A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 150 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F. and G are 2.3, 2.1, 0.9, 1.0, 1.2, 1.8, and 1.5 minutes respectively. Applying the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the LAST workstation are O a. All tasks O b. Gonly Oc Fand G O d. E,F, and G Oe. None is the correct answer

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question
A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted
demand of 150 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and Grespectively. Task A does not have any
predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks Cneeds, the task B to be completed. Also, starting task D needed
task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally,
starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F. and G are 2.3, 2.1, 0.9, 1.0, 1.2, 1.8, and 1.5 minutes
respectively. Applying the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will
be assigned to the LAST workstation are
O a. All tasks
O b. Gonly
Fand G
O d. E,F, and G
O e. None is the correct answer
Transcribed Image Text:A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 150 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and Grespectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks Cneeds, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F. and G are 2.3, 2.1, 0.9, 1.0, 1.2, 1.8, and 1.5 minutes respectively. Applying the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the LAST workstation are O a. All tasks O b. Gonly Fand G O d. E,F, and G O e. None is the correct answer
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,