Activity Normal_time Crash_time Normal_cost Crash_cost Slack A. 31 17 4800 6200 B 14 14 5500 5500 34 18 5100 6600 1 21 17 4500 6800 1 15 15 5300 5300 F 17 17 5300 5300 The table shows normal time, crash time, normal cost, crash cost and slack time of activities in a project. According to this table which activity must be crashed first? Assume there is only one critical path. (Only type the name of the activity, Example: A. @orsdemir. Copyrighted content. Cannot be posted.)
Q: Normal Crash Task Precedence Duration Cost Duration Cost Name |(week) (week) A 850 0,1 0,2 700 3 500…
A:
Q: Activity Immediate Predecessor(s) Time (days) 10 7 A, D 4 G E, F 10 This exercise contains only…
A: Forward Pass- Early Start (ES)= Maximum (or Highest) EF value from immediate Predecessor(s)…
Q: example of cost control for project
A: Cost Control A tool which is used by the organization’s management in controlling and regulating the…
Q: If indirect costs for each duration are $300 for 27 weeks, $240 for 26 weeks, $180 for 25 weeks,…
A: Find the Given Details below: Activity Normal time (Weeks) Normal Cost Maximum Crash time Crash…
Q: Development of Version 2.0 of a particular accounting software product is being considered by Jose…
A: Note: - As we can answer only three subparts, the first three(a, b, and c) will be answered. If…
Q: i. What is the project completion date? ii. What is the total cost required for completing this…
A: Total cost is the cost that includes fixed cost and variable cost of goods and services.
Q: snip
A: If a non-critical path activity is delayed, there is no change in the overall duration of the…
Q: An architect of a task force planning the construction of a domed stadium had hoped to be able to…
A: Critical path: It is the order of activities/task associated with the project network which…
Q: (1) O Construct a network diagram with activity on arrow method; (1) Estimate the expected project…
A:
Q: Explain : Activity time, Gantt chart, Critical path, Slack time, Crashing.
A: PART A: - Activity period may be a noun that represents the particular amount of your time that…
Q: What is the relationship between the earliest start time (EST) of an activity and the earliest…
A: EST is early start time. It refers to earliest possible time to start an activity. ECT is early…
Q: Development of Version 2.0 of a particular accounting software product is being considered by Jose…
A: Hi, we are supposed to answer three subparts at a time. Since you have not mentioned which subpart…
Q: primary and CPM is that CPM uses probabilities on the activity times and PERT does not. PERT…
A: The essential contrast among PERT and CPM is that Spunky arrangements with flighty exercises,…
Q: Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely…
A: Critical path analysis (CPA) is a project managerial technique that represents identifying each…
Q: H.W(1):- Draw Gantt chart for the following project and determine the duration of the project…
A: A Gantt chart is a type of bar chart. It shows the schedule of a project. It was invented by Henry…
Q: Consider the project crashing information presented in Figure 8-4. What is the cost to complete this…
A: Project duration is the total time taken to complete the project successfully measurable in days or…
Q: Izzi used a project management softwäre package and has determined the following results for a given…
A: Expected completion time of the project: μ=22 days Variance of Project: σ2=2.77 days Standard…
Q: a) The probability of completing the critical path in 12 weeks (or less), as the client desires.…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: Normal Time Crash Time Immediate Predecessor(s) Activity Normal Cost (S) Crash Cost () (days) (days)…
A: The network diagram is a visual representation of the project activities and their durations of…
Q: d. Determine the probability that the team and the contractor will be in place and the project…
A: Based on the 3-time estimates given, we find the Expected duration and Variance for each activity as…
Q: Three activities are candidates for crashing on a projectnetwork for a large computer installation…
