For the Toy Car table above, what are the Planned Order Receipts in the week of 8/31? For the Toy Car table above, what are the Planned Order Releases in the week of 9/21? For the Wheel Assembly table above, what are the Gross Requirements in the week of 9/7? For the Wheel Assembly table above, what is the Projected On-Hand Inventory in the week of 8/31? For the Wheel Assembly table above, what are the Net Requirements in the week of 8/24? For the Axle table above, what are the Gross Requirements in the week of 9/7? For the Axle table above, what are the Gross Requirements in the week of 9/14? For the Axle table above, what are the Planned Order Releases in the week of 8/17?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
  1. For the Toy Car table above, what are the Planned Order Receipts in the week of 8/31?
  2. For the Toy Car table above, what are the Planned Order Releases in the week of 9/21?
  3. For the Wheel Assembly table above, what are the Gross Requirements in the week of 9/7?
  4. For the Wheel Assembly table above, what is the Projected On-Hand Inventory in the week of 8/31?
  5. For the Wheel Assembly table above, what are the Net Requirements in the week of 8/24?
  6. For the Axle table above, what are the Gross Requirements in the week of 9/7?
  7. For the Axle table above, what are the Gross Requirements in the week of 9/14?
  8. For the Axle table above, what are the Planned Order Releases in the week of 8/17?
Toy Car Final Assembly
8/3
8/10
8/17
8/24
8/31
9/7
9/14
9/21
9/28
Gross Requirements
1100
900
2200
2500
Scheduled Receipts
290
600
390
Projected On-Hand Inv.
240
Net Requirements
Planned Order Receipts
Planned Order Releases
Lead Time (in weeks)
Lot Size
80
Wheel Assembly
8/3
8/10
8/17
8/24
8/31
9/7
9/14
9/21
9/28
Gross Requirements
Scheduled Receipts
1700
1800
2000
Projected On-Hand Inv.
Net Requirements
1,000
Planned Order Receipts
Planned Order Releases
Lead Time (in weeks)
1
Lot Size
250
Axle
8/3
8/10
8/17
8/24
8/31
9/7
9/14
9/21
9/28
Gross Requirements
Scheduled Receipts
700
1900
Projected On-Hand Inv.
Net Requirements
Planned Order Receipts
700
Planned Order Releases
Lead Time (in weeks)
2
Lot Size
300
Transcribed Image Text:Toy Car Final Assembly 8/3 8/10 8/17 8/24 8/31 9/7 9/14 9/21 9/28 Gross Requirements 1100 900 2200 2500 Scheduled Receipts 290 600 390 Projected On-Hand Inv. 240 Net Requirements Planned Order Receipts Planned Order Releases Lead Time (in weeks) Lot Size 80 Wheel Assembly 8/3 8/10 8/17 8/24 8/31 9/7 9/14 9/21 9/28 Gross Requirements Scheduled Receipts 1700 1800 2000 Projected On-Hand Inv. Net Requirements 1,000 Planned Order Receipts Planned Order Releases Lead Time (in weeks) 1 Lot Size 250 Axle 8/3 8/10 8/17 8/24 8/31 9/7 9/14 9/21 9/28 Gross Requirements Scheduled Receipts 700 1900 Projected On-Hand Inv. Net Requirements Planned Order Receipts 700 Planned Order Releases Lead Time (in weeks) 2 Lot Size 300
Bill of Material for Toy Car Assembly
Toy Car
Final Assembly
Wheel Assembly
(2 required)
Body
(1 required)
Axle
Wheel
(1 required)
(2 required)
MS.52 A toy company needs to calculate material requirements for its top-selling toy car. The graphic above shows the bill of material for this item. Below
are three MRP tables for the top-level assembly (the car) and some of its components:
Toy Car Final Assembly
8/3
8/10
8/17
8/24
8/31
9/7
9/14
9/21
9/28
Gross Requirements
Scheduled Receipts
1100
900
2200
2500
290
600
390
Projected On-Hand Inv.
240
Net Requirements
Planned Order Receipts
Planned Order Releases
Lead Time (in weeks)
1
Lot Size
80
Transcribed Image Text:Bill of Material for Toy Car Assembly Toy Car Final Assembly Wheel Assembly (2 required) Body (1 required) Axle Wheel (1 required) (2 required) MS.52 A toy company needs to calculate material requirements for its top-selling toy car. The graphic above shows the bill of material for this item. Below are three MRP tables for the top-level assembly (the car) and some of its components: Toy Car Final Assembly 8/3 8/10 8/17 8/24 8/31 9/7 9/14 9/21 9/28 Gross Requirements Scheduled Receipts 1100 900 2200 2500 290 600 390 Projected On-Hand Inv. 240 Net Requirements Planned Order Receipts Planned Order Releases Lead Time (in weeks) 1 Lot Size 80
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.