Your customer has approached you and told you that you now need to finish the project two weeks earlier than anticipated. What does this mean in terms of the critical path? A You have a project float of two weeks. B Your project will be delayed by two weeks. c You have a positive float of two weeks. D You have a negative float of two weeks. m In which of the following methods do team members pull the work from a queue? A Critical path method X B Iterative scheduling with a backlog C On-demand scheduling D Resource leveling Your initial plan was to finish all configuration work before testing would start. However, due to some delays, you have decided to start testing even though configuration is not yet complete. Which of the following would best describe this situation? You have changed a mandatory dependency to a discretionary dependency. B You have changed a finish to start to a start to start relationship. c You have changed a start to finish relationship to a finish to start. D You have changed soft logic to hard logic.
1’ You need to clear a parking lot covered in snow and decide one person should start clearing the snow before the other person starts putting down rock salt. What relationship does this best describe? A Start to start B Finish to finish c Start to finish X D Finish to start Which of the following scheduling tools would you use on an agile project? (Choose two.) A Critical path method B Iterative schedule with a backlog c On-demand scheduling D Three-point estimating E Bottom-up estimating |*| You are the manager on a project to build a new wing for the local hospital. The ribbon-cutting ceremony is set, and many high-profile local dignitaries will be present, so the deadline is set firm and approaching fast. Unfortunately, the project is behind schedule. You work with your customer to discuss the best way to bring the project back on track, and the customer decides to crash the schedule. Of the following, which is the greatest concern to you? A Getting approval from the change control board /B Finding the additional resources to perform the work C Stakeholder’s buy-in D Increased cost
You have an expected activity duration of 26 days, optimistic value of 18 days, and pessimistic value of 67 days. Calculate the PERT. 8.2 days 31.5 days Your project is running behind schedule, but you have plenty of float on some activities. You decide to move resources from noncritical path activities to critical path activities. What are you performing? D Resource leveling Crashing Resource smoothing Fast-tracking As team members work with the product owner to prioritize user stories, it has become obvious that they need a better understanding of the requirements )ecause this is a new technology that they are not familiar with. What is the best ipproach to handle this situation? Ensure the team has the tools and information to perform further analysis. Adjust the sprints so that the first sprint focuses on learning the new system and requirements. Create a spike experiment for further investigation. Extend the schedule of the sprints to allow for additional time to analyze the requirements and the new system.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Related Questions
You have been hired by a website design, production, and hosting company whose new animated website designs are attracting a lot of attention and many customers. Currently employees are organized into different functions such as hardware, software design, graphic art, and website hosting, as well as functions such as marketing and human resources. Each function takes its turn to work on a new project from initial customer request to final online website hosting. The problem the company is experiencing is that it typically takes one year from the initial idea stage to the time a website is up and running: the company wants to shorten this time by half to protect and expand its market niche. In talking to other managers, you discover that they believe the company's current functional structure is the source of the problem-it is not allowing employees to develop websites fast enough to satisfy customers' demands. They want you to design a better structure. Discuss how you can improve the…
arrow_forward
Florida Southwestern State College has decided to implement a new registration system that will allow students to register online as well as in person. As an IT manager, you decide to set up a JAD session to help define the requirements for a new system. The FSW organization is fairly typical, with an administrative staff that includes a registrar, student support and service team, a business office, an IT group, and a number of academic departments. Using this information, you start work on a plan to carry out the JAD session. Who would you invite to the session, and why? What would be your agenda for the session, and what would take place at each stage of the session?
arrow_forward
In network analysis, the process of calculating LS and LF
A.
Is sufficient for identifying the critical path
B.
Cannot be done until slack time is first determined
C.
Requires only a backward pass through the network
D.
Requires only a forward pass through the network
arrow_forward
Used : Call center optimization as project , please give Citation if possible
are required to identify and select a project that you have worked on, whether as a project manager or project team member. If you have not worked on a project before or you are unable to select a suitable project based on your work experiences, you should select a project that you know about and have sufficient access to the project’s information. Remember, the project that you select (the case) should have already been completed/finished, implemented, or executed. If you decide to select a project outside of your work experiences, there are several completed projects in your local community, your country, the region, or internationally that you may be able to use as a case for this assignment. There are no restrictions on the type of project that you select or decide to work with, however please be deliberate in your selection or when choosing a project to work with. You should avoid selecting a project…
arrow_forward
The table below contains data for the installation of new equipment in a manufacturing process at Excello Corporation. Your company is responsible for the installation project. Indirect costs are $12,000 per
week, and a penalty cost of $6,000 per week will be incurred by your company for every week the project is delayed beyond week 12.
