In a recent review meeting, the client has insisted you complete the project on time. You would like to get the Estimate at Completion for your project, so you perform Earned Value analysis and get the following data: the value of the completed work is $176,500; you have spent $223,500; and the planned value is $229,100. The initial budget of the project is $419,500. What is EAC? Your answer should be rounded to the nearest whole number, for example 123,456.73 should be rounded to 123,457. A/
Q: Vollmer Manufacturing makes three components for sale to refrigeration companies. The components are…
A: Also, the demand for 550 units of component 1 must be satisfied. Convert available hours in minutes…
Q: 21. Calculate the weighted score for each location (A, B, C, and D) shown in Table 13.6. Which…
A: Operation management is performed in each manufacturing organization. It all deals with the…
Q: Kelson Sporting Equipment, Inc., makes two different types of baseball gloves: a regular model and a…
A:
Q: a) Based on the given information regarding the activities for the project, the project completion…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: Why is payback often used as the sole method of analyzing a proposed small project? a. It is the…
A: The time needed to recoup the original investment in an investment is known as the payback period.…
Q: Draw the Schedule Network diagram and durate. Ⓒ3 Col Colate for word pass Calculate Back Word paes
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: A sample of twenty automobiles was taken, and the miles per gallon (MPG), horsepower, and total…
A: Sample No MPG Horsepower Weight 1 44 67 1,844 2 44 50 1,998 3 40 62…
Q: One unit of A is made of two units of B and one unit of C. B is made of three units of D and one…
A: Based on the information given, the product tree structure is as follows.
Q: Tesla Corporation has three different factories (A, B and C) where they make Premium Electric…
A: Transshipment is a special category of linear programming problem wherein the optimal solution is…
Q: Can you assist me with Problem 7 errors. Thank you greatly
A: The errors are given below. Incorrect gross requirements of item E in the 5th period Incorrect net…
Q: Which of the following aspects of supply chain management have strong connections? (Check all that…
A:
Q: 5.Which of the following involves granting a foreign entity the right to produce and sell the firm's…
A: Ans) Outsourcing means not producing parts by own , but giving orders to external suppliers and buy…
Q: Hi, the answer is incorreect for the x,y nd optimal profit. Any help appriciated immediately as this…
A: There was a small mistake in the constraint, x + y >= 150 It is mentioned in the question that…
Q: Read the article below and answer the questions that follow. South Africa’s indigenous rooibos tea…
A: Supply chain Linkages: Supply chain is defined as there is a chain between from raw…
Q: What is the definition of synergy is (do not use a Google definition)
A: Synergy - The term synergy is open to multiple interpretations based on context and subject. For…
Q: The accounts receivable department at Rick Wing Manufacturing has been having difficulty getting…
A: Given data: Sample size = 100 No. of samples taken=10 Σn = 10×100 = 1000 Formulae used: P…
Q: 4. You have prepared the project information that is given below: Activity Predecessor Normal Time…
A: Find the given details below: Activity Predecessor Normal Time Normal Cost Crash Cost Crash time…
Q: a) The expected completion time for this project is ___ days (enter your response as a whole…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: Incorporating flotation costs into the analysis of a project will : a. increase the initial cash…
A: Explanation : Flotation costs increase the initial outlay of money because the company must raise…
Q: 3 examples of offshore outsourcing for an educational institution in Morocco
A: Morocco, Kingdom of Opportunities :Basic infrastructure-quality line with high international…
Q: Southland Corporation's decision to produce a new line of recreational products has resulted in the…
A: Decision-making is influenced by an organization as per the degree of certainty involved in this. In…
Q: A small metal shop operates 10 hours each day, producing 100 parts/hour. If productivity were…
A: Operating days = 10 Production hour = 100 Increased productivity = 20%+100 = 120
Q: In what way services generally considered more difficult to market ? Cite one reason or attribute…
A: Marketing a service, by and large, is more difficult to market. A few examinations: Setting up a…
Q: What is Logistics Management and provide an example of it
A: The term "logistics" is used more widely to describe the process of organizing and transferring…
Q: California Gardens, Inc., prewashes, shreds, and distributes a variety of salad mixes in 2-pound…
A: The quantity at which the profit gained under both options is the same is known as the crossover…
Q: A shirt manufacturer buys cloth by the 100-yard roll from a supplier. For setting up a control chart…
A: Process control refers to the capacity to observe and modify a process to get the desired result. It…
Q: How do I obtain the answer for part b?
A: Decision variable: Suppose-F be the no. of Fliptop Model marking pens to be manufacturedT be the no.…
Q: 13-2. (Pareto Chart & Fishbone Diagram). Smith, Schroeder, and Torn (SST) is a short-haul household…
A: Given data is
Q: Q2.2. What reorder point should be?
A: Inventory management is the process of ordering, storing, using, and selling the inventory of the…
Q: Employee Wanda Trews was working in the manufacturing facility at Coves Industrial. The employees of…
A: The detailed solution is given in Step 2
Q: What is waste production and its significance?
A: Production of waste indicates the use of materials and energy as well as the depletion of both…
Q: true or false? Just type T or F after the arrow. 1. An employer must report every workplace injury…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: Kidnly answer the following and include steps: Financial planner Minnie Margin has a substantial…
A: Objective function=(R1−20)2+(R2−22)2+(R3−8)2+(R4+2)2 Constraints: (i) 22.37IS + 15.48LC + 17.42MC +…
Q: The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements…
A: Find the Calculation methods below: Average Monthly demand = Total DemandNo. of monthsOutput…
Q: IN THE MID-1960S, WALT DISNEY’S DREAM was to build a family resort destination like no other. The…
A: Forecasting is a technique to predict future value. It is useful to predict future demand, sales, or…
Q: Employee Wanda Trews was working in the manufacturing facility at Coves Industrial. The employees of…
A: The detailed solution is given in Step 2
Q: Using virutal commiunications concepts. List five to ten “Things to Do” and five to ten “Things to…
A: Project communication is not as similar to normal or routine communication. It involves many people,…
Q: All of the following costs are likely to decrease as a result of better quality EXCEPT: A.scrap…
A: A. Scrap costs:- The cost for which the fixed asset can be sold after full depreciation. If the…
Q: Boston Electric Generators has been getting many complaints from its major customer, Home Station,…
A: The scatter diagram graphs pairs of numerical data, with one variable on each axis, to look for a…
Q: ?Q) Solve the LPP problems below by using big M-Method MIN Z=8X1+2X2 S.T X1+2X2=66 X1+6X2268…
A: Given LLP- Min Z = 8x1 + 2x2Subject to-x1 + 2x2= 66x1 + 6x2≥ 68x1 + 4x2≤82x1,x2≥0
Q: Seneca Hill Winery recently purchased land for the purpose of establishing a new vineyard.…
A: This is a diagrammatic representation of decisions available to choose from considering the…
Q: Given: Demand = 1248 items per year, Inventory period or Time between orders = 13 weeks. Q5.1.…
A: Economic order quantity (EOQ) is the optimal order quantity that helps in minimizing the total…
Q: An office supply company is trying to determine the order quantity for Mt. White fountain pens that…
A: Given data is Annual demand (D) = 5000 units Unit cost = $50 Order cost (S)= $75 Holding cost (H) =…
Q: The activity list shown below represents the activities, the job logic and activities’ durations of…
A: Activity On Arrow (AOA) network is a type of convention used to present network diagram i.e., to…
Q: Which of the following is true regarding the inflow of FDI? A. Even though developing nations…
A: The amount of inward direct investment from non-resident entrepreneurs throughout the reporting…
Q: Question 12 kan Match the following terms with their descriptions: I. X-axis II. Y-axis III.…
A: (I) X-axis The horizontal line of a chart where a series of data is plotted to show the categorical…
Q: How does the Oracle, Walmart, and TikTok deal potentially impact US based tech companies such as…
A: Huge amount of money is spent in todays' scenario for the purpose of marketing and promotion each…
Q: The following payoff table shows profit for a decision analysis problem with two decision…
A: Given data: Decision Alternative State of nature S1 S2 S3 d1 260 110 35 d2 110 110 85…
Q: What products make up inventory?
A: Inventory management is the process of ordering, storing, using, and selling the inventory of the…
Q: The Problem The company business is production of porcelain The products are plates, cups…
A: Decision variable: Suppose-P be the no. of plates to be producedC be the no. of cups to be producedT…
Step by step
Solved in 3 steps
- Give an explanation of how earned value management (EVM) may be used to keep expenses under control and monitor the overall effectiveness of a project, and then hypothesise as to why it is not utilised more often. How can one determine if the data for cost variation, schedule variance, cost performance index, and schedule performance index are healthy or unhealthy? What are some basic rules of thumb?Your vice president asked you what the Estimate at Completion (EAC) will be for a small project you are working on. You were given a budget of S50,000, and to date you have spent $40,000 but only completed $30,000 worth of work. You are sure the future work will be accomplished at the planned rate. What is the EAC ?Justify the use of earned value management (EVM) to control expenses and monitor the effectiveness of a project, and speculate as to why it is not used more often. How can one determine if a cost variation, a schedule variance, a cost performance index, or a schedule performance index is favorable or unfavorable? What are some general criteria to follow?
