Tacloban Company incurred the following costs at the beginning of the current year: cost of land, P1,000,000; cost of building, P4,000,000; remodeling and repairs prior to occupancy, P500,000; escrow fee, P100,000; clearing, leveling and landfill, P250,000; property tax for period prior to acquisition, P150,000; real estate commission P300,000. What is the cost of the building?

SWFT Comprehensive Volume 2019
42nd Edition
ISBN:9780357233306
Author:Maloney
Publisher:Maloney
Chapter8: Depreciation, Cost Recovery, Amortization, And Depletion
Section: Chapter Questions
Problem 30CE
icon
Related questions
Question

Tacloban Company incurred the following costs at the beginning of the current year: cost of land, P1,000,000; cost of building, P4,000,000; remodeling and repairs prior to occupancy, P500,000; escrow fee, P100,000; clearing, leveling and landfill, P250,000; property tax for period prior to acquisition, P150,000; real estate commission P300,000. What is the cost of the building? 

Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Section 179 Deduction and Modified Accelerated Cost Recovery System (MACRS) Depreciation
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
SWFT Comprehensive Volume 2019
SWFT Comprehensive Volume 2019
Accounting
ISBN:
9780357233306
Author:
Maloney
Publisher:
Cengage
SWFT Essntl Tax Individ/Bus Entities 2020
SWFT Essntl Tax Individ/Bus Entities 2020
Accounting
ISBN:
9780357391266
Author:
Nellen
Publisher:
Cengage