An engineer bidding on the asphalting of a 7-kn stretch of road is confronted with the problem of choosing between two possible sites on which to set up the asphalt-mixing machine. At site A, the average hauling distance is 2.5km; the monthly rental would be P10,500 and the cost of installing and dismantling the equipment would be P20,000. At site B, the average hauling distance is 3.25km; the monthly rental would be P3,500 and the cost of installing and dismantling the equipment would be P10,200. The asphalt mix is to be hauled by a sub-contractor at P15.25 per cu. m. per km of haul. At site A, it would be necessary to hire 2 flagmen at P150 each per workday. The job can be completed in 30 weeks or 7 months working 6 days a week. The project requires 16,670 cu. m. of asphalt mix per km of road. Which site should he choose and how much lower would his bid be if he made the better choice?

College Algebra (MindTap Course List)
12th Edition
ISBN:9781305652231
Author:R. David Gustafson, Jeff Hughes
Publisher:R. David Gustafson, Jeff Hughes
Chapter6: Linear Systems
Section6.8: Linear Programming
Problem 4SC: If the cost of each Robust tablet increases to 75 c and the cost of each Vigortab increases to 80 c...
icon
Related questions
icon
Concept explainers
Topic Video
Question
100%
Problem 1:
An engineer bidding on the asphalting of a 7-km stretch of road
is confronted with the problem of choosing between two
possible sites on which to set up the asphalt-mixing machine.
At site A, the average hauling distance is 2.5km; the monthly
rental would be P10,500 and the cost of installing and
dismantling the equipiment would be P20,000. At site B, the
average hauling distance is 3.25km; the monthly rental would
be P3,500 and the cost of installing and dismantling the
equipment would be P10,200. The asphalt mix is to be hauled
by a sub-contractor at P15.25 per cu. m. per km of haul. At site
A, it would be necessary to hire 2 flagmen at P150 each per
workday. The job can be completed in 30 weeks or 7 months
working 6 days a week. The project requires 16,670 cu. m. of
asphalt mix per km of road. Which site should he choose and
how much lower would his bid be if he made the better choice?
Transcribed Image Text:Problem 1: An engineer bidding on the asphalting of a 7-km stretch of road is confronted with the problem of choosing between two possible sites on which to set up the asphalt-mixing machine. At site A, the average hauling distance is 2.5km; the monthly rental would be P10,500 and the cost of installing and dismantling the equipiment would be P20,000. At site B, the average hauling distance is 3.25km; the monthly rental would be P3,500 and the cost of installing and dismantling the equipment would be P10,200. The asphalt mix is to be hauled by a sub-contractor at P15.25 per cu. m. per km of haul. At site A, it would be necessary to hire 2 flagmen at P150 each per workday. The job can be completed in 30 weeks or 7 months working 6 days a week. The project requires 16,670 cu. m. of asphalt mix per km of road. Which site should he choose and how much lower would his bid be if he made the better choice?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Application of Algebra
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, advanced-math and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
College Algebra (MindTap Course List)
College Algebra (MindTap Course List)
Algebra
ISBN:
9781305652231
Author:
R. David Gustafson, Jeff Hughes
Publisher:
Cengage Learning