Activity
A
B
с
D
E
F
G
Immediate
Predecessor(s)
AB
Activity
A
B
с
D
A
C
D, E
E
Normal Time Crash Time
(weeks) (weeks)
3
1
2
2
1
3
4
1
6
3
Time according to
schedule (weeks)
1
a. What is the shortest time duration for this project regardless of cost?
The shortest project duration regardless of cost is 9 weeks. (Enter your response as a whole number.)
b. What is the minimum total cost associated with completing the project in 12 weeks?
The minimum total cost to complete the project in 12 weeks is $ 203500. (Enter your response as a whole number.)
c. What is the total time of the minimum-cost schedule? (Enter your responses as whole numbers.)
The total…
arrow_forward
William, a project manager, has a workload of 25,000 hours that needs to be completed in 30 weeks. He has a team of 20 people who work five 8-hour days per week. He notices that in the 30-week period, there are three holidays and 6 members have each requested 8 days off. Given this information, William is _____ short of completing his workload.
Question options:
23,136 hours
1,864 hours
480 hours
1,480 hours
384 hours
arrow_forward
John, Jack and Jill are project managers for Jusco Company. All three of them lead their own team, with two supervisors working under them. John’s team has 10 members, Jack has 8 members in his team and Jill has 11 members under his care. Both John and Jack completed their projects on time with the same amount of allocated budgets from top managers. But Jill didn’t manage to complete the project on time this time round.
(i) Assuming all three projects have the same scale in terms of size, quality,and complexity, what can we conclude about the effectiveness and efficiency of these three project managers based on the informationabove? Justify your answers
PLEASE PROVIDE CLEAR EXPLANATION THANK YOU , THIS TOPIC IS UNDER EVOLUTION OF FUNDAMENTAL MANAGEMENT THEORIES
arrow_forward
A large Southeast city is requesting federal funding for a park-and-ride project. One of the requirements in the request application is a
network plan for the design phase of the project. Sophie Kim, the chief engineer, wants you to develop a project network plan to meet
this requirement. She has gathered the activity time estimates and their dependencies shown here.
ID Description
A Survey
B
Soils report
с
Traffic design
D
Lot layout
E Approve design
F
G Drainage
H Landscape
I Signage
J
Illumination
Bid proposal
The project is expected to take
The critical path is:
Early start for Activity E is:
Late finish for Activity F is:
Slack for Activity C is:
Predecessor
None
A
A
A
B, C, D
E
E
E
E
F, G, H, I
Time
(days)
9
22
25
6
76
20
24
24
25
9
days.
day(s).
arrow_forward
In project management, CPM is an activity-oriented approach.
Select one:
O True
O False
arrow_forward
How long it will take for each activity on the network chart is all but one of the following.
Estimated duration
The elapsed time that will be required
Equal to the early start
O Expressed in the same time units - days, hours, months, years
arrow_forward
when discussing processes related to Project Execution, the ISO 10006 stabdard splits this category into different project groups. Which of the following is not one of these subcategories?
a. Human resource-related processes
b. Procurement processes
c. Time related processes
d. risk-related process
arrow_forward
A network diagram's ability to use probability estimates in determining critical paths and deadlines.
TRUE or FALSE?
arrow_forward
The most popular priority rules include:a) FCFS. b) EDD.c) SPT. d) all of the above.
arrow_forward
In a network diagram, an activity:A) Is the largest unit of work effort consuming both time and resources that a project manager can schedule and control?B) Should always be something the company has had experience with. C) Is the smallest unit of work effort consuming both time and resources that a project manager can schedule and control?D) Must always have a single, precise estimate for the time duration.
arrow_forward
The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing.
(a) What is the crash cost for 8 hours of time-savings?
(b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time?
Activity
Normal
Duration (hours)
Normal
Cost ($)
Crash
Duration (hours)
Crash
Cost (S)
Immediate
Predecessors
A
2
10
2
0
None
B
3
15
2
23
A
C
5
25
4
30
B
D
3
20
1
24
C
E
6
30
4
45
C
F
1
5
1
0
E
G
7
35
6
50
F
H
10
50
7
80
D, G
arrow_forward
A large Southeast city is requesting federal funding for a park-and-ride project. One of the requirements in the request application is a
network plan for the design phase of the project. Sophie Kim, the chief engineer, wants you to develop a project network plan to meet
this requirement. She has gathered the activity time estimates and their dependencies shown here.
