…
A: Technical support is a service that most organizations give to customers that assists them with…
Q: Cobonque Furniture Enterprises is a known maker of fine hand-crafted furniture in Davao del Sur.…
A: Decision Variable:Suppose-T be the no. of units of tables to be producedC be the no. of units of…
Q: A manufacturer has a production line with 4 serial machines and each unit needs to pass through all…
A: The above give question is to calculate the capacity rate of the process. Capacity utilization is a…
Q: How do these two fields differ from one another? How, for instance, are project management and…
A: Project management and software development are connected fields, however they differ in more ways…
Q: John is operating a business in the Caribbean in the manufacturing sector. Over the years the…
A: 6. If John decides to expand to South Korea, Canada, Taiwan, Thailand, or Japan, a PESTEL analysis…
Q: can u get the bcwp, bcws, schedule performance index, cost performance index (in a table)…
A: The following are the formulas used to compute BCWP, BCWS, SPI, CPI BCWP = % of work done × Actual…
Q: b) Describe the importance of quality and the importance of 4M man, machine materials and methods in…
A: Quality is a critical factor in the success of any product, including motor vehicles. It refers to…
Q: true or false To combine research from different fields or locations and to accelerate the…
A: The term research in a broad sense refers to discovering and exploration in a new field to gain…
Q: It is important to understand the different approaches to measuring performance. Discuss.
A: Measuring performance is a crucial aspect of any association's management process. Performance…
Q: Managing the risk of material misstatement in the purchasing process is critical. Identify two…
A: Two different industries where the risk of material misstatement in the purchasing processmay differ…
Q: true or false Innovative SMEs are more likely to involve product innovation than process innovation.
A: The term "product innovation" is used to describe any kind of modification to an existing product.…
Q: For the past month, a plant that has an effective capacity of 6,000 has made only 5,000 hammers per…
A: The efficiency of the plant can be determined as the actual output divided by effective capacity.…
Q: course: Strategic concept Topic: Ryanair flying too close to the sun 1. How has Ryanair…
A: 1. Ryanair has had a significant impact on the development of the airline industry, particularly in…
Q: What is the optimal objective function value for this problem
A: Here, I have been given the sensitivity report, The decision variables are Activity 1, Activity 2…
Q: Briefly defining a technique and then discussing its three constituent pieces.
A: One technique define and discuss its three constituent pieces is the SWOT analysis. SWOT analysis is…
Q: 5) What is the probability that this project will be completed after 110 days? A. 0.0228 B. 0.1587…
A: A network diagram shows the sequence of the task that is done to complete a project. It usually…
Q: 4 key constraints faced when rebuilding the elliott bay seawall
A: The Elliott Bay Seawall reconstruction is a sizable building project with many challenges that must…
Q: f a production facility equipment runs for l0 hours and must be idle for four hours while being…
A: Production is the relation of the inputs to have the required output. It includes various tools,…
Q: After listening to the video on Leadership and Change Management, consider your readings across the…
A: Leadership is an interaction by which a chief can direct, guide and impact the way of behaving and…
Q: Your mission is to track out two scholarly works on the ethics of project management and provide…
A: "Project Management Ethics: Responsibility Without Control" by John Hooker (2002)In this article,…
Q: You own a wheat warehouse with a capacity of 20 bushelsAt the beginning of month 1, you have 6…
A: Constraint formation: The constraint will be to sell only up to initial stock this means quantity…
Q23 all of these pictures are from the same initial question and I need help please!!
Help with a b c d e f and g which is not shown but here is the question:
g-
Find the Given details below:
Task | Duration (Seconds) |
Precedence |
A | 25 | - |
B | 15 | A |
C | 20 | B |
D | 29 | B |
E | 16 | C |
F | 8 | D |
G | 35 | E,F |
H | 32 | G |
Calculation methods:
Trending now
This is a popular solution!
