manufacturer operates 8 hours per day for 340 days per year, and has a demand of 2,000 units per day. There are four production cycles per day. Assume the following: 7,700 units produced per day, holding cost per unit is $5 per year, labor rate to do line set-ups is $13 per hour. With quick set-ups, the production line must be quickly re-organized. a. What is the target set-up cost? b. What is the set-up time in minutes?
Q: a number of drawbacks.
A: Robotics is a discipline of mechanical engineering that focuses on the conception, design, and…
Q: (3) What are the basic steps in risk management? Briefly describe each.
A: 3. Risk management process involves risk identification, risk analysis, risk response planning and…
Q: in the table shown, do each of the following: 1. Draw a precedence diagram. Assuming an eight-hour…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: In process improvement efforts, cost of quality is a means to quantify the total cost of…
A: The following are some probable causes of high quality-related costs: 1. Poor quality leads in…
Q: Determining whether an amount is of a capital or a revenue nature forms part of the subjective test.
A: Capital and revenue nature are objective concepts that can be determined by reference to generally…
Q: Every summer Marianna offers a special convertible roof on the Sport Coupe model. The demand for the…
A:
Q: What are the issues and tasks for organizing a project?
A: Organizing a project means structuring a project. Structuring means managing, coordinating and…
Q: Operations Management (OM) strategy changes according to the product stage in the Product Life Cycle…
A: The operation strategy would get changed in various stages of the product life cycle or PLC, in each…
Q: Why are Deming's 14 points important to quality management?
A: Quality management is the management that ensures the production and delivery of quality products…
Q: What makes the store manager of a retail company a classic example of an operations manager?
A: Operations managers are responsible for the operations of a company on a day-to-day basis. They make…
Q: Q2: The activities involved in the construction of a certain project are given in the table below.…
A: A network diagram is a visual representation of a project which helps to identify the activity…
Q: A company is producing a single product and is selling it through five agencies situated in…
A: Find the Given details below: Given details: Surplus Cities Deficit Cities A1 B1 C1 D1 E1 A…
Q: the role of a project leader in a project management process
A: A project leader is the main and responsible person who has the responsibility to manage and control…
Q: a. If there are 29 kanban containers in use, the current daily demand of the check processing…
A: Given: Average demand d 6000 Average waiting time per unit w 0.083 Average processing time…
Q: Sunseel Industries produces two types of raw materials, A and B, with a production cost of $4 and $8…
A:
Q: 360- degree feedback is effective way of appraising the performance of employees provided it is…
A: 360 Degree Employees receive private, anonymous feedback from their coworkers through a system or…
Q: How to carry out the role of nature manager? Explain
A: Manager is part of management which combines his skills and expertise in a sequence to manage nad…
Q: Why is it more difficult to implement an agile development approach in a company that has a…
A: Under Traditional Project Management, all tasks related to the proect are done in a defined…
Q: aditional art from Contemporary Art in terms of technique and materials used
A: Traditional art: The seven sorts of expressive arts are viewed as customary works of art. Drawing,…
Q: What are the solutions from a post normal perspective on increasing the healthcare capacity in the…
A: It is important to remember that post-normal perspectives emphasize the importance of flexibility…
Q: Question 9 Given the below network, what is the maximum flow from node 1 to node 6? 12 20 10 18 16…
A: Maximum flow issues in optimization theory involve finding a viable flow through a flow network that…
Q: Q1: Determine the critical path, the critical activities and the project completion time.…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: When determining whether a partnership exists, which of the following factors would a court…
A: ANSWER : A partnership is arrangement between two or more people to look after a business…
Q: Define and briefly discuss the concept of labour relations. In 10 bullet points
A: Labor relations refers to the process through which employers and employees, management, and unions…
Q: How many containers should be authorized for January? 22 containers. (Enter your response rounded up…
A: Given: Average demand d 4200 Average waiting time per unit w 0.5 Average processing time per…
Q: 4.3 If you were to play a simulation game next term, also in a group, what would you do differently?
