Management wants to design an assembly line that will turn out 800 videotapes per day. There will be eight working hours in each day. The industrial engineering staff has assembled the information below: Task a Time (min. .2 .2 .4 .1 .3 .2 .1 .2 Immediate Predecessor none a none none c, d be none £ g (A) Determine the maximum and minimum cycle time. (B) Determine the optimum cycle time. (C) What is the minimum number of stations needed?
Q: etermine the cycle time and the minimum number of stations
A: A network diagram is visual representation of project which helps to identify the Activity relations…
Q: 1. An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total…
A: Given data, Longest Task = 2.4 minutes Total time for all task = 18 minutes Operating Time = 450…
Q: Performance Task Output 2: Make a single page report about the incident with all the details and 4M…
A: 4M are the part of fishbone diagram analysis, where there are bones as the head like a machine,…
Q: 4. B.G.H.M. Inc. is a local buniness involved in many aspecta of the food supply industry. As demand…
A: PERT: Program evaluation and review technique is an approach used in project management to represent…
Q: J.C. Howard’s medical testing company in Kansas wishes to assign a set of jobs to a set of machines.…
A: Job A B C D 1 7 9 8 10 2 10 9 7 6 3 11 5 9 6 4 9 11 5 8
Q: Shown below are the tasks, times, and precedence requirements for the work required to assemble a…
A: This is question of assembly line balancing where we assign a task to each workstation as per the…
Q: TIME (IN HOURS) PREDECESSOR(S) IMMEDIATE CODE ACTIVITY Planning DESCRIPTION A Find location; 20 None…
A:
Q: Shown below are the tasks, times, and precedence requirements for the work required to assemble a…
A: The production line is the set of machines in a systematic manner for assembling of product in an…
Q: A continuous improvement team of the production wanted to know the time to assemble one of the…
A: As per Bartleby guidelines, we can only solve one question at a time...Kindly upload the other…
Q: 5. Management wants to design an assembly line that will turn out 800 videotapes per day. There will…
A: Note- We’ll answer the first three subparts of the question since the exact one wasn’t specified.…
Q: What are the 5Ss? Why does the list of the 5Ss sometimes have seven elements? How can you apply 5S…
A: 5S is a framework for getting sorted out spaces so work can be performed proficiently, adequately,…
Q: snip
A: Balance Delay: Balance delay time is the amount of idle time on production assembly lines caused by…
Q: The operations manager of an instruments company is balancing an assembly line. The company needs to…
A: given,
Q: A production process at Kenneth Day Manufacturing is shown in Figure S7.9. The drilling operation…
A: As per the Bartleby guidelines, only the first three parts have been answered.
Q: (a) Develop the precedence diagram. (b) Compute the cycle time per unit in minutes (c) Determine the…
A: As per Bartleby guidelines, we can only solve the first three subparts of a question at a…
Q: H.W (2):- Draw Gantt chart for the following project and determine the duration of the project,…
A: Find the given details below: Activity Precedence Activity Quantity or Volume of the…
Q: Samantha’s Appliances has developed a new European-style convection oven that will be made on an…
A: given,
Q: 1. What is the advantages of having proper layout design in the business operations? do you think…
A: Question 1 Layout design concerns the actual situation of assets like hardware and storage spaces.…
Q: The following information is given about an assembly line. The desired output rate is 360 units per…
A: Given Information: Task Time (sec) Immediate Predecessor(s) A 30 - B 25 A…
Q: a) A manufacturer wishes to create a flow line which will produce 555 pumps/day (8 hrs/ day). The…
A:
Q: A manager wants to assign tasks to workstations as efficiently as possible and achieve an hourly…
A: Given- Production time in minutes = 60 minutes Demand units = 30 units
Q: California Gardens, Inc., prewashes, shreds, and dis-tributes a variety of salad mixes in 2-pound…
A: The monthly profit or loss if the company changes to the Hi-Speed shredder and sells 60,000 bags per…
Q: 1. An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total…
A: Note:-We’ll answer the first three subparts of the question since the exact one wasn’t specified.…
Q: Wolfgang Kersten Mfg. intends to increase capacitythrough the addition of new equipment. Two vendors…
A: Contribution margin = CM = Price – variable cost CM for X = 200-120= $80 CM for Y = 200-100= $100
Q: Table 10-23 shows the tasks required to assemble analuminum storm door and the length of time needed…
A: From the beginning of the first task to the finish of the last task, cycle time is the amount of…
Q: A company is setting up an assembly line to produce 192 units per 8-hour shift. The following table…
A: Note: - Since we can answer only up to 3 sub-questions we will answers questions a, b, and c for…
Q: 2. The production line of product X is described below. 504 units of product X must be produced…
A: The precedence diagram method (PDM) is a tool for planning project tasks. It's a method for creating…
Q: 4. Digital Eye must design an assembly line to produce a new line of slim digital cameras.…
A: Network Diagram:
Q: Figure 1 and Figure 2 show a procedure for the industrial ergonomics in factory. Explain the effect…
A: Ergonomics is described as a scientific discipline that is associated with having proper…
Q: Shown below are the tasks, times, and precedence requirements for the work required to assemble a…
A: A network diagram is a visual representation of a project which identify the activity relationship…
Q: Professional Image Briefcases is an exclusive producer ofhandcrafted, stylish cases. The company…
A: Solution a) The precedence diagram is shown below b) Flow time is sum of all work elements…
Q: Dr. Lori Baker, operations manager at Nesa Electro-nics, prides herself on excellent assembly-line…
A: I am answering first three sub-parts. Please post the rest of the questions separately.
