Task 2. Create a digraph for the following set of tasks: Time required Tasks that must be completed first A 3 B 4 C 7 D 6 A E 5 A F 5 B G 4 D, E

Mathematics For Machine Technology
8th Edition
ISBN:9781337798310
Author:Peterson, John.
Publisher:Peterson, John.
Chapter87: An Introduction To G- And M-codes For Cnc Programming
Section: Chapter Questions
Problem 12A
icon
Related questions
Question
2. Create a digraph for the following set of tasks:
Task
Time required
Tasks that must be
completed first
ABCDEFG
3
4
с
7
6
A
5
A
5
B
4
D, E
Transcribed Image Text:2. Create a digraph for the following set of tasks: Task Time required Tasks that must be completed first ABCDEFG 3 4 с 7 6 A 5 A 5 B 4 D, E