A: Nowadays Simulation Games have become a significant instrument of management curriculum along with…
Q: Production facilities include the factory, production machines and tooling, material handling…
A: Production systems may be described as transformation processes, processes that convert resources…
Q: Read the situation below on decision making and see how it can help Eng’r. Estabillo solve his…
A: As per the given case details, Mr. R is the founder of a construction firm. The firm has been…
Q: a) Draw a precedence diagram of this operation. b) Given the demand, what is the cycle time for this…
A: Tasks are assigned to workstations on the basis of total cycle time and minimum number of…
Q: a. Are annual sales increasing or decreasing? By how much? Annual sales are by bottles per year. b.…
A: Forecasting is a technique used to predict future outcomes on the basis of past data. In businesses…
Q: ABC company, a textile manufacturing company, has recorded defects in their production for a month…
A: Given: Defect FREQ Misprinting 55 Shade Variation 38 Uneven Dyeing 10 Drop Stitching 5…
Q: What are the many tools that are used for scheduling, such as Gantt charts and PERT/CPM charts?
A: A project schedule is described as a mechanism through which task status can be known and the way…
Q: 2. The OPTIMIS factory produces cars, with the body assembly time requirements for two types of cars…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: Give the effect of the perfection of a contract? Explain by giving examples or cases that you know
A: When the components of consent, object, and consideration are present, a contract is called…
Q: What is the average inventory held at each warehouse? What is the annual inventory cost (holding +…
A: Inventory management is the process of managing the number of goods a business has in stock. The…
Q: What factors contribute to a project's success or failure during implementation? In your opinion,…
A: Project implementation refers to the process in which a project is launched or starts its working on…
Q: a) Draw the precedence diagram and assign tasks using five workstations. b) What is the efficiency…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: The following payment period ratios, averaged, for borrowings were reported for the year 2021 y five…
A: Payment period ratio indicates the time required to repay the borrowings. In other words it is the…
Q: T-Shirts Unlimited is a retailer that sells every kind of T-shirt imaginable. The different types of…
A:
Q: McDonald's is in downstream of McCain which is in the upstream of the potato farmers. Select one: O…
A: A supply chain is described as the various types of resources, people, and activities that are…
Q: analyse how the principles of Just in Time and Lean have been implemented within the PRODUCTION and…
A: The implementation of Just in Time and Lean principles within a fast food restaurant like Company M…
Q: Calculate expected values for large and small expansions. What should Dairy May Farms do? EV small…
A: Decision tree is a diagramatical representation of various alternative for a project corresponding…
Q: Wang Ceramics makes ceramic pots for a chain of stores. The output and cost figures over the past…
A: Given data is Materials cost = RM3.5 per pound Labor cost = RM11 per hour
Q: A nutritionist is planning a menu consisting of two main foods A and B. Each ounce of A contains 2…
A: Let x be ounces of A y be ounces of B Since the cost is given, we have to minimize them. (i) Ounce…
Q: Q2: The activities involved in the construction of a certain project are given in the table below.…
A: Based on the given activities and dependency, the following diagram can be prepared. Possible paths…
Q: What is good and what can be improved regarding this role as a nature manager? Explain
A: Nature mangement refers to the set of activities of a management which enables a manager to perform…
Q: Project X has the data points below. The schedule performance index (SPI) for task P is .. Task BCWS…
A: Here, we first understand the values given for each task BCWS = Budgeted Cost of work scheduled -…
Q: Please give two examples of each of the following sources of errors. a. Instrumental…
A: Errors refers to the mistakes which are caused either due to negligence or due to intentionally.
Q: Can someone explain me this Context Diagram?
A: The diagram is for a firm named Tagpuan Resto Bar System. There are three areas in which the firm…
Q: What about part D?
A: Production is the process in which inputs are combined to have the required output. It includes a…
manufacturer operates 8 hours per day for 340 days per year, and has a demand of 2,000 units per day. There are four production cycles per day. Assume the following: 7,700 units produced per day, holding cost per unit is $5 per year, labor rate to do line set-ups is $13 per hour. With quick set-ups, the production line must be quickly re-organized.
a. What is the target set-up cost?
b. What is the set-up time in minutes?
