(b) Identify all of the paths on the network diagram and note how long they are, using Figure 6- 8 as a guide for how to represent each path. Be sure to round up the duration for all activities.
Q: A construction project is broken down into the following activities Activity Immediate predecessor…
A: Network diagram is given by From the network diagram, we have four paths, namely, 1-2-5-8-10…
Q: Activity 2: Consider the following immediate preceding activity table. Draw the network and…
A: A network diagram is a visual representation of a project which helps to identify the activity…
Q: Discuss the rules for drawing networks and illustrate the above by drawing its network.
A: Project network is a visual representation of project activities and their duration to complete the…
Q: A project consists of the activities in the following table. Times are given in weeks Draw the…
A: Network Diagram is graphical representation of activities in a project. Network diagram can be…
Q: The following is the data available for a project: Activity Predecessor Expected Duration…
A: In project management, the network diagram is used to determine the critical path of the project and…
Q: (a) Construct the AON network for the project. (b) Determine all paths that run from the start to…
A: Activity-on-node is a project management term that leads to a precedence diagramming method that…
Q: . Draw the network diagram and determine the critical path for the project below:
A: A network diagram is the graphical representation of project activities and shows their duration of…
Q: a. Draw a project network. b. Identify the critical path. e Develop the activity schedule for the…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: 1. Draw the network diagram. 2. Calculate the expected duration and variance of each activity. 3.…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: The network diagram below (activity on arrow) shows the activities needed to complete a project to…
A: ANSWER IS AS BELOW:
Q: d) If the time to complete path A-C is normally distributed, what is the probability that this path…
A: Probability of competing a path indicating the proportion between the difference in line duration…
Q: B. Please draw an activity diagram for the tour reservation.
A: Please find the attachment in next step.
Q: Please answer all parts Activity Preceding activity Activity duration A - 6 B - 3 C - 1…
A: Note: - Since we can answer only up to three subparts we will answer the first three subparts…
Q: D) Using the precedence table given, construct the precedence matrix and draw an activity-on-node…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: (a) Construct a network for this problem. (b) Determine the expected time and variance for each…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: Consider the following table and answer the following questions. All duration estimates or estimated…
A: Activity on arrow and activity on node both are different concept, in AOA we use circle diagrams…
Q: For a particular project, consider following list of Activities, their duration in Days and their…
A: Given data is,
Q: Develop an "activity on Node" network diagram for this project and answer the following questions…
A: Project duration is the total time taken to complete the project successfully measurable in days or…
Q: Consider Table 6-3. All duration estimates or estimated times are in weeks, and the network proceeds…
A: The question is related to Critical Path Analysis. The details are given regarding activities and…
Q: The activities in the following table describe the construction of a new house. Construct the…
A: This question is related to the topic -Project management and this topic falls under the business…
Q: For following data Calculate Duration for each Task, Draw the Network, and find Critical Path.
A: The critical path method (CPM), also known as critical path analysis (CPA), is a scheduling method…
Q: Calculate (expected time) for each activity. For each activity, the estimates are , , , in that…
A: The answer is as below:
Q: Draw the network and identify the critical path of following data and total slack time in the…
A: Find the given details below:
Q: In the cpm network diagram given below: a-Find the critical path and show it on the diagram.…
A: Find the Given details below:
Q: Draw the network diagram for the project.
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: Draw a fully analyzed AON network diagram and determine the project duration. Be sure to include all…
A: Below is the solution:-
Q: Draw a network diagram that includes the project information above.
A: CPM stands for Critical Path Method, which was invented by DuPont and first used in the chemical…
Q: You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. a)…
A: Below is the solution:-
Q: QI/ The following table shows the activities of a construction project, sequences and estimated…
A:
Q: 1. of all the paths through a network , the critical path has the a. Maximum actual time b.…
A: Project network is the graphical representation that shows the project activities as well as their…
Q: For the project detailed in the table below: a) Draw the Activity on Node (AON) network diagram…
A: Activity Immediate Predecessors Duration A - 4 B - 6 C A,B 7 D B 8 E B 5 F C 5 G D 7…
Q: snip
A: Given: Task A must be completed to before B and C are started. Task C must be completed before task…
Q: Construct a CPM network based on activity on node method with the details given below and find the…
A: Given information, Activity Immediate Predecessor Duration A 1 B A 4 C A 2 D A 2 E…
Q: Ex7: (H.W) Draw the network of the following Table and determine critical path using CPM Act.…
A: Given Information, Activity Preceded By Duration A 3 B A 5 C A 4 D A 6 E B 4 F…
Q: In your innovative project, you are requested to produce a documentary film about the training…
A: Since you have submitted a question with multiple subparts, as per guidelines we should answer the…
Q: snip
A: PERT assumes that path lengths through a network can be modeled with Normal distribution.
