A product structure tree (BOM or tree diagram) for the scissors is shown below. 600 scissors are needed on Day 6 (as shown in the master production schedule below). Lead times are 1 day for each component and final scissor assembly, but 2 days for the plastic grips. On hand inventory: Straight blades = 200, bent blades = 350, and top blade assembly = 40. Scissors Bottom Blade Assembly Screw Top Blade Assembly Straight Blade Straight Plastic Grip Bent Blade Bent Plastic Grip Master Day Schedule for: Beg. Inv. 1 2 3 4 5 6 7 8 Scissors Quantity 600

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Determine the correct planned order release of Scissors.

 

Determine the correct planned order release of Scissors.

a. Day 5 600
b. Day 3 300
c. Day 3 600
d. Day 2 600
e. Day 4 300
A product structure tree (BOM or tree diagram) for the scissors is shown below.
600 scissors are needed on Day 6 (as shown in the master production schedule below).
Lead times are 1 day for each component and final scissor assembly, but 2 days for the plastic grips.
On hand inventory: Straight blades = 200, bent blades = 350, and top blade assembly = 40.
Scissors
Bottom Blade Assembly
Screw
Top Blade Assembly
Straight Blade
Straight Plastic Grip
Bent Blade
Bent Plastic Grip
Master
Day
Schedule for:
Beg.
Inv.
1
2
3
4
5
6
7
8
Scissors
Quantity
600
Transcribed Image Text:A product structure tree (BOM or tree diagram) for the scissors is shown below. 600 scissors are needed on Day 6 (as shown in the master production schedule below). Lead times are 1 day for each component and final scissor assembly, but 2 days for the plastic grips. On hand inventory: Straight blades = 200, bent blades = 350, and top blade assembly = 40. Scissors Bottom Blade Assembly Screw Top Blade Assembly Straight Blade Straight Plastic Grip Bent Blade Bent Plastic Grip Master Day Schedule for: Beg. Inv. 1 2 3 4 5 6 7 8 Scissors Quantity 600
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.