Q2: An intersection approach has a cycle length of 110 sec and the effective green time is 45 sec. The arrival rate varies over tree cycles. The arrival rate is 1000 veh h during the first cycle, 800 veh/h during the second cycle, and 580 veh/h during the third cycle. The Question: Find the average delay for the approach over tree cycles, if the departure rate is 2500 veh/h.

Traffic and Highway Engineering
5th Edition
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Garber, Nicholas J.
Chapter8: Intersection Control
Section: Chapter Questions
Problem 26P
icon
Related questions
Question
Q2:
An intersection approach has a cycle length of 110
sec and the effective green time is 45 sec.
The arrival rate varies over tree cycles. The arrival
rate is 1000 veh/h during the first cycle, 800 veh h
during the second eycle, and 580 veh/h during the
third cycle.
The Question:
Find the average delay for the approach over tree
cycles, if the departure rate is 2500 veh h.
Transcribed Image Text:Q2: An intersection approach has a cycle length of 110 sec and the effective green time is 45 sec. The arrival rate varies over tree cycles. The arrival rate is 1000 veh/h during the first cycle, 800 veh h during the second eycle, and 580 veh/h during the third cycle. The Question: Find the average delay for the approach over tree cycles, if the departure rate is 2500 veh h.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps

Blurred answer
Knowledge Booster
Types of Scheduling Techniques
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning