• Q2:Find out the completion time and the critical activities for the following project: D 20 E H 11 K 6 B 10 16 14 10 25
Q: How can the supply chain remain sustainable while remaining resilient
A: Concept Introduction Supply chain management helps the production firms to convert the raw materials…
Q: Question 2 Alpha Electronics (AE) is a large manufacturer of electronics products. The company sells…
A: (a)
Q: a) A manufacturer wishes to create a flow line which will produce 555 pumps/day (8 hrs/ day). The…
A:
Q: Vogel’s Approximation Method (VAM) for initial basic feasible solution Find the optimal solution…
A: The transportation model is used to calculate the minimum cost of the route by selecting different…
Q: Using the following project information, calculate the variance for each of the project activities.…
A:
Q: Uberya Towing Services repair vehicles that break down at an average 7.5 vehicles per day. The…
A: GIVEN: ARRIVAL RATE 7.5 SERVICE RATE 10
Q: What is whistleblowing? When should an employee become a whistleblower? Under what circumstances is…
A: Whistleblowing means informing to leader about a wrong activity commited in the workplace.
Q: b. Use the implied value of alpha from part a to determine the required reduction in waiting time if…
A:
Q: The Big Five Personality Model is used to organize traits and predict leadership in: a. situational…
A: The porters five force model is a behavioural theory which is studied and helps to identify the…
Q: what type of corporate diversification strategy should a coffee shop business adapt?
A: There are multiple types of corporate diversification strategies that a coffee shop business could…
Q: Project X has the data points below. The schedule performance index (SPI) for task P is .. Task BCWS…
A: Here, we first understand the values given for each task BCWS = Budgeted Cost of work scheduled -…
Q: Identify TWO (2) methods of service design that can increase service efficiency and limit customer…
A: Services are intangible in nature that we cannot see it but we can only feel it and inorder to…
Q: Demand for walnut fudge ice cream at the Sweet Cream Dairy can be approximated by a normal…
A: Weekly demand (d) = 35 gallons per week Standard deviation (σ) = 8.48 gallons per week Expected…
Q: 1.Discuss how the roles of operators and maintenance staff may change as a result of TPM(Total…
A: 1) Plant managers, line supervisors, and machine operators are all familiar with the equipment and…
Q: QUESTION 5 When CPI is calculated, chicken breasts are given greater weight than pork chops if a.…
A: Consumer price index is a tool or a equation which shows the relationship between its price and…
Q: Operations Management Give examples of measuring service quality and measuring product quality? (2…
A: Quality is the ability of excellence of producing products that can be compared with other similar…
Q: Operations Management 15.Organizational structure contributes to explaining and predicting…
A: A organisational structure refers to a structure which is created either due to fulfillment of the…
Q: Please answer it immediately sir Linear Programming The Booboo sawmill in Batangas produces pine and…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: The manufacturer of Beats headphones by Dr. Dre decides to advertise in the "lifestyles" sections of…
A: The manufacturer of Beats headphones by Dr. Dre decides to advertise in the "lifestyles" sections of…
Q: operations* is the right answer
A: A JIT system is a production system that produces goods on demand. The system stores material and…
Q: Why is it that the Quality, Delivery, and Price expectations of the customers should be considered…
A: The clients are the end-users of your product or service, therefore it’s only right that they get to…
Q: Plan D O.T. Ending Inventory 200 Production Production Stockouts Month Demand (Units) (Units)…
A: The aggregated demand table lists the various needs of a company and the corresponding product or…
Q: a. If there are 29 kanban containers in use, the current daily demand of the check processing…
A: Given: Average demand d 6000 Average waiting time per unit w 0.083 Average processing time…
Q: LahLa Mub Delivery a logistics operator process the packages for shipment. The items arrive at the…
A: Service rate is the rate at which the customers are being served by the workers in an organisation.
Q: In what ways are projects and ordinary work different?
A: Project management concerns the planning & organization of business resources to drive a…
Q: A queuing model which follows the M/M/1 assumptions has λ = 2 and μ = 3. The average waiting time in…
A: Given: ARRIVAL RATE 2 SERVICE RATE 3
Q: Can you show it without using excel please?
