Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. According to SPT, what is the average flow time? Round your answer to one decimal places. |Processing Time (days) Job A Due Date 10 12 B 4 3 6 D E 7 7 5 20

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
icon
Concept explainers
Topic Video
Question
100%
Five jobs are ready for processing at time zero through a workstation. The details of
the processing time and the due date of completion is provided in the following
table. According to SPT, what is the average flow time? Round your answer to one
decimal places.
Job
Processing Time (days)
Due Date
A
10
12
B
4
3
6
7
7
E
5
20
Your Answer:
Answer
Transcribed Image Text:Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. According to SPT, what is the average flow time? Round your answer to one decimal places. Job Processing Time (days) Due Date A 10 12 B 4 3 6 7 7 E 5 20 Your Answer: Answer
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 4 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,