a. Find the critical path.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Ha
Beyonce has started a new musical service automating the release of her key venture. Other pop stars are interested in how it works.
Beyonce has asked you to analyze it from a project management angle, addressing the questions below.
B(3)
D(5)
F(4)
A(7)
(G(5)
C(4)
(E(2)
a. Find the critical path.
O A-B-D-F-G
O A-B-D-E-G
O A-C-D-E-G
O A-C-D-F-G
BTS provided the following table with information you need to solve this problem.
Note: times are shown in days
ACTIVITY
NORMAL TIME CRASH TIME NORMAL COST CRASH COST
6.
ם00 ,$7
5,000
9,000
3,000
2,000
$ 8,000
7,000
10,200
4,500
4
D
4
E
3,000
F
2
4,000
5,000
7,000
8,000
4
Transcribed Image Text:Ha Beyonce has started a new musical service automating the release of her key venture. Other pop stars are interested in how it works. Beyonce has asked you to analyze it from a project management angle, addressing the questions below. B(3) D(5) F(4) A(7) (G(5) C(4) (E(2) a. Find the critical path. O A-B-D-F-G O A-B-D-E-G O A-C-D-E-G O A-C-D-F-G BTS provided the following table with information you need to solve this problem. Note: times are shown in days ACTIVITY NORMAL TIME CRASH TIME NORMAL COST CRASH COST 6. ם00 ,$7 5,000 9,000 3,000 2,000 $ 8,000 7,000 10,200 4,500 4 D 4 E 3,000 F 2 4,000 5,000 7,000 8,000 4
O A-C-D-E-G
O A-C-D-F-G
BTS provided the following table with information you need to solve this problem.
Note: times are shown in days
ACTIVITY
NORMAL TIME
CRASH TIME NORMAL COST
$7,000
5,000
9,000
3,000
2,000
4,000
5,000
CRASH COST
A.
7
$ 8,000
7,000
10,200
4,500
3,000
7,000
8,000
B
3
2
C
4
D
4.
E
1
ok
F
2
G
b-1. If BTS's musical project is to be shortened by four days, which activities, in order of reduction, would be shortened?
O C, F (or E), D (or E)
O A, C, D (or F), F (or D)
O E, A
O A, F, D (or E)
b-2. What is the cost of crashing BTS's musical project?
Resulting cost to crash
Transcribed Image Text:O A-C-D-E-G O A-C-D-F-G BTS provided the following table with information you need to solve this problem. Note: times are shown in days ACTIVITY NORMAL TIME CRASH TIME NORMAL COST $7,000 5,000 9,000 3,000 2,000 4,000 5,000 CRASH COST A. 7 $ 8,000 7,000 10,200 4,500 3,000 7,000 8,000 B 3 2 C 4 D 4. E 1 ok F 2 G b-1. If BTS's musical project is to be shortened by four days, which activities, in order of reduction, would be shortened? O C, F (or E), D (or E) O A, C, D (or F), F (or D) O E, A O A, F, D (or E) b-2. What is the cost of crashing BTS's musical project? Resulting cost to crash
Expert Solution
Step 1

A network diagram is a visual representation of a project which identifying the activity relationship using the nodes and arrow. Similarly, A critical path indicating the longest duration indicating path. Based on the given information, we can calculate the answers for each questions like given below. 

steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.