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: BRIEFLY DISCUSS AND DESCRIBE THE TERMS OPERATIONS MANAGEMENT AND SUPPLY CHAIN
A: Operations is defined as the actions and decisions taken by the participants and members of a…
Q: If the process capability ratio of a centered process is 0.7, and the process mean is 76, what is…
A: Given: Process capability ratio=0.7 process mean=76 Average amount of defects per 1 million
Q: Five drilling machines at Al Hamriya steel is maintained by Lumina maintenance service with 2…
A:
Q: a number of drawbacks.
A: Robotics is a discipline of mechanical engineering that focuses on the conception, design, and…
Q: For each of the following network diagrams, determine both the critical path and the expected proj-…
A: The network diagrams for critical path can be constructed in two ways: Arrow to Node - AON Arrow to…
Q: When determining whether a partnership exists, which of the following factors would a court…
A: ANSWER : A partnership is arrangement between two or more people to look after a business…
Q: Categories the challenges in surveying works towards to sustainable development.
A: Sustainable development means different things to different people, but at its core, it is about…
Q: Question 47 Different levels of supply chain analytics include Descriptive, Predictive,…
A: The processes used by the organizations to obtain the input or insight and take out value from…
Q: Automatic dividend reinvestment is a requirement of all mutual fund companies. O compounds share…
A: Automatic dividend reinvestment refers to the investment of the company's dividends directly to buy…
Q: What does "earned value" mean in the context of a project, and how does it get calculated? Explain
A: A project is the set of tasks that are to be formed to achieve the desired outcome. A project deals…
Q: Draw activity network of the project. Crash the activities step by step until all paths are critical
A: Project crashing is a process which helps to reduce the total completion time using additional costs…
Q: * 4 Roy Creasey Enterprises, a machine shop, is planning to move to a new, larger location. The new…
A:
Q: Maroons Medical Supplies, Inc. must order masks from its supplier in lots of 1 dozen boxes. Given…
A: Given, annual demand, d= 26000 dozens Ordering cost,o =P30 Carrying cost, h= 20% of unit cost Price…
Q: Think about the benefits and drawbacks of a manual task. response program (in which the customer…
A: Manual tasks are activities performed by an individual using their own body to do any work..…
Q: Labor availability 0.2 90 90 70 Proximity to major transportation 0.1 corridor 80 60 50 Determine…
A: Given, Weight for- Annual operating expenses : 0.7 Labor availability : 0.2 Proximity to major…
Q: table below. Labor costs is RM11/hour and materials costs are RM3.5/pound. Calculate multifactor…
A: Productivity is the relationship between the volume of the input and output that is calculated in…
Q: What are some laws and legal issues related to the benefits program for part-time employees.
A: There are certain benefits programs for part-time employees which benefit the employee additionally…
Q: What does a project’s NPV of $1,500 mean?
A: The Net Present Value is excess of Present Value of Cash Inflow over Present Value of Cash Outflow.…
Q: why is transportation planning important? 2. how do you make a transport plan? 3. how do you…
A: Transportation is the backbone of a supply chain and distribution system of an organisation because…
Q: What is the definition of configuration management, and what are the two types of configuration…
A: Configuration management (CM) refers to the process of systematically handling changes to a…
Q: The standard deviation of daily demand for an item is 100 units per day. The lead time for the item…
A: Daily demand is the requirement of the customer for the product it services. The customers can be…
Q: f Cassie does not maintain a safety stock, the estimated total carrying costs for the office…
A: Production management is the process of managing the production of a product, service, or result.…
Q: New-economy companies generally have higher O A. than old-economy companies. book value per share O…
A: PE ratio or profit earning ratio refers to the profit earned by a particular stock divided by the…
Step by step
Solved in 2 steps with 1 images