Q: From the following data of information prepare the (a) Net- work diagram; (b) The Early Start (ES)…
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: Shown below are the tasks, times, and precedence requirements for the work required to assemble a…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: GIvethe flow diagram of an assembly line below, using a cycle time of 27 minutes, ywaing shortest…
A: Given cycle time = 2.70 mins
Q: TASK PRECEDENCE ΤΙME (MINUT) A Tan leather 30 B Dye leather A 15 C Shape case B 10 D Mold hinges and…
A: Given data will be as follows: Work Element Precedence Time (min) A Tan leather - 30 B Dye…
Q: Question in comments
A: (A) Following formula can be used to calculate the cycle time: Consider production time be 3600…
Q: c. Calculate the cycle time and draw the precedence graph and find the minimum possible number of…
A: Given Information: Working hours in a day =8 hours or 480 minutes Production output = 375 units per…
Q: Q2: Six processes are to be laid out in six areas along a long corridor at Linda Babat Accounting…
A: Every pair of connected nodes in the network is associated with a specific demand. The demand will…
Q: What is the difference between WBS (Work Breakdown Structure) and WBS dictionary?
A: Organizations have separate departments to carry out specific functions. Departmentalization helps…
Q: 1. The program with Pilipinas Liners, who should have control on it? Should it be FLIGHT, or Ms.…
A: Controlling is the managerial process in which standards are established and measuring the actual…
Q: The Action Toy Company has decided to manufacturea new train set, the production of which is broken…
A: Note: As per the Bartleby guidelines only the first three parts have been answered.
Q: a) What is Product Breakdown Structure (PBS)?
A: Product breakdown structure:- A product breakdown structure, sometimes called an RFP, is an outline…
Q: Table 1 Activity Predecessor Duration (weeks) A - 5 B A 4 C A 5 D B 6 E C 3 F D,…
A:
Q: Shown below are the tasks, times, and precedence requirements for the work required to assemble a…
A: A product line is a model of network diagram which contains the workstation allocation in it. Here,…
Q: 3. Figure 5.11 details the process flow for two types of custom-ers who enter Barbara’s Boutique…
A: Capacity in terms of operations management it is the out come of a project/process. The standard no.…
Q: 9 The following tasks are to be performed on an assembly line: TASKS THAT MINT PRICHDE TASK SucONDS…
A: Hi, we are supposed to answer 3 subparts at a time. Since you have not mentioned which subpart to…
Management wants to design an assembly line that will turn out 800 videotapes per day. There will be eight working hours in each day. The industrial engineering staff has assembled the information below:
Task
a
Time (min.
.2
.2
.4
.1
.3
.2
.1
.2
Immediate Predecessor
none
a
none
none
c, d be
none
£ g
(A) Determine the maximum and minimum cycle time.
(B) Determine the optimum cycle time.
(C) What is the minimum number of stations needed?
(D) Draw the precedence diagram.
(E) Assign tasks to stations in order of most following tasks first.
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 4 images
- Robot Manufacturing Optimization FAY Technologies is deciding whether it should begin production of a new toy robot. It has manufactured children’s toys before but nothing as advanced as its latest robot so historical data is at a minimum. The company believes that they can secure the materials for manufacture for between $65-85 per unit and labor costs would be between $15-25 per unit. Management’s expectations are that materials will cost $70 per unit and labor $25 per unit and that 800 units will be sold monthly. Should FAY decide to manufacture the robots in-house, maintenance of the factory machine would cost $15,000 per month. However, management has found that another alternative is for the company to outsource the labor for a flat rate of $35 per unit. The company expects to sell between 750-1000 units per month initially at a price of $149. Provide recommendations for FAE technologies that will maximize profit. Also include base, worst, and best case…Accompany makes two products (1&2) each product requires time on two machines (A&B). specification for each product is as follows. Product1 product2 Processing time on Machine A (hrs/unit) 2 2 Processing time on Machine B (hrs/unit) 1 2 Material and labour cost ( ksh/unit) 14 15 Selling price (ksh/unit) 16 18 Maximum possible sale (units) 130 150 The amount of time available on machine A is 360 hours and on machine B is 260 hours. Formulate the linear programme which, when…H3. Weber Optical, an eyeglass manufacturer, pays employees an incentive based on the average amount of work completed per processing 20 invoices per hour. An employee who processes 30 invoices would earn $15 per hour. Hence, Weber Optical pa many invoices an employee processes per hour. Which type of incentive pay does this scenario illustrate? O 1. rising differential 2. straight commission plan 3. straight piecework plan 4. standard hour plan Show proper step by step calculation
- 10 Collaboration and demand flow strategy are important components of SCM strategy. Select one: a. False b. Truens Management || fall20 Petroleum be produced from crude oil is considered a system Select one: O a. Continuous O b. Assembly O c Project O d. Job Shop O e. BatchCranston Company estimates the following overhead costs for the coming year: Equipment depreciation $160,000Equipment maintenance 60,000Supervisory salaries 40,000Factory rent 100,000Total $360,000 Cranston is also budgeting $600,000 in direct labor costs and 15,000 machine hours for the coming year.(a) Calculate the predetermined overhead rate using direct labor costs as the allocation base. (b) Calculate the predetermined overhead rate using machine hours as the allocation base.
