Activity Weeks A Inspect the new building, list all required data communications facilities 3 B Order and deliver all data communications facilities and devices 10 C Identify, order and deliver replacement PCs, printers, servers and other hardware 8 D Order and deliver all required office equipment 11 E Test new hardware with all communications equipment 1 F Test new hardware with all existing operating and applications software 2 G Test all applications software and databases on the new hardware 2 H Move all staff to new premises 1       Tasks B, C and D can all run simultaneously but are all dependent on task A. Task E is dependent on tasks B and C Task F is dependent only on task C Task G is dependent on tasks E and F. Task H cannot start until tasks D and G are completed. a) Draw a full Activity on Node diagram for this project, showing clearly the earliest and latest start and end dates (as week numbers), and the float, for each node. No start or end nodes are required. Highlight and name the critical path, together with the minimum duration for the project. b) The office equipment (task D) takes two weeks longer than planned to be delivered and installed. Identify and briefly explain the resultant changes to the Activity on Node diagram and critical path

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
  Activity Weeks
A Inspect the new building, list all required data communications
facilities
3
B Order and deliver all data communications facilities and
devices
10
C Identify, order and deliver replacement PCs, printers, servers
and other hardware
8
D Order and deliver all required office equipment 11
E Test new hardware with all communications equipment 1
F Test new hardware with all existing operating and applications
software
2
G Test all applications software and databases on the new
hardware
2
H Move all staff to new premises 1
     

Tasks B, C and D can all run simultaneously but are all dependent on task A.
Task E is dependent on tasks B and C
Task F is dependent only on task C
Task G is dependent on tasks E and F.

Task H cannot start until tasks D and G are completed.


a) Draw a full Activity on Node diagram for this project, showing clearly the
earliest and latest start and end dates (as week numbers), and the float, for
each node. No start or end nodes are required. Highlight and name the critical
path, together with the minimum duration for the project.

b) The office equipment (task D) takes two weeks longer than planned to be
delivered and installed. Identify and briefly explain the resultant changes to the
Activity on Node diagram and critical path.

Expert Solution
steps

Step by step

Solved in 3 steps with 5 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.