Chuck’s Custom Boats (CCB) builds luxury yachts to customer order. CCB has landed a contract with a wealthy customer. Relevant data are shown in the table below. The complication is that the customer wants delivery in 32 weeks or he will impose a penalty of $375 for each week his yacht is late. Activity Immediate Predecessor Normal Time (NT) Weeks Crashing Cost   1st Week 2nd Week A ― 9 $410 $415 B A 7 125 -- C A 5 45 45 D B 4 300 350 E C 6 50 -- F D, E 5 200 225 G F 8 -- -- H F 7 85 90 I G 6 90 -- Construct a network diagram for the project Indicate the critical path when normal activity times are used. Develop a crashing schedule. Note: No activity can be crashed more than two weeks.

Marketing
20th Edition
ISBN:9780357033791
Author:Pride, William M
Publisher:Pride, William M
Chapter19: Pricing Concepts
Section: Chapter Questions
Problem 6DRQ
icon
Related questions
Question

Chuck’s Custom Boats (CCB) builds luxury yachts to customer order. CCB has landed a contract with a wealthy customer. Relevant data are shown in the table below. The complication is that the customer wants delivery in 32 weeks or he will impose a penalty of $375 for each week his yacht is late.

Activity Immediate Predecessor Normal Time (NT) Weeks Crashing Cost
  1st Week 2nd Week
A 9 $410 $415
B A 7 125 --
C A 5 45 45
D B 4 300 350
E C 6 50 --
F D, E 5 200 225
G F 8 -- --
H F 7 85 90
I G 6 90 --
  1. Construct a network diagram for the project
  2. Indicate the critical path when normal activity times are used.
  3. Develop a crashing schedule. Note: No activity can be crashed more than two weeks.
  4. Show breakdown of work
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Marketing
Marketing
Marketing
ISBN:
9780357033791
Author:
Pride, William M
Publisher:
South Western Educational Publishing