A: Critical path is the sequence of dependent tasks that form the longest duration, allowing you to…
Q: 00:19:06 Remaining An activity in a PERT network is expected to require 54 days to complete. This…
A: Given data is O = 48 days M = 200 days Expected time = 54 days
Q: Task Name Normal time Normal Crash time Crash cost (slope) Predecessor cost 4. 85 3. 10 5. 100 4. 30…
A: We are using Forward pass method to solve below problem. Forward pass is a strategy to push ahead…
Q: activities, of which are on the critical path. If the estimated time along the critical path is 214…
A: We have for the estimated time, Mean = 214 Variance = 169
Q: CRASHING A new order filling system is needs to be installed as soon as possible. The following…
A: Given data is
Q: Consider the office renovation project data in Table 7.16. A “zero” time estimate means that the…
A: According to the given information, the critical path is A-C-F. Compute total expected time:
Q: Explain SEVEN (7) steps for Project Time Management Processes. What is Work Breakdown…
A: 1.) Plan schedule management: - The first step is to remain on the schedule that was planned and…
Q: the working of the t
A: The triple constraint theory in project management states that undertaking works inside the limits…
Q: days. Carl's team should be able to complete the project in
A: A network diagram is the graphical representation of project activities and shows their duration of…
Q: Development of Version 2.0 of a particular accounting software product is being considered by Jose…
A: Find the Given details below: Activity Normal Time (NT) (Weeks) Normal cost (NC) ($) Crash Time…
Q: Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned…
A: Given Information:
Q: Activity A B Ꭰ E F G H Crashed Activity Time 0.25 0.5 1 0.25 2 1 2 0.5 Cost ($) Normal Cras hing 750…
A: Activity Crashed activity time Normal cost Crashing cost A 0.25 750 1000 B 0.5 250 750 C 1 750…
Q: Activity A B C E F G H Preceded By ** A B,C D E BC F.G Expected Time Direct Cost Regular Crash…
A:
Q: PROJECT PLANNING & SCHEDULING WITH GANNT CHART Given the activities of a project; their optimistic…
A: Note: - As we can answer only up to 3 questions, we will answer questions 1, 2, and 3 for your…
Q: The possibility of completing the project in less or equal time The critical path plus 2 weeks is 95…
A:
Q: Given the activities of a project; their optimistic (t.), most likely (t_) and pessimistic (t) time…
A: Note: - Since we can answer only up to 3 questions we will answer questions 1, 2, and 3 for your…
Q: a) The critical path and the expected project completion time. b) Find the optimal duration and…
A: A project schedule network diagram shows the sequence of the task that is performed to complete a…
Q: ESTIMATED RESOURCES IMMEDIATE PREDECESSOR TASKS ESTIMATED TIME DURATION(S) TASKS ASSIGNED TO FIGURE…
A: Project Managers have the responsibility that makes the plan, procures, and execute the project with…
Q: An R&D project in a company is working on a project to make a sample product to be displayed at an…
A: Given- Activity Cost per month to crash A 9,000 B 4,000 C 6,000 D 4,000 E 2,000 F…
Q: PROJECT PLANNING & SCHEDULING WITH PERT/CPM Given the activities of a project; their optimistic…
A: Given data is
Q: 1. For cach of the following network diagrams, determine both the critical path and the expected…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: 14 - In earned value analysis, we found that BCWP: $24,800 BCWS: $27,650 ACWP: $21,900 The project…
A: Earned Value Analysis (EVA): It is a system that enables the project manager to estimate the amount…
Q: A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the…
A:
Q: (i) The backward pass in project network calculations determines the A. Latest time's activities can…
A: network diagram helps in scheduling the activities of project management. It helps in analysing the…
Q: An architect of a task force planning the construction of a domed stadium had hoped to be able to…
A: Critical path: It is the order of the activities of the project network in which the shortest…
Q: Consider a project having the following seven activities: Normal Normal Crash Crash Maximum Time…
A: A network diagram is a visual representation of a project which helps to identify the project…
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table D Total Cost with Normal Time Crash Time Normal Immediate Activity (weeks) (weeks) Cost Crashing Predecessor(s) A 4 3 $2,000 $2,650 B 2 1 $2,300 $3,100 TTTT C 3 3 $750 $750 D 8 4 $2,300 $2,580 A E 6 3 $1,000 $1,300 B F 3 2 $3,000 $4,400 C G 4 2 $1,600 $2,000 D, E a) Based on the given information regarding the activities for the project, the project length = weeks. b) The total cost required for completing this project on normal time = $ ▼ c) For reducing the duration of the project by one week, the activity that should be crashed first is activity The cost of the project based on the first activity selected for crashing will increase by $ weeks. d) The maximum weeks by which the project can be reduced by crashing = Total cost of crashing the project to…Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Total Cost Normal Time Crash Time Normal with Immediate Activity (weeks) (weeks) Cost Crashing Predecessor(s) $2,200 $2,100 $2,900 $2,900 A 4 3 1 C 3 3 $500 $500 $2,500 $1,000 $3,200 $2,800 $1,375 $4,600 $2,100 8. E 6. 3 G 4 $1,600 D, E a) Based on the given information regarding the activities for the project, the project length = weeks. %3D b) The total cost required for completing this project on normal time = $ %3D c) For reducing the duration of the project by one week, the activity that should be crashed first is activity The cost of the project based on the first activity selected for crashing will increase by $ d) The maximum weeks by which the project can be reduced by crashing = weeks. %3D Total cost of crashing the project to minimum (or…Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Normal Crash Normal Activity Time (weeks) Time (weeks) Cost ABCDEFG 4 2 3 8 6 3 4 3 1 3 4 3 2 2 $2,100 $2,300 $600 $2,400 $800 $3,400 $1,400 Total Cost with Crashing Immediate Predecessor(s) $2,750 $2,900 $600 $2,680 $1,100 $4,600 $1,900 a) Based on the given information regarding the activities for the project, the project length b) The total cost required for completing this project on normal time = $ 13000. | | A B C D, E = 16 weeks. c) For reducing the duration of the project by one week, the activity that should be crashed first is activity D The cost of the project based on the first activity selected for crashing will increase by $ 70. d) The maximum weeks by which the project can be reduced by crashing = 7 weeks. Total cost of crashing the…
- Activity Normal_time Crash_time Normal_cost Crash_cost Slack A 31 28 4500 6700 2 13. 13 5800 5800 0 27 27 5000 5000 0 27 16 4000 6900 2 24 24 5500 5500 0 34 13 4500 6900 0 B C D E F The table shows normal time (in days), crash time (in days), normal cost (in dollars), crash cost (in dollars) and slack time (in days) of activities in a small construction project. According to this table which activity must be crashed first? Assume there is only one criticalDevelopment of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Immediate Predecessor(s) A 44 33 $ 2 comma 100$2,100 $ 2 comma 700$2,700 long dash— B 22 11 $ 2 comma 200$2,200 $ 2 comma 900$2,900 long dash— C 33 33 $ 500$500 $ 500$500 long dash— D 88 44 $ 2 comma 500$2,500 $ 2 comma 820$2,820 A E 66 33 $ 1 comma 000$1,000 $ 1 comma 300$1,300 B F 33 22 $ 3 comma 400$3,400 $ 4 comma 800$4,800 C G 44 22 $ 1 comma 500$1,500 $ 2 comma 000$2,000 D, E Part 2 a) Based on the given information…Consider the following activity description with associated cost data shown in Table 1. The cost data represents the total cost and should be considered linear with time. Table 1: Crash Cost Table Activity Immediate Predecessor Normal Duration (days) Normal Cost ($) Crash Duration (days) Crash Cost ($) A --- 5 50 3 150 B --- 4 40 2 200 C B 7 70 5 250 D A, C 2 20 1 50 E A, C 5 125 1 525 F B 10 80 7 290 G D 7 50 3 250 H E, F 6 60 3 180 Reduce the project duration to minimum duration and calculate the cost. Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.