Description
Survey
Soils report
C
Traffic design
D
Lot layout
E Approve design
Illumination
G Drainage
H
Landscape
I
Signage
J
Bid proposal
ID
A
B
The project is expected to take
The critical path is:
Early start for Activity E is:
Late finish for Activity F is:
Slack for Activity C is:
Predecessor
None
A
A
A
B, C, D
E
E
E
E
F, G, H, I
Time
(days)
13
22
21
a
9
74
20
20
22
17
15
12
days.
day(s).
arrow_forward
The table below contains data for the installation of new equipment in a manufacturing process a
Excello Corporation. Your company is responsible for the installation project. Indirect costs are
$10,000 per week, and a penalty cost of $9,000 per week will be incurred by your company for
every week the project is delayed beyond week12.
Activity Immediate Predecessor(s)
ABCDEFG
long dash-
long dash-
ABCDEFG
A
B
C
D, E
E
Normal Time Crash Time Normal Cost Crash Cost
(weeks)
(weeks)
($)
($)
1
14,000
2
3,000
1
40,000
3
22,000
1
8,000
4
13,000
2
16,000
3234
1
6
63
7,000
3,000
12,000
12,000
8,000
5,000
9,000
a. What is the shortest time duration for this project regardless of cost?
(Enter your response as a whole number.)
b. What is the minimum total cost associated with completing the project in 12
weeks?
C. What is the total time of the minimum cost schedule? (enter your response as whole
numbers). The total project's duration according to minimum cost schedule is?
The minimum cost schedule…
arrow_forward
1 Cara's clients, Emily and Dave, have just had a baby and she would like to do something nice for them. She signs them up for a baby registry that sends them a small gift.
Emily and Dave will be sent information and service lists that are geared toward helping new parents. She provided their names, address and phone numbers so that they will
not miss any of the activities provided in the package. Has Cara dealt with her clients appropriately?
NUYLOTNQhObm1bEVKUTO90
a0 Cara did not protect her clients' privacy when she shared their personal information with the baby registry.
O Cara should not make this a regular practice. Her clients will begin to expect gifts and she will not be able to sustain this.
CO Cara should have set up an appointment to re-evaluate her clients' needs now that they have had a baby.
40 Cara's gift is very thoughtful and will help to build a relationship with her clients.
NUTYks10TNRUQ2h0bmkbEVKUTO90
arrow_forward
Kim-Jae is a sales associate who receives
escrow funds on Monday. She gives them to her
broker on Tuesday.
If her broker deposits the funds on the following
Monday, did she meet the required timeline?
Yes, the broker deposited the funds within the
correct time frame.
No, the broker should have deposited the funds
by Thursday.
No, the broker should have deposited the funds
by Wednesday.
No, the broker should have deposited the funds
by Friday.
arrow_forward
Suppose that a task in a project has the following time estimates:
to=optimistic completion time=9 weeks
tm=most likely completion time=17 weeks
tp=pessimistic completion time=21 weeks
Compute the expected task completion time.
The expected task completion time is _________ weeks. (Enter your response rounded to one decimal place.)
arrow_forward
A mortgage service office has the following four activities involved in approving a loan application. Note that a working day is 8 hours and there are 60 minutes in one hour.
Activity
Time (minutes)
A. Property survey
24
B. Credit report
19
C. Title search
18
D. Final decision
20
The office has three employees, activities A, B and C are combined together and assigned to two employees, while the other employee is responsible for the last activity D. Under this setting, what would be the maximum number of loan applications the office can process per day?
Numbers only, keep three decimals if not exact, either round up or down is ok
arrow_forward
Draw the network diagram for the whole project (with AoN Activity on Node)
x=optimistic time
y=pessimistic time
m=probable time
arrow_forward
What feature of manufacturing planning and control systems operates under the premise that the planned work input to a workcenter should never exceed the planned work output?
arrow_forward
A Work Breakdown Structure (WBS) identifies deliverables, activities, and tasks. Which statement describes a task?
arrow_forward
Ed is planning to build a treehouse as a present for his son's upcoming 10th birthday. The
details for each task are as follows:
DE F G
AD C,E F
12
Task
A
B
Preceding Task
Duration (day) | 12
A
B
10
12
5
Cost (RM)
50 140 120 60 70
80
60
(a) Obtain the following:
• The number of days it will take for Ed to finish building the treehouse.
• Which tasks are cannot be delayed at all without delaying the whole project.
• The total cost of building the treehouse.
(b) Due to illness, Ed has to begin building the treehouse later than planned. He reckons that
he must reduce the build duration by 3 days to complete the treehouse by his son's birthday.
He has determined the crash cost and crash time for each task as follows:
Task
А В С
DE F G
Crash Time (day) | 12 8
9
8 10 5
6
Crash Cost (RM) | 50 170 180 70 95 80 60
Obtain the following:
• All tasks that are crashed and by how much.
• The new total cost for building the treehouse.
arrow_forward
Baha is a professional Chemical Engineer. He has been appointed as the department manager for an upcoming large chemical process plant that will be designed and constructed by the organization that he is currently attached to. Baha's responsibilities will include organizing the process unit staff and overseeing the project designers' sketch plans to ensure that the new plant will be designed safely, operable and maintainable. After the construction, he will then be responsible to start up the plant. From experience, Baha noted that a new type of valve sold by a newer supplier could be used in place of more common gate valves sold by established suppliers. In any case, the new valve was less expensive and often gave a tighter shut-off than the current gate valve used by his organization. Thus, Baha convinced the project designers to add more of these new valves to the design of the process unit. His decision improved safety because more flows could be shut off instantaneously in an…
arrow_forward
A Company wants to execute a project within 95 weeks. This project includes 10 activities
(labeled A, B, ..., J), where their precedence relationships are shown in the following table:
Predecessor
Normal
Crash
Normal Cost
Crash Cost
Activity
Activity
Time(weeks) Time(weeks) (in million S) (in million S)
A
32
28
160
180
В
28
25
125
146
C
A
36
31
170
210
D
B
16
13
60
72
E
32
27
135
160
B
54
47
215
257
D
17
15
90
96
H
E,G
20
17
120
132
E,G
34
30
190
226
F.C
18
16
80
84
a) Draw the project network according to the previous table.
(b)Find all possible paths and the corresponding lengths to finish the project.
(c) Which is the critical path and what is its length?
(d) Determine the least expensive way to crash activities to reduce overall duration to 95
weeks using Marginal cost analysis.
arrow_forward
Analyze which type of project termination is this:i. Completing a bridge constructionii. Completing an extra building construction of a collegeiii. Opening a new department of an universityiv. Stopping a project due to lack of budget
arrow_forward
What are the benefits of using flowcharts as part of the requirement model in project management.
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you
BUSN 11 Introduction to Business Student Edition
Business
ISBN:9781337407137
Author:Kelly
Publisher:Cengage Learning
Essentials of Business Communication (MindTap Cou...
Business
ISBN:9781337386494
Author:Mary Ellen Guffey, Dana Loewy
Publisher:Cengage Learning
Accounting Information Systems (14th Edition)
Business
ISBN:9780134474021
Author:Marshall B. Romney, Paul J. Steinbart
Publisher:PEARSON
International Business: Competing in the Global M...
Business
ISBN:9781259929441
Author:Charles W. L. Hill Dr, G. Tomas M. Hult
Publisher:McGraw-Hill Education
Related Questions
- You have been hired by a website design, production, and hosting company whose new animated website designs are attracting a lot of attention and many customers. Currently employees are organized into different functions such as hardware, software design, graphic art, and website hosting, as well as functions such as marketing and human resources. Each function takes its turn to work on a new project from initial customer request to final online website hosting. The problem the company is experiencing is that it typically takes one year from the initial idea stage to the time a website is up and running: the company wants to shorten this time by half to protect and expand its market niche. In talking to other managers, you discover that they believe the company's current functional structure is the source of the problem-it is not allowing employees to develop websites fast enough to satisfy customers' demands. They want you to design a better structure. Discuss how you can improve the…arrow_forwardFlorida Southwestern State College has decided to implement a new registration system that will allow students to register online as well as in person. As an IT manager, you decide to set up a JAD session to help define the requirements for a new system. The FSW organization is fairly typical, with an administrative staff that includes a registrar, student support and service team, a business office, an IT group, and a number of academic departments. Using this information, you start work on a plan to carry out the JAD session. Who would you invite to the session, and why? What would be your agenda for the session, and what would take place at each stage of the session?arrow_forwardIn network analysis, the process of calculating LS and LF A. Is sufficient for identifying the critical path B. Cannot be done until slack time is first determined C. Requires only a backward pass through the network D. Requires only a forward pass through the networkarrow_forward