- J 1 ue K Beth Zion Hospital has received initial certification from the state of California to become a center for liver transplants. The hospital, however, must complete its first 10 transplants under great scrutiny and at no cost to the patients with the hospital picking the expenses. The cost per hour of surgery is estimated to be $5,000. The very first transplant, just completed, required 27 hours. On the basis of research at the hospital, Beth Zion estimates that it will have an 75% learning curve. Using Table E.3, estimate the time it will take to complete: a) the 10th transplant hours (round your response to two decimal places). Learning Curve Coefficients Unit Number (N) 10 Unit Time .385 75% Total Time 5.589 Unit Time .477 80% Total Time 6.315 Unit Time .583 85% Total Time 7.116 Xsjoo g Enabled: Chapter 5 What-If Analysis for Linear . Saved HI ... Based on the following sensitivity report, how much should the firm be willing to pay for 76 more units of Resource_C? Variable Cells Final Objective Allowable Allowable Cell Name Value Reduced Cost Coefficient Increase Decrease se $B$2 $B$3 $B$4 Product 1 Product_2 Product_3 -2 5 1E+30 175 7 1E+30 -1.5 9. 1.5 1E+30 Constraints Final Shadow Constraint Allowable Allowable Cell Name Value Price R.H.Side Increase Decrease SH$9 Resource A Resource B Resource C 100 1E+30 10 SH$10 525 800 1E+30 220 SH$11 700 1.36 700 180 69 (Round your answer to 2 decimal places.) Units of Resource_C Mc Graw Hill < Piey 5 of 5 NeOperations Management Fall20 ?Which of the following is considered as a design decision 18 Jlgw لم يتم الاجابة عليه اخترأحد الخيارات 1.50 jo jll a. Market share growth O b. Inventory management O Lis ple P السؤال C. Quality control O d. Facility layout O Previous page 19:55 ) ENG 15 01/12/2020
- Cox Electric makes electronic components and has estimated the following for a new design of one of its products. . Fixed cost-$21,000 • Material cost per unit $0.17 Labor cost per unit = $0.11 Revenue per unit $0.68 Note that fixed cost is incurred regardless of the amount produced. Per-unit material and labor cost together make up the variable cost per unit. Assuming that Cox Electric sells all that it produces, profit is calculated by subtracting the fixed cost and total variable cost from total revenue. Construct an appropriate spreadsheet model to find the profit based on a given production level and use the spreadsheet model to answer these questions. (a) Construct a one-way data table with production volume as the column input and profit as the output. Breakeven occurs when profit goes from a negative to a positive value; that is, breakeven is when total revenue the total cost, yielding a profit of zero. Vary production volume from 0 to 100,000 in increments of 10,000. In which…Consider the planned construction of new office building in a downtown area of a large city when office space in in surplus demand (i.e. more office space than users). 1. Explain how the analysis would change if the office were in high demand.Here are four samples A В of business cards. Juan Dea Cue, MD pediatrician CLEAR VISON EYE CEN了! Identify what is wrong with the design of each card and suggest HM Mall of Canlubang 3rd Floor Buildling C improve to ways them. Clinic Schedule: MWF 8:00 – 12:00 Phone: 0909 090 0909 0606 000 6666 Your child's health is my concerm! Your chilld's health is my concern! I can provide you with the best and mest premising breakthrough trends and Maria O. Clara Gigi San Simone: Decorator nteriotr skop at 777 Writter. Editr. Content Creatress. Jveeuntatn Avenue, Bukidnon. Our phone number is (777) 077.7700.. Our email adresss is GGSS. Hurry and avail of sur latest quarantine diseount with free PPE! 'All these bareause I eare for you now and ferever! I specializes in all kind of content. Visit my FB page OCLARA CARD Issues in the Design Suggestions for Improvement A B C D