Step by step
Solved in 6 steps with 10 images
- The following tasks are to be performed on an assembly line: TASK ABCDEFGH SECONDS 30 Cycle time 16 21 15 17 14 20 9 Number of workstations. TASKS THAT MUST PRECEDE The workday is 8 hours long. Demand for completed product is 900 per day. a. Find the cycle time required to meet the desired output rate. (Round your answer to 1 decimal place.) 51.0 seconds per unit Work Station A B b. What is the theoretical number of workstations required to meet the desired output rate? (Round up yo number.) Task C D E, F d. Balance the line using sequential restrictions and the longest-operating-time rule. (Leave no cells blar wherever required. Round your answers to 1 decimal place.) Idle TimeSITUATION: A company is about to begin production of a new product. The manager of the department that will produce one of the components for the product wants to know how often the machine used to produce the item will be available for other work. The machine will produce the item at a rate of 200 units a day. Eighty units will be used daily in assembling the final product. Assembly will take place five days a week, 50 weeks a year. The manager estimates that it will take almost a full day to get the machine ready for a production run, at the cost of $300. Inventory holding costs will be $10 a year. QUESTION: Suppose the manager decides to increase the run size of the new product. How many additional units would be needed just to accommodate the other job? How much will that increase the total annual cost?An assembly line is to be designed to operate 7.5 hours per day and supply a steady demand of 300 units per day. a)assign tasks to workstations using the longest operating time b)suppose demand increase by 10%.how would you react to this?assume you can operatee only 7.5 hours per day TASK PRECEDING TASKS PERFORMANCE TIME(seconds) a - 70 b - 40 c - 45 d a 10 e b 30 f c 20 g d 60 h e 50 i f 15 j g 25 k h,i 20 l j,k 25
- A production process at Kenneth Day Manufacturing is shown in Figure S7.9. The drilling operation occurs separately from, and simultaneously with, sawing and sanding, which are independent and sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel).a) Which operation is the bottleneck?b) What is the bottleneck time?c) What is the throughput time of the overall system?d) If the firm operates 8 hours per day, 20 days per month, whatis the monthly capacity of the manufacturing process?A manufacturing plant has the process displayed below. The drilling operation occurs separately from and simultaneously with the sawing and sanding operations. The product only needs to go through one of the three one of the three assembly operations (the assembly operations are ‘parallel’). Use diagram titled "q3" attached as an image a) What is the bottleneck operation? b) What is the throughput time for the overall system? c) If the firm operates 10 hours a day, 21 days a month, what is the monthly and yearly capacity of the manufacturing process? d) Supposed that a second drilling machine is added, and it takes the same time as the original drilling machine. What is the new bottleneck time of the system? e) What is the new throughput time if the second drilling machine is added? f) What is the new hourly capacity if the second drilling machine is added?kindly do question 5 & 6 pls. thx Kiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40 teddy bears per hour on its assembly line. The following information will assist in answering the questions that follow: Task Information for Kiko Teddy Bear Work Element Task Description Immediate Predecessor Task Time (in seconds) A Cut teddy bear pattern None 90 B Sew teddy bear cloth A 75 C Stuff teddy bear B 50 D Glue on eyes C 20 E Glue on nose C 15 F Sew on mouth C 35 G Attach manufacturer’s label B 15 H Inspect and pack teddy bear D,E,F,G 40 Draw a precedence diagram. What cycle time would provide the desired output? What is the maximum possible output of the line?…
- A paced assembly line has been devised to manufacture calculators, as the following data show: Station Work ElementAssigned Work ElementTime (min) S1 S2 S3 S4 S5 S6 A D,E C B,F,G H,I,J K 2.7 0.6, 0.9 3.0 0.7, 0.7, 0.9 0.7, 0.3, 1.2 2.4 a. What is the maximum hourly output rate from this line? (Hint: The line can go only as fast as its slowest workstation.)b. What cycle time corresponds to this maximum output rate?c. If a worker is at each station and the line operates at this maximum output rate, how much idle time is lost during each 10-hour shift?d. What is the line’s efficiency?T. Smunt Manufacturing Corp. has the process displayed below. The drilling operation occurs separately from and simultaneously with the sawing and sanding operations. The product only needs to go through one of the three assembly operations (the assembly operations are “parallel”). See attached image with outline a. Which operation is the bottleneck? b. What is the throughput time (time from start to finish for one unit) of for the overall system? c. If the firm operates 8 hours per day, 22 days per month, what is the monthly capacity of the manufacturing process? d. Suppose that a second drilling machine is added, and it takes the same time as the original drilling machine. What are the new bottleneck operation and the bottleneck time? e. Suppose that a second drilling machine is added, and it takes the same time as the original drilling machine. What is the new throughput time? f. Suppose that a second drilling machine is added, and it takes the same time as the…A dress-making operation is being designed as an assemblyline. Table 10-22 shows the tasks that need to be performed, theirtask times, and preceding tasks. If the goal is to produce 30 dressesper hour, answer the questions that follow the table. (a) Compute the cycle time.(b) Which task is the bottleneck?(c) What is the maximum output for this line?(d) Compute the theoretical minimum number of stations.(e) Assign work elements to stations, using the longest tasktime rule.(f) Compute the effi ciency and balance delay of yourassignment.
- Suppose the times for the individual operations for the in-line skate assembly are as follows: Task Description Time (sec) 1 Assemble wheels, bearings, and axle hardware 11 2 Assemble brake housing and pad 8 3 Complete wheel assembly 20 4 Inspect wheel assembly 13 5 Assemble boot 18 6 Join boot and wheel subassemblies 7 7 Add line and final assembly 10 8 Perform final inspection 10 Consider the production line achieving an output rate of 180 per hour below. Using the proposed design, calculate the total time and idle time for each workstation. If your answer is zero, enter "0". Round your answers to the nearest whole number. Station Tasks Total Time, seconds Idle Time, seconds A 1 and 2 B 3 C 5 D 4 and 6 E 7 and 8 Total What is the assembly line efficiency? Round your answer to one decimal place. %You've just been assigned the job of setting up an electric fan assembly line with the following tasks and precedence relationships The assemtly line wil be nunning 8 hours per day and 5 days per week, The demand forast is 600 Items per week. Your goal is to minimie the numbor of workstations necesary to complete enough units to satisfy the demand forecast. What is the takt time (in minutes) needed to produce the required number of units? (Integer Answer, do not put anything other than numbers.) What is the theoretical minimum number of workstations that you will need (apply the round-up rule)? (Integer Answer, do not put anything other than numbers.)Draw a process fl ow diagram of your last doctor’s offi cevisit. Identify bottlenecks. Did any activities occur in parallel?