- Example 2.39 Table 2.119 provides normal and crash times as well as normal and crash costs for the activities of a project. Table 2.119 Project activity details Activity Normal Time (Weeks) Normal Cost (Lakhs) Crash Time (Weeks) 1-2 3 5 2-3 4 8 2-4 3 4 2-5 8 S 3-6 4 3 4-6 6 2 5-7 5 10 6-7 3 7 1 3 2 7 2 4 4 1 Crash Cost (Lakhs) 9 14 6 6 5 3 14 10 Project Network Analysis-1 | 141 (a) Draw the network and find the critical path. (b) Using the above information, crash or shorten the activities step by step until the shortest duration is reached. MMM, VI Sem, Mumbai Univ, 2006Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Immediate Predecessors(s) A 4 3 $2,200 $2,850 --- B 2 1 $2,100 $2,700 --- C 3 3 $750 $750 --- D 8 4 $2,500 $2,800 A E 6 3 $800 $1,250 B F 3 2 $3,200 $4,400 C G 4 2 $1,400 $1,800 D, E a) Based on the given information regarding the activities for the project, the project length = _______ weeks ? b) The total cost required for completing this project on normal time = _______ ? c) If you wish to reduce the time required to complete this project by 1 week, which activity should be crashed, and how much will this increase the total cost? The critical path with the longest length through the project is _______ ? Note:- Do not provide…A project consist of 5 activities A,B,C,D,E with ES, EF, LS and LF of A (0, 6, 9, 15); B (0, 7, 0, 7); C (6, 13, 15, 22); D (7, 13, 7, 13); E (13, 22, 13, 22). Normal Time (in month), Crash time (in month), Normal cost (in million Rp), Crash cost (in million Rp) from each activity are A (6, 4, 20, 24); B (7, 5, 30, 35); C (7, 6, 10, 13); D (6, 4, 20, 26); E (9, 8, 88, 90) a. What activities are in the critical path? How long is the project duration? b. If we want to crash the project for 2 months, what activities need to be crashed? How much additional cost required?
- Activity normal durations, crash durations and cost Activity Normal Duration (weeks) Crash Duration (weeks) Normal Cost ($) Crash Cost ($) A-B 4 2 300,000.00 420,000.00 B-C 3 3 100,000.00 100,000.00 B-D 2 1 50,000.00 55,000.00 B-E 6 5 150,000.00 200,000.00 C-F 3 2 30,000.00 150,000.00 C-K 3 2 20,000.00 25,000.00 D-G 2 1 300,000.00 350,000.00 E-H 10 8 60,000.00 140,000.00 F-G 3 2 160,000.00 260,000.00 F-I 3 2 350,000.00 500,000.00 F-K 2 1 170,000.00 270,000.00 F-L 2 1 330,000.00 440,000.00 F-N 2 1 250,000.00 500,000.00 G-L 2 1 60,000.00 65,000.00 H-K 10 9 100,000.00 110,000.00 I-J 2 1 10,000.00 20,000.00 J-O 3 1 30,000.00 35,000.00 K-N 8 7 50,000.00 80,000.00 L-M 4 2 40,000.00 50,000.00 M-O 2 1 5,000.00 6,000.00 N-O 12 10 200,000.00 240,000.00 Note: The Crash duration represents the minimum duration where an activity is speeded up as much as possible. The crash cost represents the increased cost…Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity Normal Time(weeks) Crash Time(weeks) Normal Cost Total Cost with Crashing Immediate Predecessor(s) A 4 3 $2,000 $2,650 — B 2 1 $2,100 $2,900 — C 3 3 $750 $750 — D 8 4 $2,300 $2,620 A E 6 3 $900 $1,275 B F 3 2 $3,200 $4,700 C G 4 2 $1,400 $1,900 D, E I have answers for the frist part of the question: a) Based on the given information regarding the activities for the project, the project length = 16 weeks. b) The total cost required for completing this project on normal time = $12,650. c) For reducing the duration of the project by one week, the activity that should be crashed first is activity…Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity Normal Time(weeks) Crash Time(weeks) Normal Cost Total Cost with Crashing Immediate Predecessor(s) A 4 3 $2,000 $2,650 — B 2 1 $2,100 $2,900 — C 3 3 $750 $750 — D 8 4 $2,300 $2,620 A E 6 3 $900 $1,275 B F 3 2 $3,200 $4,700 C G 4 2 $1,400 $1,900 D, E a) Based on the given information regarding the activities for the project, the project length = 16 weeks. b) The total cost required for completing this project on normal time = $12,650. c) For reducing the duration of the project by one…