Suppose you are a project manager of a power plant project and there is a penalty in your contract with the main client for every day you deliver the project late. You need to decide which sub-contractor is appropriate for your projects critical path activities. But while selecting a sub-contractor, you should take into consideration the costs and delivery dates. • Sub-contractor A bids 200,000 OMR. You estimate that there is a 35% possibility of completing 50 days late. As per your contract with the client, you must pay a delay penalty of 4,500 OMR per calendar day for every day you deliver late. • Sub-contractor B bids 260,000 OMR. You estimate that there is a 13% possibility of completing 15 days late. As per your contract with the client, you must pay a delay penalty of 4,500 OMR per calendar day for every day you deliver late. Determine which sub-contractor is appropriate for your projects critical path activities. Both sub- contractors promise successful delivery and high-quality work.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
Question

Suppose you are a project manager of a power plant project and there is a penalty in your contract with the main client for every day you deliver the project late. You need to decide which sub-contractor is appropriate for your projects critical path activities. But while selecting a sub-contractor, you should take into consideration the costs and delivery dates.

• Sub-contractor A bids 200,000 OMR. You estimate that there is a 35% possibility of completing 50 days late. As per your contract with the client, you must pay a delay penalty of 4,500 OMR per calendar day for every day you deliver late.
• Sub-contractor B bids 260,000 OMR. You estimate that there is a 13% possibility of completing 15 days late. As per your contract with the client, you must pay a delay penalty of 4,500 OMR per calendar day for every day you deliver late.

Determine which sub-contractor is appropriate for your projects critical path activities. Both sub- contractors promise successful delivery and high-quality work.

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Knowledge Booster
Team dynamics
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,