Q: You have to manage a project with activities and their respective durations as listed in the table…
A: Given data is
Q: Develop the appropriate PERT network using an Activity-on-Arrow Diagram. Be sure to indicate the…
A: while drawing AOA drawings, dummy activities are made when there are more than one predecessor of…
Q: b) - Draw the Activity-on-Node (AON) diagram using the following representation for every node:…
A: Activity-on-node is a project management term that directs to a precedence diagramming technique…
Q: i. Draw the network diagram linking all the activities in a way that it shows if there exist any…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: nship in network below. The estimate (in weeks) of the duration of each activity is in the table…
A: Since you have posted a question with multiple sub-parts, we will solve the first three sub-parts…
Q: The network diagram for a new project your company is undertaking is as shown: Start Einish a.…
A:
Q: A D A A B,C D H D,E F H,G You are required to a) Draw the network diagram b) Calculate ES, EF, LS,…
A: The answer is as below:
Q: a. Use the Table 1 above to develop a network diagram. b. Calculate the Early Start (ES), Early…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: 1) Use the List of Activities to develop an AON/CPM/Network Diagram 2) Complete the Critical Path…
A: Find the given details below: Activity Duration(Weeks) Predecessor 1 - - 2 0 - 3 4 2 4 4…
Q: snip
A: PERT stands for Program Evaluation and Review Technique. It is a strategy used to look at the…
Q: What is the activity-on-node (AON) project network?
A: Activity-on-node is an operational project management term that refers to a priority graphing…
Q: Read the following set of activities carefully. The precedence of all activities is finish to start.…
A: The program evaluation and review technique (PERT) is a statistical device utilized in undertaking…
Q: Using information provided to draw a Project Network. Nodes in your Project Network must organize…
A: Critical path is the path with the shortest possible duration which a project can take to complete…
(b) Identify all of the paths on the network diagram and note how long they are, using Figure 6- 8 as a guide for how to represent each path. Be sure to round up the duration for all activities.
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images
- Kimpel Products makes pizza ovens for com-mercial use. James Kimpel, CEO, is contemplating produc-ing smaller ovens for use in high school and college kitchens.The activities necessary to build an experimental model andrelated data are given in the following table: a) What is the project completion date?b) Crash this project to 10 weeks at the least cost.c) Crash this project to 7 weeks (which is the maximum it canbe crashed) at the least cost.III. Risks and Feasibility This section of your report identifies risks and confirms the feasibility of the information systems development project. Project feasibility analysis verifies whether a project may be started and successfully completed. Your report should address the feasibility issues listed below. Start by clearly describing what issues are addressed by each feasibility category (see the relevant definitions in the textbook), and discuss the feasibility of the project with respect to each category. Determine organizational and cultural feasibility. This evaluates organizational and cultural issues to identify potential risks for the new system. See pp. 269–270 of the textbook for examples of potential issues.Note: the textbook does not provide an exhaustive list of possibilities!Note: ‘organization’ in this context refers to the Car Sharing community—all stakeholders, but particularly members and prospective members. Assess technological feasibility. See p. 270 of the…Slove the quation: Tony and his team identified some risks during the first month of the Recreation and Wellness Intranet Project. However, all they did was document the risks in a list. They never ranked the risks or developed any response strategies. Because the project has had several problems, such as key team members leaving the company, users being uncooperative, and team members not providing good status information. Tony has decided to be more proactive in managing risks. He also wants to address positive risks as well as negative risks. The quation is ; Develop a response strategy for one of the negative risks and one of the positive risks. Enter the information in the risk register.
- Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following table Total Cost with Crashing Immediate Predecessor(s) $2,050 $2,800 a) Based on the given information regarding the activities for the project, the project completion date = b) To reduce the duration of the project to 10 weeks at the least cost, the following is the order of what needs to be followed while crashing the activities: The first activity to crash is by 2 weeks at a per week crashing cost of Ned, one should crash activity dollars. Total cost of crashing the project to 7 weeks = and activity E by 1 week at a total per week crashing cost of dollars. dollars. weeks. dollars. dollars. Normal Activity Time (weeks) A TERSE Doo LU LỞ MATMARIATION percen 32 TON * Next one should crash activity D and activity by 2 weeks for an…23 The Identify Stakeholders process has four inputs Three of them are project charter, enterprise environmental factors and organizational process assets. What is the fourth one? A Procurement documents B Stakeholder register C. Stakeholder engagement matrix D Stakeholder management plan 24 The Project Managers have maximum authority in which type of organization? A Weak Matrix B Strong Matrix C Functional D Balanced Matrix 25 Accepted deliverables are an input to the Close Project or Phase process These deliverables would have been accepted through which of the following processes? A. Validate Scope B Control Quality C. Control Scope D. Perform Quality Assurance 26. Which process group corresponds to the "do" part of the plan-do-check-act cycle? A Closing B. Monitoring and Controlling C. Planning D. Executing 27. To control the schedule, a project manager is re-analyzing the project to predict project duration. This is done by analyzing the sequence of activities with the least…a) Explain with examples the differences between the following pairs of terminologies in project risk management:i.Proximity and Dormancy of a Riskii.Stakeholder Risk Threshold and Toleranceiii. iv.Variability Risk and Ambiguity RiskQualitative Risk Analysis and Quantitative Risk Analysis Risk Review and Risk Audit.b) During the execution of a project, a risk is identified by a team member. This newly identified risk is currently not in the risk register. As a project manager, list and briefly explain the steps you will take to manage this risk.c) As a project manager, you will be required to implement risk response plans for your projects. List and explain any five (5) typical outputs of this process.
- d) Risk is defined as the uncertain event or condition that if occurs has a positive or negativeeffect on the project's objective. The project objectives can be classified into three; cost,schedule and performance. There are 5 steps on risk identification process which startfrom identification and end with monitoring.Based on these three project objectives please explain the project risk managementprocess.explain it briefly and include exampleRESEARCH TOPICS1. The difference between project feasibility and project appraisal and their significance toproject sustainability2. The interplay between the project components (Cost, time, scope and quality) and thesignificance to project performance and sustainability3. Report writing process and utility of project report to project management Justify as to how the management of the positive risk will influence theachievement of project objectivesc) Explain why it is important for a risk management process to cover both threat andopportunity. Make sure that you justify your reasons.Question twelveA firm has developed a new product X. They can either test the market or abandon the project. The details are set out below;Testing the market cost 50,000FCFA, while the likely outcomes are favourable with a probability of 0.7 or unfavourable (failure) with a probability of 0.3. If favourable they could either abandon or produce it. The demand, probability and loss/profit for the product when produced are anticipated and presented in the table below;DemandProbabilityProfit/lossLow 0.25- 100,000Medium 0.6150,000High0.15450,000If the test market indicates failure, the project would be abandoned. Abandonment at any stage results in a gain of 30,000FCFA for the special machinery used. a) Draw the decision tree showing the nodes and…
- Analyze the following situations. Choose one situation which you think is less harmful. Explain why it is less harmful. How can you counter the harm that it causes?1. (Project A) Mr Ang plans plans to have a project which is a factory that would employ 50% of the people in the community but his factory would releases harmful chemicals to the sea.2. ( Project B) Mr. Bin plans to create an amusement park project to attract people to work on his place/business so that the factory would be closed and stop releasing harmful chemicals to the sea. However, Mr. Bin needs to cut the trees along the place where he has to build his amusement park but this again would cause harm to the environment. 3. (Project C) Mr. Ching plans to establish a resort and hotel project so that Mr Bin cannot cut the trees in order to save nature. However, by so doing he has to reclaim an area where mangroves grow which serves as fish sanctuary. Question: If you are a lover of nature and a…3.1 The PMBOK categorises risks into internal and external factors. Anne found that her working relationship with Mr. Richard Cramer was progressively deteriorating as his micro management of the project was taking a toll on the project and staff morale. As a result, Anne and some of the project team members wanted to absolve themselves of the project. Had this transpired, it would have posed a risk on the successful delivery of the project. Define the concept the above situation would have created.The following precedence diagram reflects three time estimates for each activity. Determine: Use Table B1 and Table B2. 9-10-12 3 8 5-7-10 8-10-14 11-12-13 6 11 14-18-26 10.5-13-15.5 10 8-8-8 1 5-6-7 2 4 13-13-13 7 7-10-12 a. The expected completion time for each path and its variance. (Round intermediate calculations to 4 decimal places and final answers to 2 decimal places.) Path Mean Var. Std. Dev. 1-2-3-8-11 37.33 1-2-4-6-11 43.00 5.11 1-2-4-7-11 0.81 1-2-5-9-10-11 46.83 1.25 9-9-9 10-11-12 10-12-14