On March 1, 2022, AGGREGATES Company enters a contract to build a hotel which is estimated to cost P31,200,000. The company recognizes construction revenue over time. Data on this project for 2022-2024 follow: Contract Billings Costs incurred Est'd Costs to complete 2022 10,500,000 5,460,000 20,540,000 2023 12,500,000 9,984,000 13,156,000 2024 14,440,000 15,756,000 - The contract contains a penalty clause that penalizes the company a reduction of P70,000 from the contract price for every week of delay. In 2024, the contract was delayed for 8 weeks. What is the gross profit for 2024? A. 1,164,000 C. 1,724,000 B. 1,466,400 D. 1,824,000
On March 1, 2022, AGGREGATES Company enters a contract to build a hotel which is estimated to cost P31,200,000. The company recognizes construction revenue over time. Data on this project for 2022-2024 follow: Contract Billings Costs incurred Est'd Costs to complete 2022 10,500,000 5,460,000 20,540,000 2023 12,500,000 9,984,000 13,156,000 2024 14,440,000 15,756,000 - The contract contains a penalty clause that penalizes the company a reduction of P70,000 from the contract price for every week of delay. In 2024, the contract was delayed for 8 weeks. What is the gross profit for 2024? A. 1,164,000 C. 1,724,000 B. 1,466,400 D. 1,824,000
Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 26E
Related questions
Question
100%
On March 1, 2022, AGGREGATES Company enters a contract to build a hotel which is estimated to cost P31,200,000. The company recognizes construction revenue over time. Data on this project for 2022-2024 follow:
Contract Billings | Costs incurred | Est'd Costs to complete | |
2022 | 10,500,000 | 5,460,000 | 20,540,000 |
2023 | 12,500,000 | 9,984,000 | 13,156,000 |
2024 | 14,440,000 | 15,756,000 | - |
The contract contains a penalty clause that penalizes the company a reduction of P70,000 from the contract price for every week of delay. In 2024, the contract was delayed for 8 weeks.
What is the gross profit for 2024?
A. 1,164,000 C. 1,724,000
B. 1,466,400 D. 1,824,000
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning