Flexible Budgeting and Variance Analysis I Love My Chocolate Company makes dark chocolate and light chocolate. Both products require cocoa and sugar. The following planning information has been made available: Standard Amount per Case   Dark Chocolate Light Chocolate Standard Price per Pound Cocoa 11 lb.   8 lb.   $4.7   Sugar 9 lb.   13 lb.   0.6   Standard labor time 0.4 hr.   0.5 hr.           Dark Chocolate Light Chocolate Planned production 5,200 cases   11,700 cases   Standard labor rate $15 per hr.   $15 per hr.   I Love My Chocolate does not expect there to be any beginning or ending inventories of cocoa or sugar. At the end of the budget year, I Love My Chocolate Company had the following actual results:   Dark Chocolate Light Chocolate Actual production (cases) 4,900 12,200   Actual Price per Pound Actual Pounds Purchased and Used Cocoa $4.8   152,300   Sugar 0.55   197,600     Actual Labor Rate Actual Labor Hours Used Dark chocolate $14.6 per hr.   1,780   Light chocolate 15.4 per hr.   6,250   Required: Prepare the following variance analyses for both chocolates and total, based on the actual results and production levels at the end of the budget year: Direct materials price variance, direct materials quantity variance, and total variance. Direct labor rate variance, direct labor time variance, and total variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. If there is no variance, enter a zero. a.   Direct materials price variance $fill in the blank 1     Direct materials quantity variance $fill in the blank 3     Total direct materials cost variance $fill in the blank 5           b.   Direct labor rate variance $fill in the blank 7     Direct labor time variance $fill in the blank 9     Total direct labor cost variance $fill in the blank 11

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter8: Standard Costs And Variances
Section: Chapter Questions
Problem 10PB: Use the following standard cost card for 1 gallon of ice cream to answer the questions. Actual...
icon
Related questions
Topic Video
Question

Flexible Budgeting and Variance Analysis

I Love My Chocolate Company makes dark chocolate and light chocolate. Both products require cocoa and sugar. The following planning information has been made available:

Standard Amount per Case
  Dark Chocolate Light Chocolate Standard Price per Pound
Cocoa 11 lb.   8 lb.   $4.7  
Sugar 9 lb.   13 lb.   0.6  
Standard labor time 0.4 hr.   0.5 hr.      

 

  Dark Chocolate Light Chocolate
Planned production 5,200 cases   11,700 cases  
Standard labor rate $15 per hr.   $15 per hr.  

I Love My Chocolate does not expect there to be any beginning or ending inventories of cocoa or sugar. At the end of the budget year, I Love My Chocolate Company had the following actual results:

  Dark Chocolate Light Chocolate
Actual production (cases) 4,900 12,200
  Actual Price per Pound Actual Pounds Purchased and Used
Cocoa $4.8   152,300  
Sugar 0.55   197,600  
  Actual Labor Rate Actual Labor Hours Used
Dark chocolate $14.6 per hr.   1,780  
Light chocolate 15.4 per hr.   6,250  

Required:

Prepare the following variance analyses for both chocolates and total, based on the actual results and production levels at the end of the budget year:

  1. Direct materials price variance, direct materials quantity variance, and total variance.
  2. Direct labor rate variance, direct labor time variance, and total variance.

Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. If there is no variance, enter a zero.

a.   Direct materials price variance $fill in the blank 1  
  Direct materials quantity variance $fill in the blank 3  
  Total direct materials cost variance $fill in the blank 5  
       
b.   Direct labor rate variance $fill in the blank 7  
  Direct labor time variance $fill in the blank 9  
  Total direct labor cost variance $fill in the blank 11  

2.  The variance analyses should be based on the   amounts at   volumes. The budget must flex with the volume changes. If the   volume is different from the planned volume, as it was in this case, then the budget used for performance evaluation should reflect the change in direct materials and direct labor that will be required for the   production. In this way, spending from volume changes can be separated from efficiency and price variances.

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Performance measurements
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College