- Used : Call center optimization as project , please give Citation if possible are required to identify and select a project that you have worked on, whether as a project manager or project team member. If you have not worked on a project before or you are unable to select a suitable project based on your work experiences, you should select a project that you know about and have sufficient access to the project’s information. Remember, the project that you select (the case) should have already been completed/finished, implemented, or executed. If you decide to select a project outside of your work experiences, there are several completed projects in your local community, your country, the region, or internationally that you may be able to use as a case for this assignment. There are no restrictions on the type of project that you select or decide to work with, however please be deliberate in your selection or when choosing a project to work with. You should avoid selecting a project…arrow_forwardThe table below contains data for the installation of new equipment in a manufacturing process at Excello Corporation. Your company is responsible for the installation project. Indirect costs are $12,000 per week, and a penalty cost of $6,000 per week will be incurred by your company for every week the project is delayed beyond week 12. Activity A B с D E F G Immediate Predecessor(s) AB Activity A B с D A C D, E E Normal Time Crash Time (weeks) (weeks) 3 1 2 2 1 3 4 1 6 3 Time according to schedule (weeks) 1 a. What is the shortest time duration for this project regardless of cost? The shortest project duration regardless of cost is 9 weeks. (Enter your response as a whole number.) b. What is the minimum total cost associated with completing the project in 12 weeks? The minimum total cost to complete the project in 12 weeks is $ 203500. (Enter your response as a whole number.) c. What is the total time of the minimum-cost schedule? (Enter your responses as whole numbers.) The total…arrow_forwardWilliam, a project manager, has a workload of 25,000 hours that needs to be completed in 30 weeks. He has a team of 20 people who work five 8-hour days per week. He notices that in the 30-week period, there are three holidays and 6 members have each requested 8 days off. Given this information, William is _____ short of completing his workload. Question options: 23,136 hours 1,864 hours 480 hours 1,480 hours 384 hoursarrow_forward
- John, Jack and Jill are project managers for Jusco Company. All three of them lead their own team, with two supervisors working under them. John’s team has 10 members, Jack has 8 members in his team and Jill has 11 members under his care. Both John and Jack completed their projects on time with the same amount of allocated budgets from top managers. But Jill didn’t manage to complete the project on time this time round. (i) Assuming all three projects have the same scale in terms of size, quality,and complexity, what can we conclude about the effectiveness and efficiency of these three project managers based on the informationabove? Justify your answers PLEASE PROVIDE CLEAR EXPLANATION THANK YOU , THIS TOPIC IS UNDER EVOLUTION OF FUNDAMENTAL MANAGEMENT THEORIESarrow_forwardA large Southeast city is requesting federal funding for a park-and-ride project. One of the requirements in the request application is a network plan for the design phase of the project. Sophie Kim, the chief engineer, wants you to develop a project network plan to meet this requirement. She has gathered the activity time estimates and their dependencies shown here. ID Description A Survey B Soils report с Traffic design D Lot layout E Approve design F G Drainage H Landscape I Signage J Illumination Bid proposal The project is expected to take The critical path is: Early start for Activity E is: Late finish for Activity F is: Slack for Activity C is: Predecessor None A A A B, C, D E E E E F, G, H, I Time (days) 9 22 25 6 76 20 24 24 25 9 days. day(s).arrow_forwardIn project management, CPM is an activity-oriented approach. Select one: O True O Falsearrow_forward
- How long it will take for each activity on the network chart is all but one of the following. Estimated duration The elapsed time that will be required Equal to the early start O Expressed in the same time units - days, hours, months, yearsarrow_forwardwhen discussing processes related to Project Execution, the ISO 10006 stabdard splits this category into different project groups. Which of the following is not one of these subcategories? a. Human resource-related processes b. Procurement processes c. Time related processes d. risk-related processarrow_forwardA network diagram's ability to use probability estimates in determining critical paths and deadlines. TRUE or FALSE?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- BUSN 11 Introduction to Business Student EditionBusinessISBN:9781337407137Author:KellyPublisher:Cengage LearningEssentials of Business Communication (MindTap Cou...BusinessISBN:9781337386494Author:Mary Ellen Guffey, Dana LoewyPublisher:Cengage LearningAccounting Information Systems (14th Edition)BusinessISBN:9780134474021Author:Marshall B. Romney, Paul J. SteinbartPublisher:PEARSON
- International Business: Competing in the Global M...BusinessISBN:9781259929441Author:Charles W. L. Hill Dr, G. Tomas M. HultPublisher:McGraw-Hill Education
BUSN 11 Introduction to Business Student Edition
Business
ISBN:9781337407137
Author:Kelly
Publisher:Cengage Learning
Essentials of Business Communication (MindTap Cou...
Business
ISBN:9781337386494
Author:Mary Ellen Guffey, Dana Loewy
Publisher:Cengage Learning
Accounting Information Systems (14th Edition)
Business
ISBN:9780134474021
Author:Marshall B. Romney, Paul J. Steinbart
Publisher:PEARSON
International Business: Competing in the Global M...
Business
ISBN:9781259929441
Author:Charles W. L. Hill Dr, G. Tomas M. Hult
Publisher:McGraw-Hill Education