- Projected costs are calculated during the planning phase of a project and must be approved before work begins. 1. How does a project engineer prepare the projected costs? Describe the procedure in detailed form. As the project plan is executed, expenses are documented and tracked so things stay within the cost management plan. 2. How are expenses documented and tracked? 3. As the project manager, what will you do if the expenses go beyond the cost management plan? Once the project is completed, predicted costs vs. actual costs are compared, providing benchmarks for future cost management plans and project budgets. 4. How will you use the results of the comparison between the predicted and actual costs for your future projects?[Project Management] Because a housing project is running late, the developer will need to complete and deliver the houses as quickly as possible. You and your management team are responsible for mitigating the situation by including a time-cost trade-off analysis into the project. You will need to include the following: Normal crash Activity Prior Days cost, RM Days cost, RM A 7,000 7,000 B A 8,000 9 8,000 B 14 6,000 12 11,000 D B 18 5,000 11 8,500 E C,D 12 8,000 12 8,000 E 20 6,000 16 12,000 E 7,000 7,000 E 11 11,000 7 15,000 G, H 10 15,000 21,000 7 I, F 6 9,000 6 9,000 Construct a network diagram (PDM), including activity early start, late start, early finish, late finish and float.given the following information for a 1-year project, answer the following questions. Assume you have actual and earned value data at the end of the second month. Recall that PV is the plan value, Evie is the earned value, AC is the actual cost, and BAC is the budget at completion.pv =$ 23,000ev = 20,000ac= 25,000bac = 130,000a. what is the cost variance, schedule variance, cost performance index CPI and schedule performance index SPI for the project?B. how is the project progressing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?C. use the CPI to calculate the estimate at completion EAC for this project.d. use the SPI to estimate how long it will take to finish this project.e. sketch the earned value chart for this project, use the figure below as a guide. Assume the data for month one is half of the values given for Pv, Ev and ac at the end of month 2
- If earned value management (EVM) is so beneficial, why is it not used more often? Explain how it may be used to track costs and evaluate the success of a project. When evaluating cost variation, schedule variance, cost performance index, and schedule performance, what criteria should be used as a starting point?You are developing a performance progress report for a project you are managing. The following time-phased budget was developed earlier in the planning stage and is being used as the standard against which the project performance is measured. Work Packages W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 4 10 6 A B C Total 1 6 8 4 10 6 1 6 8 5 6 10 8 5 6 8 88 10 3 3 At the end of Week 8, activity "C" is 50% complete. What is the Earned Value of this activity? Use two decimal places in your calculations.You are developing a performance progress report for a project you are managing. The following time-phased budget was developed earlier in the planning stage and is being used as the standard against which the project performance is measured. Work Packages A B C Total W1 4 4 W2 8 8 W3 2 W4 5 5 W5 9 19 W6 6 6 You are analyzing the project performance at the end of Week 5. Activity "C" is 80% complete and its actual cost is 15. What is the schedule variance of this activity? Use two decimal places in your calculations.
- The use of probability curves to describe a project estimate helps to deal with: Your answer: The impact of uncertainty on demand. The impact of uncertainty on estimating times. The impact of uncertainty on costs. The impact of uncertainty on satisfaction.The decision was made by JMP management that a certain critical development in the overall project will be subcontracted-out to a vendor. JMP has issued a six-month cost plus fixed fee contract for that development, and you are the vendor's project manager. The approved JMP budget for your development is $500,000. A recent Earned Value Analysis that your firm (the vendor) has done shows that you will complete the project four weeks ahead of time, thus depriving your firm of $80,000 of billable time. Among your options are: 1. Since it was the approved budget, go ahead and bill JMP for the entire $500.000. 2. Inform JMP of the project status and completion date, and ask if they'd like to add any features to account for the monies spent. 3. Inform JMP of the project status and completion date. 4. Bill JMP for the $500,000 by adding more work at the end of the project.Calculate the cost budget for the project below with a contingency reserve of 20% is applied to the cost estimate and 4% management reserve is applied to the cost baseline. Control Account Cost /$ Project Management 1,000,000 Design 4,000,000 Execution 10,200,000 Certification 600,000 Marketing 4,500,000 Launch 320,000 You have a budget at completion of $2500. You had planned to have $2200 worth of work accomplished by now. However, you have just found out that you are only 60% complete with the task. What is your SV? A project was budgeted at $1,000,000. Meanwhile, the project is executed, and the following current figures have been assessed: PV: $500,000 EV: $450, 000 AC: $550, 000 Assuming that the cost variance was…