a. Determine the critical path and the early completion time in weeks for the project. b. For the data shown, reduce the project completion time by three weeks. Assume a lin- ear cost per week shortened, and show, step by step, how you arrived at your schedule.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
15. For the network shown:
Crash Cost/week - (CC-NC)/(NT-CT)
TOTAL COST-$44,000
Crash D-$1,000
Crash G-$2,000
Crash A-$3,000
0
0
ATS)
Activity
A
B
54
C
D
E
F
45
45
B(10)
C(8)
1514
15
10
13 12
14
Normal Time
5
8
6
7
14 15
15
D(6)
21 20 19
21
a. Determine the critical path and the early completion time in weeks for the project.
b. For the data shown, reduce the project completion time by three weeks. Assume a lin-
ear cost per week shortened, and show, step by step, how you arrived at your schedule.
20 19
E(7)
14
13 17
F(4)
17 21
Normal Cost
$7,000
12,000
5,000
4,000
3,000
6,000
7,000
21
20
21 25
G(4)
25
Crash Time
3
7
7
24 23 22
A 2
B3
C1
D1
E1
5
6 F1
3 G1
Crash Cost
$13,000
18,000
7,000
5,000
6,000
7,000
9,000
A $3,000
B $2,000
C $2,000
D $1,000
E $3,000
F $1,000
G $2,000
Transcribed Image Text:15. For the network shown: Crash Cost/week - (CC-NC)/(NT-CT) TOTAL COST-$44,000 Crash D-$1,000 Crash G-$2,000 Crash A-$3,000 0 0 ATS) Activity A B 54 C D E F 45 45 B(10) C(8) 1514 15 10 13 12 14 Normal Time 5 8 6 7 14 15 15 D(6) 21 20 19 21 a. Determine the critical path and the early completion time in weeks for the project. b. For the data shown, reduce the project completion time by three weeks. Assume a lin- ear cost per week shortened, and show, step by step, how you arrived at your schedule. 20 19 E(7) 14 13 17 F(4) 17 21 Normal Cost $7,000 12,000 5,000 4,000 3,000 6,000 7,000 21 20 21 25 G(4) 25 Crash Time 3 7 7 24 23 22 A 2 B3 C1 D1 E1 5 6 F1 3 G1 Crash Cost $13,000 18,000 7,000 5,000 6,000 7,000 9,000 A $3,000 B $2,000 C $2,000 D $1,000 E $3,000 F $1,000 G $2,000
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 5 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.