Step by step
Solved in 3 steps with 2 images
- Guesstimate how much work-in-process inventory they would expect to see in a production line that produces ambulances.Which of the following is a fixed cost? a) Direct materials b ) Direct labor c) Rent on factory building d) Variable manufacturing overhead21 A process where goods are manufactured according to confirmed orders: Select one: a. Demand push b. Continuous inventory c. Just in Time d. Product pull
- Eastwood Cake Factory sells chocolate cakes, birthday cakes, and specialty cakes. The factory is experiencing a bottleneck and is trying to determine which cake is most profitable. Even though Eastwood may have to limit its orders, it is concerned about customer service and satisfaction. Line Item Description Chocolate Cake Birthday Cake Specialty Cake Sales price $20.00 $45.00 $60.00 Variable cost per cake $5.00 $12.00 $20.00 Hours needed to bake, frost, and decorate 1 hour 2.5 hours 2 hours a. Compute the contribution margin per hour per cake. If required, round your answers to two decimal places. Cake Amount Chocolate cake $fill in the blank 1 Birthday cake $fill in the blank 2 Specialty cake $fill in the blank 3 b. Determine which cakes the company should try to sell more of first, second, and then last. Rank Cake 1st: 2nd: 3rd:Make legs Finish furniture Assemble Cut wood and ship Make topsWhy is a process table needed in a timesharing system and what are the field in a typical process table entry?
- C&A Furniture uses a four-step process to make its famous wood table: Processing Time Process Milling Table top Milling Table stand Assembly Finishing The milling machine requires a setup time of 30 minutes to make table tops and a changeover time of 30 minutes to make table stands. If the batch size is 10, what is the capacity of the process in tables per minute? A) 0.077 B) 0.05 C) 0.067 10 5 15 20 D) 0.048A.J.’s Wildlife Emporium manufactures two unique birdfeeders (Deluxe and Super Duper) that are manufactured and assembled in up to three different workstations (X, Y, Z) using a small batch process. Each of the products is produced according to the flowchart in Figure. Additionally, the flowchart indicates each product’s price, weekly demand, and processing times per unit. Batch setup times are negligible.A.J. can make and sell up to the limit of its weekly demand and there are no penalties for not being able to meet all of the demand. Each workstation is staffed by a worker who is dedicated to work on that workstation alone and is paid $16 per hour. The plant operates 40 hours per week, with no overtime. Overhead costs are $2,000 per week. Based on the information provided, as well as the information contained in the flowchart, answer the following questions. a. Using the traditional method, which bases decisions solely on a product’s contribution to profits and overhead, what is the…Create a business scenario/description. 2) Based on the business description created, construct an Order Processing flow chart that is appropriate for the business.
- Shown below is a partially completed MPS record for hand drills. a. Develop the MPS record for the hand drills. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: Hand drills Quantity on Hand: 30 Forecast Customer orders (booked) Projected on-hand inventory MPS quantity MPS start 1 15 20 N 40 25 3 15 15 Week Available-to- promise (ATP) inventory b. A distributor of the hand drills places an order for 15 units. What is the appropriate shipping date for the entire order? The order should ship on week (Enter your response as an integer.) 4 20 20 Order Policy: 60 units Lead Time: 1 week 5 55 0 6 35 0Table B shows a partially completed MPS record for ball Develop the MPS for ball Four customer orders arrived in the following sequences (Table B). Table A Order Quantity Week desired 1 500 4 2 400 5 3 300 1 4 300 7 Assume that you must commit to the orders in the sequence of arrival and cannot change the desired shipping dates or your MPS. Which orders should you accept? Table B Item: Ball bearings Quantity on hand: 400 Order policy: 500 units Lead time: 1 week Week 1 2 3 4 5 6 7 8 9 10 Forecast 550 300 400 450 300 350 200 300 450 400 Customer order booked 300 350 250 250 200 150 100 100 100 100 Projected on-hand inventory MPS quantity 500 MPS start Available to promise (ATP)Giving examples distinguish between make-to-stock and make-to-order suppy chain processes.