- Q6:write briefly but relevant answer a) PERT and CPM b) Risk Management and its types.The expected times and variances for the activities for a project for Test Marketers, Inc. are given below. (Assume time is provided in days.) ID 12345678 Description Pilot production Select channels of distrib. Develop mktg. program Test market Patent Full production Ad promotion Release Predecessor None None None 1 1 4 3 2,5,6,7 t₂ 6 7 4 4 10 16 3 2 Varlance [(b-a)/6]² 34225221 10What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? NORMAL CRASH TIME (DAYS) TIME (DAYS) 9 7 7 6 5 4 6 4 9 6 ACTIVITY Design (A) Wiring (B) Chip install (C) Software (D) Testing (E) The minimum cost of crashing the following project at Sawaya Robotics by. 4 days is $ NORMAL COST 200 800 600 1,100 1,200 CRASH COST 300 875 675 1,300 1,875 IMMEDIATE PREDECESSOR(S) (enter your response as a whole number). A, B C
- ++ Earned value analysis is the project management tool that is used to measure project progress. You are a project manager in company XYZ that responsible to handling the packaging machine project with the total cost budgeting is RM100,000. There are including RM24,000 (Design), RM60,000 (build) and RM16,000 (install & test). The information regarding on the project progress development in weeks 8 as shown in Table 2 below: Table 2 No 1 2 3 Type Cumulative Budgeted Cost (CBC) Cumulative Actual Cost (CAC) Cumulative Earned Value (CEV) TOTAL RM 64,000 68,000 54,000 100,000 Percentage 64.0 68.0 54.0 100.0 a) With the aid of a typical S-curve diagram, draw and explain the four cost-related measures such as TBC, CBC, CAC and CEV to analyses the overall project cost performance.What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? NORMAL CRASH TIME (DAYS) TIME (DAYS) NORMAL COST 8 6 6 4 ACTIVITY Design (A) Wiring (B) Chip install (C) Software (D) Testing (E) 8 5335 400 1,000 600 1,000 1,100 CRASH COST 450 1,100 700 1,300 1,625 IMMEDIATE PREDECESSOR(S) A, B C The minimum cost of crashing the following project at Sawaya Robotics by 4 days is $900 (enter your response as a whole number).Q5: Reduce the following project activity Normal Time Cost 1-2 3 300 2-3 6 480 7 2100 2-5 8 400 3-4 4 320 4-5 5 500 Crash Time AS9SAN 2 Cost 400 520 2500 600 360 520 MWEBd
- What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? NORMAL TIME (DAYS) CRASH TIME (DAYS) 5 4 ACTIVITY Design (A) Wiring (8) Chip install (C) 7 5 3 4 7 2 2 4 NORMAL COST 300 900 500 CRASH COST 1,100 1,200 350 975 575 Software (D) Testing (E) The minimum cost of crashing the following project at Sawaya Robotics by 4 days is $1,875 (enter your response as a whole number). IMMEDIATE PREDECESSOR(S) 1,300 1,650 A, B сHey there I have a project management related task in which I have to design a new university library. Fo these I need some help related to following things:1-Major constraints 2-Expected Benifits3-Major AssumptionsAlso if you can tell some risks for risk register as well.Q4) What Is Project Quality Management? Write briefly about the five Cost Categories Related to Quality .Describe about Quality Assurance.
- Q3.When we start a project how we know this project or program is feasible for our future? Explain with help of diagramEX8-14 (Algo) Given the time-phased work packages... Given the time-phased work packages and network, complete the baseline budget form for the project. 0 0 0 A 3 Design 3 3 A Design prototype B Build prototype C Order parts Legend ES ID EF SLK Descrip LS DUR LF ID A B C D E F G D Prepare production E Prepare marketing F Assemble and test G Launch Total 3 0 B 5 Build 3 2 5 Budget Cumulative 21 12 17 62 32 36 12 192 Soccer Toy Project Cost By Week ($000) 3 5 12 20 5 2 10 0 14956682 1 10 2 2 4 18 18 5 0 1 6 5 0 5 5 1 6 ... C 8 с Order 3 9 D 9 Prod. 4 9 E 10 Mktg 5 11 8 22 16 4 6 0 0 0 0 0 0 Enter the appropriate values in the truncated portion of the budget form shown below. 4 5 0 Enter the appropriate values in the truncated portion of the budget form shown below. 0 0 0 0 0 12 Time Periods 8 9 F 11 0 Assy. 9 2 11 9 11 0 11 10 G 12 Launch 1 12blä 8 Q2/ By using PERT Method, Solve the ? following Q2/ For the project described in table below, assume that the activity durations are approximately normally distributed. Determine the probability to complete this project in (15 weeks). Activity Path m b a A (1,2) 1 2 В (2,3) 2 4 C (2,4) 1 3 D (4,5) 2 5 8 E (1,5) 2 4 F (5,6) 1 2 Note that the activity (3,4) is a dummy activity. 3. 3.